The County construction page marks the Innerkip OR29 bridge project complete and reports reopening October 2. Completion applies to this project, not every OR29 project.
Rehabilitate bridge805907 on Oxford Road 29, including bearings, approach slabs, deck overlay and railing.
Project 930200 · Asset 805907
Who approves and delivers this project?
Expenditure approval
Oxford County Council
County capital budget authority; individual votes not inferred.
These amounts use the in-year approvals schedule's basis. They are not substituted for bidder prices, executed contract values, whole-project budgets or payments, or added to other project figures.
Contract Award – within budget
$1,589,554 · Report dated 2026-08-12 · Individual approval date not established
Not specified in inspected attachment; no inclusive/exclusive assumption
Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total Individual approval dates are not specified in the row Not specified in inspected attachment; no inclusive/exclusive assumption No supplier assigned from a separate procurement register. Named housing organizations are funding recipients in the project description.
Milestone completion confirmed; deadline performance not established
Extended full-closure target
The official notice extends closure to September 30. No reopening confirmation was found by October 1. The later County notice confirms completion and reopening October 2; this does not establish that the September 30 target was met.
The County construction page marks the Innerkip OR29 bridge project complete and reports reopening October 2. Completion applies to this project, not every OR29 project.
Construction complete; reopened October 2, 2026. Completion or reopening of this scope does not establish final acceptance, final project cost or payment.
Questions
What is the current approved project total, including carryforward and changes?
What spending and final completion or acceptance records are available?
The official construction page confirms completion and reopening on October 2. The earlier September 30 closure target is retained in the timeline. Final costs, payments and formal acceptance are not established.
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Official central page confirms construction completion and reopening October 2. October 2 is the event date; a separate first-publication date is not established. Final payment and formal acceptance records were not reviewed.
Report dated August 12, 2026; publication and individual approval dates not established
Event / reporting date
2026-08-12
Reviewed
2026-10-30
Retrieved
2026-10-30
Evidence status
verified_primary
Evidence note
15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.