More spending decisions (19)
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$1,950,000 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: Indwell Community Homes: 515 Main Street, Woodstock, 50-unit supportive housing — Capital
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$150,000 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: Indwell Community Homes: same development operating support — Operating
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$1,500,000 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: Tillsonburg Non-Profit: 288 Tilson Avenue, 30-unit affordable housing
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$2,486,643 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: OR19 Otterville Bridge 225536 superstructure replacement
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$1,704,929 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: Thornton Water Treatment Plant solar PV
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$2,554,908 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: 2026 county-wide culvert replacement and OR2/35th Line left-turn lane
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$5,495,286 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: OR2 Dundas reconstruction CPKC overhead railway to OR12 Mill Street
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$1,505,089 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: Green initiatives residential buildings: 16 George Norwich and 135 Carroll Ingersoll
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$4,953,246 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: OR35 Devonshire reconstruction Victoria to Knightsbridge
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$4,831,972 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: 2026 CIP/HMA resurfacing parts of OR8 and OR59
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$1,589,554 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: OR29 Innerkip Bridge 805907 rehabilitation
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$4,234,659 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: OR59 Church Street urbanization Burgessville
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$1,744,977 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: OR59 Norwich Bridge 773216 superstructure replacement
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – <10% over budget
$1,537,648 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: Tillsonburg inlet trunk sanitary sewer replacement
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$1,394,730 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: Unit 742 Tractor Dozer; delivery scheduled 2027
Open the source record
- FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
- Source date
- 2026-08-12
- Date context
- Report dated August 12, 2026; publication and individual approval dates not established
- Event / reporting date
- 2026-08-12
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Evidence note
- 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.
2026-06-30 · Municipal council / official public record
forecast; report dated August 12
Consequence: FS2026-17 forecasts an overall year-end operating deficit of $1,338,050 from June 30 information: general levy deficit $1,121,930; library surplus $10,155; water/wastewater surplus $284,380; programme-reserve deficit $510,655.
Open the source record
- Q2 operating forecast: $1.338 million deficit
- Source date
- 2026-06-30
- Date context
- Financial period ending
- Event / reporting date
- 2026-06-30
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Decision / approval status
- forecast; report dated August 12
- Evidence note
- Primary-source body reviewed in the October 30 audit Not final actuals or available cash. The report plans a November update for September 30. Financial period ending
2026-04-22 · Oxford County Council
Official County timeline confirms Council approved the purchase; the acquisition closed May 29.
$4,550,000 · Property acquisition price; excludes renovation and operation
Consequence: County ownership enables the proposed support centre; capital renovation and service operation require their own delivery evidence.
Open the source record
- New Homelessness Support Centre — purchase, costs and timeline
- Publisher
- Oxford County
- Published
- 2026-06-01
- Event / reporting date
- 2026-05-29
- Reporting period
- 2025 authorization; 2026 acquisition; proposed delivery through 2028
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- Official confirmation of purchase approval and completed acquisition; later delivery dates estimated
- Passage / page
- Timeline; Background — Process and Costs
- Evidence notes
- Acquisition, estimated capital costs and annual operating costs have distinct scopes. The centre and HART Hub are separate projects.
2025-12-10 · Oxford County Council
County approval confirmed by the official budget hub; the detailed approved document is the financial source.
$406,890,915 · Detailed document total of operating plus financed capital; the budget hub headline conflicts.
Consequence: General levy: $96,680,548; library levy: $6,297,357; court security levy: $61,266. Water and wastewater are supported by utility rates.
2 source records
- Business plans and budgets
- Publisher
- Oxford County
- Reporting period
- 2026
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- official approval summary
- Passage / page
- 2026 approved budget section
- Evidence notes
- The hub reports $406.1 million total and $278.2 million operating, while the approved detailed PDF reports $406,890,915 and $279,035,275.
- Approved 2026 Business Plan and Budget
- Publisher
- Oxford County
- Published
- 2026-01-14
- Event / reporting date
- 2025-12-10
- Reporting period
- 2026
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- approved
- Passage / page
- PDF page 58; printed page 58
- Evidence notes
- File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.
2025-12-10 · Oxford County Council
County confirms Council authorized staff to submit an offer, conditional on funding and administrative requirements.
$5,000,000 · Maximum conditional offer authorization; not final price or total project budget
Consequence: County ownership enables the proposed support centre; capital renovation and service operation require their own delivery evidence.
Open the source record
- New Homelessness Support Centre — purchase, costs and timeline
- Publisher
- Oxford County
- Published
- 2026-06-01
- Event / reporting date
- 2026-05-29
- Reporting period
- 2025 authorization; 2026 acquisition; proposed delivery through 2028
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- Official confirmation of purchase approval and completed acquisition; later delivery dates estimated
- Passage / page
- Timeline; Background — Process and Costs
- Evidence notes
- Acquisition, estimated capital costs and annual operating costs have distinct scopes. The centre and HART Hub are separate projects.