2026 Business Plan and Budget approval

County approval confirmed by the official budget hub; the detailed approved document is the financial source.

$406,890,915 · Detailed document total of operating plus financed capital; the budget hub headline conflicts.

Consequence: General levy: $96,680,548; library levy: $6,297,357; court security levy: $61,266. Water and wastewater are supported by utility rates.

2 source records
  1. Business plans and budgets
    Publisher
    Oxford County
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    official approval summary
    Passage / page
    2026 approved budget section
    Evidence notes
    The hub reports $406.1 million total and $278.2 million operating, while the approved detailed PDF reports $406,890,915 and $279,035,275.
  2. Approved 2026 Business Plan and Budget
    Publisher
    Oxford County
    Published
    2026-01-14
    Event / reporting date
    2025-12-10
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    approved
    Passage / page
    PDF page 58; printed page 58
    Evidence notes
    File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

The amount in this decision

$406,890,915

Detailed document total of operating plus financed capital; the budget hub headline conflicts.

2025-12-10 · County approval confirmed by the official budget hub; the detailed approved document is the financial source.
Sources for these figures · 2
  1. Business plans and budgets2026 approved budget section
  2. Approved 2026 Business Plan and BudgetPDF page 58; printed page 58

Authority & recorded votes

Oxford County Council

Individual votes are not confirmed.

Connected projects

County · Roads & bridges

Stover Street South bridge: who got the job?

Replace the deck and girders of County bridge 773216 south of Tidey Street; abutments remain.

Norwich

October 2026 target; completion not verified
2026 allocation
$2,500,000
Named supplier
Clearwater Structures Inc.
Next target
2026-10 · Published completion target
Latest update
2026-08-12 · OR59 Norwich Bridge 773216 superstructure replacement

County · Roads & bridges

Otterville bridge: follow the full project cost

Bridge rehabilitation on Oxford Road 19 between Church and Bullock Streets, phased with alternating traffic.

Norwich

Construction notice; December 2026 completion target
2026 allocation
$400,000
Named supplier
Urbanlink Civil Ltd.
Next target
2026-12 · Expected completion
Latest update
2026-09-28 · Scheduled one-day girder installation closure

County · Roads & bridges

Burgessville Church Street reconstruction

Urbanize Oxford Road 59 across Burgessville with road, sidewalk and lighting upgrades.

Norwich

Current October 2026 target; completion not verified
2026 allocation
$4,100,000
Named supplier
GIP Paving Inc.
Next target
2026-10 · Published completion target
Latest update
2026-08-12 · OR59 Church Street urbanization Burgessville

County · Roads & bridges

Innerkip bridge rehabilitation

The County construction page marks the Innerkip OR29 bridge project complete and reports reopening October 2. Completion applies to this project, not every OR29 project.

East Zorra-Tavistock

Construction complete; reopened October 2, 2026
2026 allocation
$2,100,000
Named supplier
2585284 Ontario Inc. o/a Beton
Next target
No next date listed
Latest update
2026-10-02 · Construction complete and road reopened

County · Roads & bridges

Oxford Road 59 railway bridge steel coating

Clean and coat existing structural steel on bridge59755.

Woodstock

Steel-coating work; October 2026 target, completion unverified
2026 allocation
$4,500,000
Named supplier
Harrison Muir Inc.
Next target
2026-10 · Coating completion target
Latest update
2026-04-27 · Steel-coating work begins

County · Roads & bridges

Oxford Road 2 boundary culvert rehabilitation

Rehabilitate culvert686444 1.7km east of Oxford Road 22.

Blandford-Blenheim

Funding approved · delivery unconfirmed
2026 allocation
$650,000
Named supplier
PSCO technical group
Next target
No next date listed
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Roads & bridges

Oxford Road 119 culvert rehabilitation

Rehabilitate culvert194950 south of Oxford Road 2 in Thamesford.

Zorra

Funding approved · delivery unconfirmed
2026 allocation
$750,000
Named supplier
2274084 ONTARIO LTD o/a GMP CONTRACTING
Next target
No next date listed
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Other projects

Norwich lagoon biosolids cleanout

Clean biosolids from the County wastewater treatment lagoon.

Norwich

Enviroland named; $809,080 contract value published; completion unverified
2026 allocation
$1,400,000
Named supplier
Enviroland Services Inc.
Next target
No next date listed
Latest update
2026-10-29 · Published contract value verified

County · Water, drainage & wastewater

Tillsonburg inlet trunk sewer replacement

Replace the sewer near Old Vienna Road with manholes, connections, restoration and erosion protection. Construction is scheduled for October 19 to mid-December 2026. Dates remain subject to change; actual commencement and completion have not been independently confirmed.

Tillsonburg

Awardee named; construction scheduled October 19–mid-December 2026; actual start unconfirmed
2026 allocation
$1,350,000
Named supplier
Birnam Excavating Ltd.
Next target
2026-12 · Expected completion: mid-December 2026
Latest update
2026-10-16 · Revised schedule and pedestrian access announced

County · Roads & bridges

Oxford Road 59 and Fairway sanitary trunk sewer

Replace the sanitary trunk sewer at Oxford Road 59 and Fairway Road.

Woodstock

County construction page labels work complete
2026 allocation
$950,000
Named supplier
Kieswetter Excavating Inc.
Next target
No next date listed
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Roads & bridges

Devonshire Avenue phase 2: road and utility reconstruction

Victoria Street to Knightsbridge Road; replace sanitary, storm and water infrastructure, three-lane road, bike lanes, sidewalks and pedestrian signals.

Woodstock

Phase 2 work; November 2026 completion target
2026 allocation
$2,500,000
Named supplier
J-AAR Civil Infrastructures Limited
Next target
2026-11 · Expected completion
Latest update
2026-08-12 · OR35 Devonshire reconstruction Victoria to Knightsbridge

County · Roads & bridges

Dundas Street reconstruction: phases and closures

The OR2/Dundas–OR12 intersection phase reopened October 21. Phase 2A of the wider reconstruction remains ongoing. The entire project is not complete.

Woodstock

Oxford Roads 2/12 intersection reopened; Phase 2A continues
2026 allocation
Not established
Named supplier
Network Sewer and Watermain Ltd
Next target
2026-11 · Overall completion target
Latest update
2026-10-21 · Phase 2B intersection complete and reopened

County · Roads & bridges

Oxford Road 30 slope and trail stabilization

Stabilize slope by Standard Tube, Burgess and Rotary Millennium trails on11thLine.

Woodstock

August–November 2026 construction target
2026 allocation
$100,000
Named supplier
Cambridge Landscaping & Construction Ltd
Next target
2026-11 · Expected completion
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Roads & bridges

Ingersoll Street South and Thomas Street retaining wall

Replace the retaining wall at393ThomasStreet.

Ingersoll

Funding approved · delivery unconfirmed
2026 allocation
$150,000
Named supplier
519 London Excavating Inc.
Next target
No next date listed
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Other projects

Oxford Roads 8 and 59 resurfacing

Cold-in-place recycling, hot-mix paving and roadside work on Oxford Road 8 near Plattsville and Oxford Road 59 between Oxford Roads 17 and 8.

Blandford-Blenheim · East Zorra-Tavistock

September target passed; completion not verified
2026 allocation
Not established
Named supplier
GIP Paving Inc.
Next target
No next date listed
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Roads & bridges

County culvert replacements across local roads

Culvert replacements on parts of Oxford Roads 2, 10, 13, 22, 55 and 59, plus a left-turn lane at Oxford Road 2 and 35th Line.

Blandford-Blenheim · East Zorra-Tavistock · South-West Oxford · Zorra

Named OR2/OR22/OR59 sections complete; OR10 scheduled mid-October–end-November
2026 allocation
Not established
Named supplier
Steve Smith Construction Corporation
Next target
2026-10 · Oxford Road 10 start target
Latest update
2026-10-29 · Section-specific status reviewed

County · Other projects

Drumbo and Embro patrol-yard backup generators

Backup generators and transfer equipment at the Drumbo and Highland patrol yards.

Blandford-Blenheim · Zorra

Funding approved · delivery unconfirmed
2026 allocation
$350,000
Named supplier
2592275 Ontario inc
Next target
No next date listed
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Water, drainage & wastewater

Thamesford wastewater plant upgrade

New two-storey headworks, aeration-roof removal, generator and process equipment.

Zorra

Multi-year construction planned May/June 2026–May 2028
2026 allocation
$6,000,000
Next target
2028-05 · Expected completion
Latest update
2026-03-11 · Multi-year award recommended

County · Water, drainage & wastewater

Mount Elgin wastewater capacity expansion

Increase wastewater treatment capacity for Mount Elgin.

South-West Oxford

Funding approved · delivery unconfirmed
2026 allocation
$4,500,000
Next target
No next date listed
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Buildings & facilities

Tillsonburg Well 7A treatment facility

Build onsite treatment at 445 Broadway Street, demolish the existing facility at 451 Broadway Street and upgrade services.

Tillsonburg

December 2026 construction target; completion unverified
2026 allocation
$5,590,667
Named supplier
Baseline Constructors Inc.
Next target
2026-12 · Expected completion
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Water, drainage & wastewater

Tavistock Well 4: added water supply

Drill and test a production well on Hope Street West to increase water supply capacity and backup.

East Zorra-Tavistock

August target passed; completion not verified
2026 allocation
$798,000
Named supplier
AECOM Canada ULC
Next target
No next date listed
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Roads & bridges

William Street sanitary pumping station

Sanitary pumping station and associated trunk sewer planning in Tavistock.

East Zorra-Tavistock

Survey work announced for June and July 2026
2026 allocation
$712,000
Named supplier
Stantec Consulting Ltd.
Next target
No next date listed
Latest update
2026-07-06 · Survey week

County · Water, drainage & wastewater

Woodstock wastewater biogas utilization

Use biogas from the Woodstock wastewater treatment plant in renewable energy infrastructure.

Woodstock

Funding approved · delivery unconfirmed
2026 allocation
$2,500,000
Named supplier
Sutherland Schultz Ltd
Next target
No next date listed
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Other projects

Salford landfill gas collection

Expand or renew the landfill gas collection system at the County waste management facility.

South-West Oxford

NPL Canada named for Phase 2-2; contract value and completion unverified
2026 allocation
$1,500,000
Named supplier
NPL Canada Ltd.
Next target
No next date listed
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Roads & bridges

Thamesford Dundas Street traffic changes

New signals at George Street, a crossing relocated to Stanley Street, a central turn lane, signal upgrades and removal of on-street parking.

Zorra

KWS named; September 28 week–November 2026 construction schedule
2026 allocation
Not established
Named suppliers
J.L. Richards & Associates Limited; KWS Electrical Services
Next target
2026-11 · Expected finish
Latest update
2026-09-24 · Pre-construction meeting
Who’s actually in charge?

Who’s actually in charge?

01

East Zorra-Tavistock council

Municipal services, local roads, recreation, zoning and the local budget.

Explore this level →
02

Oxford County

County roads, water and wastewater, housing services, paramedics and County planning.

Explore this level →

Meet your representatives