Oxford County · Project

MURC - Construction

Money & projects Explore sections

At a glance

Location
Ingersoll
Responsible authority
Ingersoll
Current stage
Design-build contract reported signed; current construction progress unverifiedAs of 2026-01-31
Lifetime project budget
$38,000,000
Next target
No next date listed

The Town-hosted January 2026 status report says the design-build contract with Ball Construction was signed following Council approval. The exact signing day and executed agreement were not reviewed. This dated report does not establish current construction progress or opening.

This project represents the construction phase of the MURC. The scope of this work includes full construction of the MURC. This includes structural, mechanical, electrical systems, interior and exterior finishes.

Who approves and delivers this project?

Budget and delivery

Town of Ingersoll — Community Services

The service department manages delivery. Finance reports actual spending. Council approves appropriations and changes.

Money

Project money

Budget and forecast

Lifetime project budget
$38,000,000

Annual allocation

2026 allocation
$22,850,000
2026 capital allocation

Recorded spending

Expenditure through 2026-06-30
$823,629
CAD · Not separately specified in capital schedule · 2026 capital allocation

Proposed funding

$38,000,000Listed funding total

  1. ReviseddebentureauthorityBorrowing capacity, not confirmed debt issued
    $18,758,00049.4% of listed total
  2. Land salesRevised funding scenario reduces reliance on timing of sales
    $2,750,0007.2% of listed total
  3. Arena ReserveMulti-year funding allocation
    $12,392,00032.6% of listed total
  4. DCReserveRestricted growth funding
    $1,100,0002.9% of listed total
  5. FundraisingTarget, not received cash
    $3,000,0007.9% of listed total
Listed funding adds to the lifetime budget amount. Proposed sources are not confirmed receipts. CAD.

Timeline

  1. historical estimate

    Historical design and pricing presentation

    The December 8, 2025 presentation reports a $37,935,297 guaranteed maximum price for the then-current scope against a $38 million construction budget. Tax basis is unstated. This is historical pricing, not final cost, payment or the full campus and servicing price.

  2. staff report

    January report says design-build contract signed

    The Town-hosted January 2026 status report says the design-build contract with Ball Construction was signed following Council approval. The exact signing day and executed agreement were not reviewed. This dated report does not establish current construction progress or opening.

  3. review

    October 30 webpage availability check

    The October 30 check recorded Page Not Found at the old project webpage. Cached December 2025 text did not establish current project progress.

  4. original target

    Original project-sheet schedule

    Start: Summer 2025; completion: Summer 2028. Budget book physical PDF page 168. These are targets, not confirmed dates.

Contracts

The January 2026 Town status report says the Ball Construction design-build contract was signed. The executed agreement and a separate award record were not reviewed; final contract value and payments are not established here.

Decisions

2026-03-09 · By-law26-5451

MURC and Clarke Road borrowing authority

By-law form attached to primary report; subsequent financing applications carried June16

$29,360,000 · Maximum authorized borrowing, not debt issued

Consequence: Increase from $15.895 mto $29.360 m for cash-flow flexibility; combined approved project cost stated as unchanged $56.856 m.

2026-08-10 · 2026-212

Allocate 2025 operating surplus to Arena Facility Reserve

approved

$1,862,203.94 · Modified accrual operating surplus transferred to reserve

Consequence: Transfer the budget-basis surplus to Arena Facility Reserve for MURC. This does not itself increase the project budget.

Outcomes

Current construction milestones, completion, opening and final expenditure have not been established by this review. The unavailable old webpage does not negate the accessible dated project reports.

Questions

  • What is the current forecast cost and expected completion date?

Related issues

What is the complete cost, funding and delivery plan for the campus?
Scope & interpretation notes
  • 2026 annual allocation and YTD spending are separate from the $38 m multi-year construction budget. T-008-26 identifies a $56.856 m combined MURC and servicing package. Borrowing authority is not expenditure. The January report’s Q2/Q3 2028 opening and closeout forecasts remain historical, not current commitments.

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. 2026–2027 Mayor’s Budget

    Source ID: ingersoll-budget-2026

    Publisher
    Town of Ingersoll
    Published
    2026-01-12
    Event / reporting date
    2026-01-12
    Reporting period
    2026–2027
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    Mayor’sbudget; Councilshortenedamendmentperiod Jan 12; originalversionpreserved
    Passage / page
    179 pages; original operating summary on physical page 18; capital funding on page 130; project sheets pages 131–179.
    Evidence notes
    The finance hub now links the 179-page Town Budget PDF dated January 12. Comparison found no substantive numerical change; preserve this earlier version and its sourced figures.
    Current version source
    oct29-ingersoll-town-budget-version
    Version checked
    2026-10-29

    Open the current linked version

    Open in source library

  2. T-022-26 — Q 2 operating and capital variance report

    Source ID: ingersoll-q2-2026

    Publisher
    Town of Ingersoll
    Published
    2026-08-10
    Event / reporting date
    2026-08-10
    Reporting period
    sixmonthsended 2026-06-30
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    Received as information; annualbudgetcolumn asreported June 30
    Passage / page
    Capital status pages 3–7; operating summaries pages 10–11; all 41 detailed department/facility tables pages 12–52.

    Open in source library

  3. T-008-26

    Source ID: ingersoll-record-55942

    Publisher
    Town of Ingersoll
    Event / reporting date
    2026-03-09
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published primary record
    Passage / page
    Full public staff report and attached schedules; report number identifies Council agenda item.

    Open in source library

  4. MURC source link remains unavailable

    Source ID: oct30-ing-murc

    Source date
    2026-10-30
    Date context
    Source check date
    Event / reporting date
    2026-10-30
    Reviewed
    2026-10-30
    Retrieved
    2026-10-30
    Evidence status
    inaccessible
    Decision / approval status
    broken-live-link
    Evidence note
    Primary-source body reviewed in the October 30 audit Source check date October 30 live check: Page Not Found. Cached December 2025 text is not current progress.

    Open in source library

  5. MURC January 2026 project status report

    Source ID: nov7-ingersoll-january-status

    Source date
    2026-01-31
    Event / reporting date
    2026-01-31
    Reviewed
    2026-11-07
    Evidence status
    verified_primary
    Passage / page
    Page 2; January 2026 narrative and dashboard
    Evidence note
    The report says the Ball Construction contract was signed following Council approval. The cover year says 2025, while the narrative and dashboard establish January 2026. Exact signing day, executed agreement and current construction progress were not verified.

    Open in source library

  6. MURC December 8, 2025 Council presentation

    Source ID: nov7-ingersoll-december-design

    Source date
    2025-12-08
    Event / reporting date
    2025-12-08
    Reviewed
    2026-11-07
    Evidence status
    verified_primary
    Passage / page
    Slide 25
    Evidence note
    The $37,935,297 guaranteed maximum price is for the then-current scope, compared with the $38 million construction budget. Tax basis is unstated. It is not final expenditure, a payment or the full campus and servicing package.

    Open in source library

  7. MURC source link remains unavailable

    Source ID: oct30-ing-murc

    Source date
    2026-10-30
    Date context
    Source check date
    Event / reporting date
    2026-10-30
    Reviewed
    2026-10-30
    Retrieved
    2026-10-30
    Evidence status
    inaccessible
    Decision / approval status
    broken-live-link
    Evidence note
    Primary-source body reviewed in the October 30 audit Source check date

    Open in source library

  8. Special Meeting of Council Minutes - June 16, 2026

    Source ID: ingersoll-record-58962

    Publisher
    Town of Ingersoll
    Event / reporting date
    2026-06-16
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published primary record
    Passage / page
    Public Council minutes; numbered resolutions.

    Open in source library

  9. T-023-26 —2025 audited statements and surplus allocation

    Source ID: ingersoll-audit-2025

    Publisher
    Town of Ingersoll
    Published
    2026-08-10
    Event / reporting date
    2026-08-10
    Reporting period
    2025
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    Audited PSASaccounts; Councilapproved August 10
    Passage / page
    Report Tables 1–4; appended audited statements pages 3–4 and notes 5–10.

    Open in source library

  10. Regular Meeting of Council Minutes - August 10, 2026

    Source ID: ingersoll-record-60715

    Publisher
    Town of Ingersoll
    Event / reporting date
    2026-08-10
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published primary record
    Passage / page
    Public Council minutes; numbered resolutions.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

Why are there different County totals?

The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.

Detailed approved budget ↗ · County budget hub ↗

Open the full money explanation