On this page Overview Money Timeline Contracts Decisions Outcomes Questions Evidence At a glance
Location East Zorra-Tavistock
Responsible authority Oxford County Current stage August target passed; completion not verifiedAs of 2026-10-29 Stage and project evidence: [1] [2] [3] [4]
2026 allocation $798,000
Next target No next date listed Drill and test a production well on Hope Street West to increase water supply capacity and backup.
Well drilling, production-well construction and pumping tests.
Project 960437
Who approves and delivers this project? Expenditure approval
Oxford County Council County capital budget authority; individual votes not inferred.
Sources for this record: [1]
Asset owner and delivery lead
Oxford County Public Works County project located within the local municipality; local council is not the County contract manager.
Sources for this record: [5]
Money Project money Annual allocation 2026 allocation $798,000 2026 expenditure allocation; entirely carryforward Latest spending total not published here.
CAD · Project allocation as published; bid HST basis not established · 2026 expenditure allocation; entirely carryforward Project money evidence: [1] [2] [3] [4]
Where the funding comes from $798,000 Listed funding total
$438,71955% of listed total $359,28145% of listed total Listed funding adds to the 2026 allocation amount. CAD. Timeline 2026-06-01 Target date passed; milestone status needs a verified update Expected start week Drilling and testing.
Sources for this record: [2]
2026-08 Target date passed; milestone status needs a verified update Expected completion The County page has no completion confirmation for this project.
Sources for this record: [2]
Contracts RFP-ENG-2025-618 · awardee named in annual register
AECOM Canada ULC
Published bid Not established
Published award / contract value Not established
Unit price Not established Not established in annual register
2025 award connected to current 2026 work. The annual register names the awardee but leaves the contract value and award date unpublished.
Sources for this record: [3]
Open procurement record Decisions 2025-12-10 · Oxford County Council
County approval confirmed by the official budget hub; the detailed approved document is the financial source.
$406,890,915 · Detailed document total of operating plus financed capital; the budget hub headline conflicts.
Consequence: General levy: $96,680,548; library levy: $6,297,357; court security levy: $61,266. Water and wastewater are supported by utility rates.
Sources for this record: [6] [7]
Outcomes Completion not confirmed.
Questions What is the current approved project total, including carryforward and changes? What spending and final completion or acceptance records are available? Scope & interpretation notes The entire $798,000 2026 allocation is carried forward from prior approval. Sources & evidence These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: county-budget2026-p47
Publisher Oxford County
Published 2026-01-14
Event / reporting date 2025-12-10
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status approved
Passage / page PDF page 47; printed page 47
Evidence notes File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs. Open in source library
Source ID: county-construction
Publisher Oxford County
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status official project notice
Passage / page Named project sections; updates through September 2026 Open in source library
Source ID: county-award-rfp-eng-2025-618
Publisher Oxford County
Reporting period 2025 award register; 2026 active project
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status published record
Passage / page RFP-ENG-2025-618; named awardee and bidder-price row
Evidence notes Prior-year award linked to a project active during 2026. The contract value cell is --; the bid is not a signed contract value. Open in source library
Source ID: county-construction-20261029
Publisher Oxford County
Reporting period 2026
Reviewed 2026-10-29
Retrieved 2026-10-29
Verified 2026-10-29
Evidence status verified_primary
Decision / approval status official source
Passage / page Named road, bridge, culvert and water/wastewater project sections
Evidence notes Current central-page text was reviewed. Named completion notices apply only to their stated scope; a passed target is not proof of completion. Newer linked PDF handouts were not all independently read. Open in source library
Source ID: county-budget2026-p5
Publisher Oxford County
Published 2026-01-14
Event / reporting date 2025-12-10
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status approved
Passage / page PDF page 5; printed page 5
Evidence notes File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs. Open in source library
Source ID: county-budget-hub
Publisher Oxford County
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status official approval summary
Passage / page 2026 approved budget section
Evidence notes The hub reports $406.1 million total and $278.2 million operating, while the approved detailed PDF reports $406,890,915 and $279,035,275. Open in source library
Source ID: county-budget2026-p58
Publisher Oxford County
Published 2026-01-14
Event / reporting date 2025-12-10
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status approved
Passage / page PDF page 58; printed page 58
Evidence notes File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs. Open in source library