Woodstock · Parks, recreation & culture
The City’s November 6 notice schedules the Southside Aquatic Centre front-entrance closure for November 9 and directs patrons to the north side entrance until work is complete. No reopening date is supplied. This entrance notice does not establish a pool-wide closure or current conditions before November 9.
Woodstock · Southside Aquatic Centre
Front-entrance closure scheduled November 9; north side entrance- 2026 allocation
- Not established
- Next target
- 2026-11-09 · Scheduled front-entrance closure
- Latest update
- 2026-11-06 · Newer entrance notice schedules November 9
Open project →Blandford-Blenheim · Roads & bridges
The September 24 notice set a weather-dependent October 10 paving target. A November 7 source check did not establish later Phase 5 completion, inspection or current road access. June 17 adopted minutes record a $1,091,195.04 plus HST award to Armstrong Paving and Materials Group Ltd.; this is not final expenditure.
Blandford-Blenheim
Past paving target; current access and completion unverified- 2026 allocation
- Not established
- Named supplier
- Armstrong Paving Group
- Next target
- No next date listed
- Latest update
- 2026-11-04 · Term review provides broader reconstruction context
Open project →Norwich · Roads & bridges
October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The earlier report’s 2027 surface-treatment forecast remains a dated plan.
Norwich
Asphalt award in adopted minutes; execution and completion unverified- Original budget
- $1,797,160
- Named suppliers
- South Brant Excavating Inc.; Walker Construction Limited; Permanent Paving Ltd.
- Next target
- No next date listed
- Latest update
- 2026-11-03 · October 13 minutes adopted
Open project →Norwich · Roads & bridges
October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The earlier report’s 2027 surface-treatment forecast remains a dated plan.
Norwich
Related Substation asphalt award in adopted minutes; Beaconsfield completion unverified- Revised budget
- $771,000
- Named suppliers
- South Brant Excavating Inc.; Walker Construction Limited; Permanent Paving Ltd.
- Next target
- No next date listed
- Latest update
- 2026-11-03 · October 13 minutes adopted
Open project →South-West Oxford · Housing & community services
October 20 draft minutes record resolution 8 authorizing $1,304,091 plus applicable HST for Early Works from the Working Capital Reserve and arrangements with Sierra General Contracting, subject to approvals. A November 3 staff follow-up says Sierra was notified. Minutes adoption, an executed contract and payment are not established; this is not approval or completion of the whole facility.
South-West Oxford
Early Works authorized in draft minutes; full facility separate- Original budget
- $12,000,000
- Next target
- 2028-01-01 · Anticipated childcare occupancy in proposed MOU
- Latest update
- 2026-11-03 · Staff report says Sierra was notified
Open project →Norwich · Buildings & facilities
Council approved the property proposal in principle on September 8, 2026 and requested a working group and a fully costed plan and design to return in Q1 2027 for a final decision. A final construction budget, completed property transaction or open new facility is not established by the cited records.
Norwich
Approved in principle; costed plan requested- 2026 allocation
- Not established
- Next target
- 2027 · Q1 2027: costed plan and design requested
- Latest update
- 2026-11-03 · October 13 minutes adopted
Open project →Norwich · Parks, recreation & culture
October 13 adopted minutes record reconsideration of the September 8 motion, defeat of the grant application and preliminary-design authority of up to $60,000, and receipt of CAO2026-29 for information. This does not establish cancellation of the whole pool-replacement project. The October 13 minutes were adopted November 3 under resolution 2. Adoption confirms the written record; it does not add a construction, payment or completion decision.
Norwich
Grant/design motion lost in adopted minutes; whole project separate- Historical September 8 consulting ceiling
- $60,000
- Next target
- No next date listed
- Latest update
- 2026-11-03 · October 13 minutes adopted
Open project →Norwich · Roads & bridges
October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The earlier report’s 2027 surface-treatment forecast remains a dated plan.
Norwich
Asphalt award in adopted minutes; execution and completion unverified- Revised budget
- $1,026,100
- Named suppliers
- South Brant Excavating Inc.; Walker Construction Limited; Permanent Paving Ltd.
- Next target
- No next date listed
- Latest update
- 2026-11-03 · October 13 minutes adopted
Open project →Zorra · Roads & bridges
Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.
Zorra
Complete per staff report; road reopened- 2026 allocation
- $172,616
- Named suppliers
- Brantco Construction; Claussen Farms Custom Farming Inc.
- Next target
- No next date listed
- Latest update
- 2026-10-30 · Road 92 and 25th Line paving complete
Open project →Zorra · Roads & bridges
Report 2026-112 says Bridge 140 work on 33rd Line between Road 96 and Road 98 started October 5 and was completed with the road reopened within two weeks. Prepared for the November 4 council meeting; no exact reopening day is stated.
Zorra
Complete per staff report; road reopened- Revised budget
- $224,072.69
- Named supplier
- AJN Builders Inc.
- Next target
- No next date listed
- Latest update
- 2026-10-30 · Bridge 140 work complete; 33rd Line reopened
Open project →Zorra · Roads & bridges
Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.
Zorra · South-West Oxford
Complete per staff report; road reopened- 2026 allocation
- $1,322,880
- Named supplier
- Weathertech Restoration Services Inc.
- Next target
- No next date listed
- Latest update
- 2026-10-30 · Road 92 and 25th Line paving complete
Open project →Tillsonburg · Roads & bridges
Dufferin Construction is scheduled to mill and resurface Hardy Avenue from the Community Centre access road to Sanders Street, tentatively during the week of November 9 through November 27. Portions will close to public traffic. The Community Centre access intersection remains open; vehicle access to the Lions Den and South Pool entrances will be unavailable during the closure. Weather-dependent schedule; not evidence work has started.
Tillsonburg
Scheduled; weather-dependent- 2026 allocation
- Not established
- Next target
- 2026-11-09 · Tentative start week, weather permitting
- Latest update
- 2026-10-30 · Hardy Avenue resurfacing planned for November
Open project →Ingersoll · Parks, recreation & culture
A professional advisor who will guide the Town through the planning and execution of the MURC A live browser visit returns Page Not Found. Search retrieval still exposes a cached December 2025 project page. That old timeline or on-budget badge is not current project progress.
Ingersoll
Current project progress unverified; official page unavailable- Revised budget
- $290,000
- Named supplier
- Interkom Inc.
- Next target
- No next date listed
- Latest update
- 2026-10-30 · MURC source link remains unavailable
Open project →Ingersoll · Roads & bridges
The lands designated through the Town of Ingersoll Secondary Plan for the new Multi-Use Recreation Facility are currently unserviced. The Secondary Plan indicated that servicing would be enabled through the extension of water and sanitary sewers from Walker Road. Through preliminary investigation it was determined that sufficient grade is not available to enable this servicing scheme, and instead, servicing is to be extended from Harris Street. To service the lands with sanitary sewer from Harris Street via gravity feed, approximately 3 m± of fill is required in order to remove the existing sag in the road. This additional loading requires replacement of the existing culvert C 16 on Clark Road, initially slated for replacement in the 2026-2030 time horizon. Thus the total scope of work on Clark Road to service the MURC lands includes: Water and Sanitary Servicing, Storm Sewers, addition of 1 eastbound lane (total 3 lanes), sidewalks (or Multi-Use Trail), Streetlighting. A Class D (±20% accuracy) enabling works estimate was provided by Dillon Consulting amounting to $12,700,000. This estimate may reasonably be reduced to $8,500,000 though further design considerations relating to Hydraulic Conductivity of Halls Creek, and subsequent Geotechnical Investigation to confirm subgrade adequacy for structural footing design. Additional to this work will include the engineering design and contract administration estimated at 10% of construction value from the Class D estimate. A live browser visit returns Page Not Found. Search retrieval still exposes a cached December 2025 project page. That old timeline or on-budget badge is not current project progress.
Ingersoll
Current project progress unverified; official page unavailable- 2026 allocation
- $262,000
- Next target
- No next date listed
- Latest update
- 2026-10-30 · MURC source link remains unavailable
Open project →Ingersoll · Parks, recreation & culture
The Town-hosted January 2026 status report says the design-build contract with Ball Construction was signed following Council approval. The exact signing day and executed agreement were not reviewed. This dated report does not establish current construction progress or opening.
Ingersoll
Design-build contract reported signed; current construction progress unverified- Lifetime project budget
- $38,000,000
- Next target
- No next date listed
- Latest update
- 2026-10-30 · October 30 webpage availability check
Open project →Ingersoll · Parks, recreation & culture
Through completion of the Clark Road Urbanization and service extensions, water and sanitary sewer will be available to the designated MURC lands. Internal grading and servicing design will allow in-progress institutional development for a long-term care facility, new elementary school, and the MURC to be completed and leave a balance of 20±acres for residential development. The scope of work for the internal grading and servicing will include topsoil stripping for the impacted lands, earth cut and fill, water, sanitary and storm sewer construction, and was all road building, streetlighting and sidewalks constructed to the MURC facility. Grading works will allow the MURC to commence construction while Clark Road is being reconstructed. Servicing and internal road-building can take place following Clark Road reconstruction and before the MURC grand opening. A Class D (±20% accuracy) estimate was provided by Dillon Consulting amounting to a constructed value of $8,323,405. Additional to this work will include the engineering design and contract administration estimated at 10% of construction value from the Class D estimate. A live browser visit returns Page Not Found. Search retrieval still exposes a cached December 2025 project page. That old timeline or on-budget badge is not current project progress.
Ingersoll
Current project progress unverified; official page unavailable- 2026 allocation
- $8,424,000
- Next target
- No next date listed
- Latest update
- 2026-10-30 · MURC source link remains unavailable
Open project →Ingersoll · Parks, recreation & culture
The MURC project involves ongoing oversight and coordination and administration required to complete the MURC. A live browser visit returns Page Not Found. Search retrieval still exposes a cached December 2025 project page. That old timeline or on-budget badge is not current project progress.
Ingersoll
Current project progress unverified; official page unavailable- 2026 allocation
- $250,000
- Next target
- No next date listed
- Latest update
- 2026-10-30 · MURC source link remains unavailable
Open project →Zorra · Roads & bridges
Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.
Zorra
Complete per staff report; road reopened- 2026 allocation
- $426,798
- Named suppliers
- Brantco Construction; Claussen Farms Custom Farming Inc.
- Next target
- No next date listed
- Latest update
- 2026-10-30 · Road 92 and 25th Line paving complete
Open project →Zorra · Roads & bridges
Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.
Zorra
Complete per staff report; road reopened- 2026 allocation
- $426,798
- Named suppliers
- Brantco Construction; Claussen Farms Custom Farming Inc.
- Next target
- No next date listed
- Latest update
- 2026-10-30 · Road 92 and 25th Line paving complete
Open project →County · Roads & bridges
Culvert replacements on parts of Oxford Roads 2, 10, 13, 22, 55 and 59, plus a left-turn lane at Oxford Road 2 and 35th Line.
Blandford-Blenheim · East Zorra-Tavistock · South-West Oxford · Zorra
Named OR2/OR22/OR59 sections complete; OR10 scheduled mid-October–end-November- 2026 allocation
- Not established
- Named supplier
- Steve Smith Construction Corporation
- Next target
- 2026-10 · Oxford Road 10 start target
- Latest update
- 2026-10-29 · Section-specific status reviewed
Open project →County · Other projects
Clean biosolids from the County wastewater treatment lagoon.
Norwich
Enviroland named; $809,080 contract value published; completion unverified- 2026 allocation
- $1,400,000
- Named supplier
- Enviroland Services Inc.
- Next target
- No next date listed
- Latest update
- 2026-10-29 · Published contract value verified
Open project →County · Roads & bridges
The published update schedules a November winter pause, reopening with an all-way stop over winter and resumption in early 2027. The notice gives a planned reopening, not confirmation that the road reopened.
Ingersoll
November winter pause planned; work resumes early 2027- 2026 allocation
- Not established
- Named supplier
- J-AAR Civil Infrastructures Limited
- Next target
- 2026-11 · Planned winter pause and reopening
- Latest update
- 2026-10-22 · Winter-pause schedule published
Open project →East Zorra-Tavistock · Roads & bridges
Posted October 21 written minutes record a carried motion accepting Vandenberk Construction Inc.’s bid of $373,454.20 exclusive of taxes, with contingency if needed, and authorizing the CAO and Treasurer to sign. The staff report specifies $50,000 contingency; the motion does not repeat that amount. Formal minutes adoption, an executed agreement and completion have not been verified.
East Zorra-Tavistock
Bid acceptance recorded in written minutes; adoption unverified- 2026 allocation
- $600,000
- Named supplier
- Vandenberk Construction
- Next target
- No next date listed
- Latest update
- 2026-10-21 · Written minutes record bid acceptance
Open project →County · Roads & bridges
The OR2/Dundas–OR12 intersection phase reopened October 21. Phase 2A of the wider reconstruction remains ongoing. The entire project is not complete.
Woodstock
Oxford Roads 2/12 intersection reopened; Phase 2A continues- 2026 allocation
- Not established
- Named supplier
- Network Sewer and Watermain Ltd
- Next target
- 2026-11 · Overall completion target
- Latest update
- 2026-10-21 · Phase 2B intersection complete and reopened
Open project →