Oxford County · Project

Dundas Street reconstruction: phases and closures

Money & projects Explore sections
Oxford County project

At a glance

Location
Woodstock
Responsible authority
Oxford County
Current stage
Oxford Roads 2/12 intersection reopened; Phase 2A continuesAs of 2026-10-21
2026 allocation
Not established
Next target
2026-11 · Overall completion target
Named supplier
Network Sewer and Watermain Ltd See contract details

The OR2/Dundas–OR12 intersection phase reopened October 21. Phase 2A of the wider reconstruction remains ongoing. The entire project is not complete.

Oxford Road 2 reconstruction from west city limit to Mill Street, with utility and road improvements.

Project 930002

Who approves and delivers this project?

Expenditure approval

Oxford County Council

County capital budget authority; individual votes not inferred.

Asset owner and delivery lead

Oxford County Public Works

County project located within the local municipality; local council is not the County contract manager.

Money

Reported in-year approvals (1)

These amounts use the in-year approvals schedule's basis. They are not substituted for bidder prices, executed contract values, whole-project budgets or payments, or added to other project figures.

Contract Award – within budget

$5,495,286 · Report dated 2026-08-12 · Individual approval date not established

Not specified in inspected attachment; no inclusive/exclusive assumption

Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total Individual approval dates are not specified in the row Not specified in inspected attachment; no inclusive/exclusive assumption No supplier assigned from a separate procurement register. Named housing organizations are funding recipients in the project description.

Project money

Project cost not published in this record.

Latest spending total not published here.

CAD · Project allocation as published; bid HST basis not established · Approved 2026 new/additional allocation; excludes carryforward unless expressly stated

Timeline

  1. Target date passed; milestone status needs a verified update

    Tentative start

    Three-phase work

  2. completion

    Phase 1 reported complete

    Official County update specifically confirms Phase 1; not whole project.

  3. Target date passed; milestone status needs a verified update

    Phase 2B expected start

    Mill/Oxford intersection closure estimated four weeks.

  4. completion

    Phase 2B intersection complete and reopened

    The October 21 notice confirms the Oxford Roads 2 and 12 intersection reopened. Phase 2A remains in progress; the whole project is not marked complete.

  5. completion

    Dundas intersection reopened; wider work continues

    The OR2/Dundas–OR12 intersection phase reopened October 21. Phase 2A of the wider reconstruction remains ongoing. The entire project is not complete.

  6. original target

    Overall completion target

    Weather dependent.

Contracts

TENDER-ENG-2026-676 · awardee named in annual register

Oxford Road 2 (Dundas St) Reconstruction: CPKC Overhead Railway Bridge to Oxford Road 12 (Mill St)

Network Sewer and Watermain Ltd

Published bid
$5,935,704.25
Published award / contract value
Not established
Unit price
Not established

The published bid does not establish the final executed contract value. Not established in annual register

Published bid is not an executed or final contract value. The register provides no dated award or payment history.

Open procurement record

Decisions

2025-12-10 · Oxford County Council

2026 Business Plan and Budget approval

County approval confirmed by the official budget hub; the detailed approved document is the financial source.

$406,890,915 · Detailed document total of operating plus financed capital; the budget hub headline conflicts.

Consequence: General levy: $96,680,548; library levy: $6,297,357; court security levy: $61,266. Water and wastewater are supported by utility rates.

2026-08-12 · FS2026-17 Attachment 2

OR2 Dundas reconstruction CPKC overhead railway to OR12 Mill Street

Contract Award – within budget

$5,495,286 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total

Consequence: OR2 Dundas reconstruction CPKC overhead railway to OR12 Mill Street

Outcomes

Completion not confirmed.

Questions

  • What is the current approved project total, including carryforward and changes?
  • What spending and final completion or acceptance records are available?

Related issues

Which level of infrastructure service are we buying, and what risk does a cheaper option leave behind?
Scope & interpretation notes
  • Shared 930002 allocation $4.3m also covers Thamesford lane reconfiguration. Amount not assigned in full to this project; separate water/storm costs also apply.

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. Approved 2026 Business Plan and Budget

    Source ID: county-budget2026-p122

    Publisher
    Oxford County
    Published
    2026-01-14
    Event / reporting date
    2025-12-10
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    approved
    Passage / page
    PDF page 122; printed page 122
    Evidence notes
    File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

    Open in source library

  2. County construction projects

    Source ID: county-construction

    Publisher
    Oxford County
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    official project notice
    Passage / page
    Named project sections; updates through September 2026

    Open in source library

  3. 2026 procurement register: Oxford Road 2 (Dundas St) Reconstruction: CPKC Overhead Railway Bridge to Oxford Road 12 (Mill St)

    Source ID: county-award-tender-eng-2026-676

    Publisher
    Oxford County
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    register entry
    Passage / page
    TENDER-ENG-2026-676
    Evidence notes
    Full annual register downloaded and parsed. Contract-value field is -- for this entry; this is not proof the contract does not exist.

    Open in source library

  4. Oxford Road 2, Woodstock — October 21 update

    Source ID: county-construction-dundas-20261021

    Publisher
    Oxford County
    Source date
    2026-10-21
    Published
    2026-10-21
    Reporting period
    2026
    Reviewed
    2026-10-29
    Retrieved
    2026-10-29
    Verified
    2026-10-29
    Evidence status
    verified_primary
    Decision / approval status
    official source
    Passage / page
    Oxford Road 2/Dundas Street reconstruction: October 21 update
    Evidence notes
    Phase 2B at the Oxford Roads 2 and 12 intersection is complete and the intersection reopened. Phase 2A continues; this is not whole-project completion.

    Open in source library

  5. Dundas intersection reopened; wider work continues

    Source ID: oct30-or2

    Source date
    2026-10-21
    Event / reporting date
    2026-10-21
    Reviewed
    2026-10-30
    Retrieved
    2026-10-30
    Evidence status
    verified_primary
    Decision / approval status
    partially complete
    Evidence note
    Primary-source body reviewed in the October 30 audit The entire project is not complete.

    Open in source library

  6. FS2026-17 Attachment 2: Summary of In-Year Budget Approvals

    Source ID: oct30-county-inyear-approvals

    Source date
    2026-08-12
    Date context
    Report dated August 12, 2026; publication and individual approval dates not established
    Event / reporting date
    2026-08-12
    Reviewed
    2026-10-30
    Retrieved
    2026-10-30
    Evidence status
    verified_primary
    Evidence note
    15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.

    Open in source library

  7. Approved 2026 Business Plan and Budget

    Source ID: county-budget2026-p5

    Publisher
    Oxford County
    Published
    2026-01-14
    Event / reporting date
    2025-12-10
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    approved
    Passage / page
    PDF page 5; printed page 5
    Evidence notes
    File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

    Open in source library

  8. Business plans and budgets

    Source ID: county-budget-hub

    Publisher
    Oxford County
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    official approval summary
    Passage / page
    2026 approved budget section
    Evidence notes
    The hub reports $406.1 million total and $278.2 million operating, while the approved detailed PDF reports $406,890,915 and $279,035,275.

    Open in source library

  9. Approved 2026 Business Plan and Budget

    Source ID: county-budget2026-p58

    Publisher
    Oxford County
    Published
    2026-01-14
    Event / reporting date
    2025-12-10
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    approved
    Passage / page
    PDF page 58; printed page 58
    Evidence notes
    File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

Why are there different County totals?

The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.

Detailed approved budget ↗ · County budget hub ↗

Open the full money explanation