Bridge 640, 25th Line, Meathrell Creek

Money & projects Explore sections

At a glance

Location
Zorra, South-West Oxford
Responsible authority
Zorra
Current stage
Complete per staff report; road reopenedAs of 2026-07-24
2026 allocation
$1,322,880
Next target
No next date listed
Named supplier
Weathertech Restoration Services Inc. See contract details

Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.

Bridge 640, 25th Line, Meathrell Creek

Who approves and delivers this project?

Budget authority

Township Council

Approves annual allocation; delivery and contract authority must be traced separately.

Money

Project money

Annual allocation

2026 allocation
$1,322,880
2026 annual capital allocation; not a final contract or lifetime cost

Latest spending total not published here.

CAD · Source budget basis; HST treatment not separately stated · 2026 annual capital allocation; not a final contract or lifetime cost

Where the funding comes from

$1,322,880Listed funding total

  1. ReservesZorra share financing
    $378,87228.6% of listed total
  2. $282,56821.4% of listed total
  3. South-West Oxford sharePlanned 50% partner contribution
    $661,44050% of listed total
Listed funding adds to the 2026 allocation amount. CAD.

Timeline

  1. work

    Construction began

  2. work

    Bridge work started

  3. completion

    Bridge rehabilitation completed

  4. Target date passed; milestone status needs a verified update

    Original completion target

    Target in Q1 update; no completion certificate reviewed.

  5. Target date passed; milestone status needs a verified update

    Original bridge-work completion target

  6. Target date passed; milestone status needs a verified update

    Conditional road reopening target

    Dependent on paving/shouldering; not evidence the road opened that day.

  7. completion

    Road 92 and 25th Line paving complete

    Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.

Contracts

2026-02 · Award explicitly reported by staff

Meathrell Creek bridge replacement

Weathertech Restoration Services Inc.

Published bid
Not established
Published award / contract value
$775,600.80
Unit price
Not established

Excludes HST; after-rebate $789,251.37

Award is not final payment; actual quantity, changes and final account not supplied in this update.

Open procurement record

Decisions

No separate decision record is linked. Approval details may appear in the timeline or source documents.

Outcomes

Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24.

Questions

  • What is the latest committed cost, spending to date and completion milestone?
Scope & interpretation notes
  • Joint bridge funded 50/50 with South-West Oxford; Zorra invoices partner. Gross contract is not Zorra-only net cost.

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. 2026 final operating budget and ten-year capital plan, report 2025-130

    Source ID: zorra-budget2026

    Publisher
    Township of Zorra
    Published
    2025-12-03
    Event / reporting date
    2025-12-03
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    adopted
    Passage / page
    PDF pp. 1–95; account and project pages retained in rows
    Evidence notes
    Final council-approved schedules. 2025 comparatives restated; 2024 not restated. Capital is excluded from the 2026 operating schedule.

    Open in source library

  2. Report 2026-033: Roads Division Q1 update

    Source ID: zorra-roads-q1

    Publisher
    Township of Zorra
    Published
    2026-05-06
    Event / reporting date
    2026-05-06
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published
    Passage / page
    PDF pp. 1–3; tender results and project update
    Evidence notes
    Report header says April 15, approval April 30; May 6 Council agenda receives it. Event date uses Council receipt; inconsistent header retained in note.

    Open in source library

  3. Report 2026-075: Roads Division quarterly update

    Source ID: zorra-v7-q2-roads

    Publisher
    Township of Zorra
    Published
    2026-08-13
    Event / reporting date
    2026-08-13
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published
    Passage / page
    pp. 1–5
    Evidence notes
    Report includes July events despite Q2 label; tax basis is amount-specific.

    Open in source library

  4. Report 2026-084: Bridge 140 and Bridge Culvert 70 tender results

    Source ID: zorra-v7-bridge140-award-report

    Publisher
    Township of Zorra
    Published
    2026-08-13
    Event / reporting date
    2026-08-13
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published
    Passage / page
    pp. 1–2; paired with carried resolution 07-08-2026
    Evidence notes
    Bridge 140 amount includes contingency and non-rebatable HST. Do not confuse joint bid $258,664 before HST with Bridge 140 award authorization $224,072.69 after HST rebate.

    Open in source library

  5. Road 92 and 25th Line paving complete

    Source ID: oct30-z-roads

    Source date
    2026-09
    Event / reporting date
    2026-09
    Reviewed
    2026-10-30
    Retrieved
    2026-10-30
    Evidence status
    verified_primary
    Decision / approval status
    completed per staff report
    Passage / page
    Page 3 paving and Bridge 640 sections
    Evidence note
    Primary-source body reviewed in the October 30 audit Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

Why are there different County totals?

The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.

Detailed approved budget ↗ · County budget hub ↗

Open the full money explanation