Expenditure approval
Oxford County Council
County capital budget authority; individual votes not inferred.
Sources for this record: [1]
Eight places. One shared future.
Oxford County · Project
Build onsite treatment at 445 Broadway Street, demolish the existing facility at 451 Broadway Street and upgrade services.
Treatment facility and site services at 445 and 451 Broadway Street.
Project 960200
Expenditure approval
County capital budget authority; individual votes not inferred.
Sources for this record: [1]
Asset owner and delivery lead
County project located within the local municipality; local council is not the County contract manager.
Sources for this record: [5]
Latest spending total not published here.
Project money evidence: [1] [2] [3] [4]
$5,590,667Listed funding total
Early November 2025.
Sources for this record: [2]
County says existing drinking water remains safe; the project adds arsenic filtration so this well can supply water independently in future.
Sources for this record: [2]
TENDER-ENG-2025-637 · awardee named in annual register
Baseline Constructors Inc.
The published bid does not establish the final executed contract value. Not established in annual register
2025 award connected to current 2026 work. The annual register names the awardee but leaves the contract value and award date unpublished.
Sources for this record: [3]
Open procurement record2025-12-10 · Oxford County Council
County approval confirmed by the official budget hub; the detailed approved document is the financial source.
$406,890,915 · Detailed document total of operating plus financed capital; the budget hub headline conflicts.
Consequence: General levy: $96,680,548; library levy: $6,297,357; court security levy: $61,266. Water and wastewater are supported by utility rates.
Completion not confirmed.
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: county-budget2026-p46
Source ID: county-construction
Source ID: county-award-tender-eng-2025-637
Source ID: county-construction-20261029
Source ID: county-budget2026-p5
Source ID: county-budget-hub
Source ID: county-budget2026-p58
Your taxes called. They’d like a receipt.
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.
Detailed approved budget ↗ · County budget hub ↗