Award / contract$439,196Walker Construction Limited · 2026-07-14
Recorded paymentsAmount not publishedNo payment amounts attached
Bid before tax; published award includes non-refundable HST · Bid, award and payment are separate measures. No price-change calculation is inferred between them.
Award amount is authorization recorded by Council, not proof of final contract expenditure.
October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The earlier report’s 2027 surface-treatment forecast remains a dated plan.
Norwich
Asphalt award in adopted minutes; execution and completion unverified
Revised budget
$1,026,100
Named suppliers
South Brant Excavating Inc.; Walker Construction Limited; Permanent Paving Ltd.
October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The earlier report’s 2027 surface-treatment forecast remains a dated plan.
Norwich
Related Substation asphalt award in adopted minutes; Beaconsfield completion unverified
Revised budget
$771,000
Named suppliers
South Brant Excavating Inc.; Walker Construction Limited; Permanent Paving Ltd.
October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The earlier report’s 2027 surface-treatment forecast remains a dated plan.
Norwich
Asphalt award in adopted minutes; execution and completion unverified
Original budget
$1,797,160
Named suppliers
South Brant Excavating Inc.; Walker Construction Limited; Permanent Paving Ltd.
Next target
No next date listed
Latest update
2026-11-03 · October 13 minutes adopted
Open project →
What still needs an answer
What is the executed contract value, any changes, and final accepted cost?
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.
Why are there different County totals?
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.