The City’s November 6 notice schedules the Southside Aquatic Centre front-entrance closure for November 9 and directs patrons to the north side entrance until work is complete. No reopening date is supplied. This entrance notice does not establish a pool-wide closure or current conditions before November 9.
Universal changeroom addition and renovation, separate from roof replacement.
Universal changeroom closure scheduled from October 5
The notice offered men’s/women’s changerooms, limited pool-deck tents and front-desk assistance. Programs were expected to continue subject to unforeseen disruptions. Actual changeroom closure and reopening date are not independently verified.
The City reports water-clarity and chemical-feeding equipment problems. Construction alerts also warn of unavailable parking and reduced front-entrance accessibility. No disputed entrance-closure dates are asserted.
The City’s notice dated October 13 announces reopening October 14 at 6 a.m., following the water-clarity closure. Separate changeroom renovations are not confirmed complete.
The October 29 notice scheduled a November 3 front-entrance closure and directed patrons to the north side entrance. It does not establish whether that closure occurred.
The City’s November 6 notice schedules the Southside Aquatic Centre front-entrance closure for November 9 and directs patrons to the north side entrance until work is complete. No reopening date is supplied. This entrance notice does not establish a pool-wide closure or current conditions before November 9.
The November 6 notice directs patrons to the north side entrance during the scheduled front-entrance closure. This is a target, not confirmation that it occurred.
No separate decision record is linked. Approval details may appear in the timeline or source documents.
Outcomes
The November 6 notice does not confirm the earlier November 3 closure, a postponement, current November 7 entrance conditions or completed changeroom work. Pool-water closure/reopening notices concern a separate event.
Questions
What is the current approved cost and delivery date?
The universal changeroom addition is separate from the roof-replacement project. The October 29 and November 6 entrance notices both direct patrons to the north side entrance.
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Schedules a November 9 front-entrance closure and directs patrons to the north side entrance until work is complete. No reopening date, actual November 3 closure or November 7 access condition is established.
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.
Why are there different County totals?
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.