2025-12-10 · Oxford County Council
808 Dundas conditional offer authorized
County confirms Council authorized staff to submit an offer, conditional on funding and administrative requirements.
$5,000,000 · Maximum conditional offer authorization; not final price or total project budget
Consequence: County ownership enables the proposed support centre; capital renovation and service operation require their own delivery evidence.
Open the source record
- New Homelessness Support Centre — purchase, costs and timeline Timeline; Background — Process and Costs
Oxford County · Published 2026-06-01 · Event/reporting date 2026-05-29 · 2025 authorization; 2026 acquisition; proposed delivery through 2028
Official confirmation of purchase approval and completed acquisition; later delivery dates estimated · Primary record verified · Acquisition, estimated capital costs and annual operating costs have distinct scopes. The centre and HART Hub are separate projects.