October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The earlier report’s 2027 surface-treatment forecast remains a dated plan.
Norwich
Asphalt award in adopted minutes; execution and completion unverified
Revised budget
$1,026,100
Named suppliers
South Brant Excavating Inc.; Walker Construction Limited; Permanent Paving Ltd.
October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The earlier report’s 2027 surface-treatment forecast remains a dated plan.
Norwich
Related Substation asphalt award in adopted minutes; Beaconsfield completion unverified
Revised budget
$771,000
Named suppliers
South Brant Excavating Inc.; Walker Construction Limited; Permanent Paving Ltd.
October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The earlier report’s 2027 surface-treatment forecast remains a dated plan.
Norwich
Asphalt award in adopted minutes; execution and completion unverified
Original budget
$1,797,160
Named suppliers
South Brant Excavating Inc.; Walker Construction Limited; Permanent Paving Ltd.
Next target
No next date listed
Latest update
2026-11-03 · October 13 minutes adopted
Open project →