Oxford County · Project
Beaconsfield Rd. (033A) Grvl Conv. - Per OP 2026-12 (Budget Ammend.)
October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The earlier report’s 2027 surface-treatment forecast remains a dated plan.
Beaconsfield Rd. (033A) Grvl Conv. - Per OP 2026-12 (Budget Ammend.)
Budget approval
Township authority; departmental delivery subject to report-specific approvals.
Sources for this record: [8]
Delivery lead
Township staff oversee road-base reuse during reconstruction; Mayor and Clerk execute authorized agreements.
Reported spending does not establish physical completion.
Sources for this record: [1]
OP 2026-32 forecasts base work in mid-October and 800 metres of asphalt east from Highway 59 in mid-November. Double surface treatment is deferred to 2027 after the 2026 seasonal cutoff. This dated forecast is not October 29 completion evidence.
Sources for this record: [4]
Historical October 29-30 review: Draft minutes record a formal tender waiver and award to Permanent Paving Ltd. for $183,741 plus non-refundable HST. Oxford Cattle Company is to cover the incremental cost above double surface treatment. Draft minutes pending adoption; award is not evidence of completed paving. No new completion date verified.
Sources for this record: [6]
October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established.
Sources for this record: [7]
The October 13 minutes were adopted November 3 under resolution 2. Adoption confirms the written record; it does not add a construction, payment or completion decision.
Sources for this record: [7]
PW-2026-03 · awarded
South Brant Excavating Inc. · 2026-07-14
Bid before tax; Council award as published includes Township non-refundable HST
Award amount is authorization recorded by Council, not proof of final contract expenditure. Portal search bid $1,563,820.56 is consistent with 13% tax on the report bid, but separately published Council award is the authoritative award figure. Do not derive a different award from tax arithmetic.
Sources for this record: [2] [3]
Open procurement recordJoint County Tender2026-08 — Norwich portion · awarded
Walker Construction Limited · 2026-07-14
Bid before tax; published award includes non-refundable HST
Award amount is authorization recorded by Council, not proof of final contract expenditure.
Sources for this record: [2] [3]
Open procurement recordOP2026-32 / Resolution 17 · Award in adopted minutes; execution and payment unverified
Permanent Paving Ltd. · 2026-10-13
$183,741 plus non-refundable HST; Township $66,507 plus HST; Oxford Cattle $117,234 plus HST
October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The October 13 minutes were adopted November 3 under resolution 2. Adoption confirms the written record; it does not add a construction, payment or completion decision.
Sources for this record: [4] [5] [6] [7]
Open procurement record2026-07-14 · Resolution21
Carried
$1,837,191 · sum of the two approved award amounts; excludes estimated asphalt component
Consequence: Original estimate $1,797,160; staff forecast $1,922,046. Funding table leaves $197,710 to yearend recommendation.
2026-10-13 · Resolution 17
Resolution 17 carried in adopted minutes
$183,741 · Award plus the Township’s non-refundable portion of HST, not payment or an executed final contract.
Consequence: October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established.
2026-03-24 · Resolution 6
Carried
Consequence: Authorized 2026 Beaconsfield and Substation gravel conversions. Zenda Line, Quaker to Evergreen, was directed into the draft 2027 budget, not approved for construction.
Sources for this record: [9]
Completion not confirmed.
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: norwich-fs2026-15-capital
Source ID: norwich-op2026-25
Source ID: norwich-minutes-07-14
Source ID: norwich-oct13-packet-2026
Source ID: norwich-oct13-captions-2026
Source ID: oct30-nor-substation-award
Source ID: nov7-norwich-road-adopted-minutes
Source ID: norwich-minutes-01-13
Source ID: norwich-oct29-minutes-2026-03-24
Your taxes called. They’d like a receipt.
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.
Detailed approved budget ↗ · County budget hub ↗
Open the full money explanation