Project engineer
Oxford County Public Works
County project page names Michael Holstenson as project engineer and Jesse Keith as Supervisor of Engineering Services.
Sources for this record: [2]
Eight places. One shared future.
Oxford County · Project
The latest published plan points to a winter pause, with more work in 2027. A scheduled reopening is not confirmation the road is open.
Oxford County’s October 23 project update plans a November 2026 construction pause, with work restarting in early 2027. It does not confirm that the road has reopened. Continue following posted detours until the road and intersection reopen.
The project covers Oxford Road 9 (Hamilton Road/King Street West), from the CPKC railway west to the Town of Ingersoll boundary, including the intersection with Oxford Road 10 (Ingersoll Street South). The winter plan uses an all-way stop at that intersection.
Check signs and the current County notice before travelling. This summary is not live navigation and does not establish access to an individual property.
The 2027 plan includes surface asphalt and restoration. At the Roads 9/10 intersection, planned work includes new curb, sidewalk, traffic signals and street lighting, plus replacement asphalt. That newer plan replaces the earlier December 2026 completion expectation.
Keep three milestones separate: reopening for traffic, restarting construction and finishing the project. Evidence of one does not establish the other two. Look for a stated date, the affected section and remaining restrictions. Do not assume a road reopening also reopens nearby trails.
Read the latest official Oxford Road 9 project update
Check the County’s current construction notices
Official sources checked (UTC). These pages are visitor and project guides, not live condition reports.
Oxford Road 9: follow the $14.2 million bid into delivery
The published update schedules a November winter pause, reopening with an all-way stop over winter and resumption in early 2027. The notice gives a planned reopening, not confirmation that the road reopened.
Road, sanitary sewer, watermain, storm sewer, sidewalks, traffic signals, lighting, landscaping and restoration.
Project engineer
County project page names Michael Holstenson as project engineer and Jesse Keith as Supervisor of Engineering Services.
Sources for this record: [2]
Project cost not published in this record.
Latest spending total not published here.
Microtunnel sanitary sewer installation scheduled from November 2025 through March 2026.
Sources for this record: [1]
Full reconstruction and utility work scheduled March–December 2026. Historical schedule, superseded by the October 22 winter-pause notice.
Sources for this record: [1]
County announced a September 14 start week for the Oxford Roads 9 and 10 intersection stage, targeting November completion for that stage.
Sources for this record: [1]
November winter pause is planned, with roads reopening and an all-way stop for winter. Detours continue until the actual reopening. Work resumes in early 2027; surface asphalt and restoration are planned for 2027.
Sources for this record: [4]
The published update schedules a November winter pause, reopening with an all-way stop over winter and resumption in early 2027. The notice gives a planned reopening, not confirmation that the road reopened.
Sources for this record: [5]
Scheduled transition, not proof the roads were already open on October 29.
Sources for this record: [4]
December 2026 remains the published completion target; it is not an actual completion date. Historical schedule, superseded by the October 22 winter-pause notice.
Sources for this record: [1]
No exact restart or final completion day is established.
Sources for this record: [4]
TENDER-ENG-2025-587 · awardee named in annual register
J-AAR Civil Infrastructures Limited
The published bid does not establish the final executed contract value. Not established in annual register
2025 award connected to current 2026 work. The annual register names the awardee but leaves the contract value and award date unpublished.
Sources for this record: [3]
Open procurement recordNo separate decision record is linked. Approval details may appear in the timeline or source documents.
Completion not confirmed.
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: county-construction
Source ID: county-ingersoll-road9-page
Source ID: county-award-tender-eng-2025-587
Source ID: county-construction-road9-20261022
Source ID: oct30-or9
Your taxes called. They’d like a receipt.
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.
Detailed approved budget ↗ · County budget hub ↗
Open the full money explanation