County · Roads & bridges
New signals at George Street, a crossing relocated to Stanley Street, a central turn lane, signal upgrades and removal of on-street parking.
Zorra
Start scheduled for September 28 week; November 2026 completion target- 2026 allocation
- Not established
- Named supplier
- J.L. Richards & Associates Limited
- Next target
- 2026-11 · Expected finish
- Latest update
- 2026-09-24 · Pre-construction meeting
Open project →Zorra · Parks, recreation & culture
Proposed off-leash area behind the ball diamond. Matheson Park selected; committee requested fall 2026 fencing and amenities.
Zorra
Location selected; committee requested earlier phase-one construction- 2026 allocation
- Not established
- Next target
- No next date listed
- Latest update
- 2026-08-20 · Committee requested fall fencing and amenities
Open project →Zorra · Roads & bridges
Bridge 140, 33rd Line over Trout Creek
Zorra
Additional reserve funding and AJN award authorized- Revised budget
- $224,072.69
- Named supplier
- AJN Builders Inc.
- Next target
- No next date listed
- Latest update
- 2026-08-13 · Funding increased and contract award authorized
Open project →Zorra · Roads & bridges
Bridge 70 rigid frame
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $41,000
- Next target
- No next date listed
- Latest update
- 2026-08-13 · Increase Bridge 140 funding and award AJN Builders
Open project →Zorra · Fire & public safety
Council selected the former Public Works site at 8 Commissioners Street as the preferred location and requested separate cost, funding and implementation reports for Embro and Uniondale.
Zorra
Preferred site endorsed; detailed cost and delivery plan requested- 2026 allocation
- Not established
- Next target
- No next date listed
- Latest update
- 2026-08-13 · Endorse former Public Works site for replacement Embro fire station
Open project →Zorra · Roads & bridges
Bridge 640, 25th Line, Meathrell Creek
Zorra · South-West Oxford
Bridge rehabilitation completed July 24; road reopening awaited paving- 2026 allocation
- $1,322,880
- Named supplier
- Weathertech Restoration Services Inc.
- Next target
- No next date listed
- Latest update
- 2026-07-24 · Bridge rehabilitation completed
Open project →Zorra · Parks, recreation & culture
Don Knox trail phase 2
Zorra
Paving completed in July 2026- 2026 allocation
- $20,000
- Next target
- No next date listed
- Latest update
- 2026-07 · Trail paving completed
Open project →Zorra · Roads & bridges
Maintenance gravel haul
Zorra
Gravel hauling and application completed June 12- Original budget
- $305,000
- Named supplier
- E+W Blane Trucking
- Next target
- No next date listed
- Latest update
- 2026-06-12 · Gravel work completed
Open project →Zorra · Parks, recreation & culture
TDRC storage facility
Zorra
Additional reserve authority approved; staff to negotiate with lowest bidder- Revised budget
- $260,000
- Next target
- No next date listed
- Latest update
- 2026-05-06 · Reserve increase approved
Open project →County · Water, drainage & wastewater
New two-storey headworks, aeration-roof removal, generator and process equipment.
Zorra
Multi-year construction planned May/June 2026–May 2028- 2026 allocation
- $6,000,000
- Next target
- 2028-05 · Expected completion
- Latest update
- 2026-03-11 · Multi-year award recommended
Open project →Zorra · Other projects
School plan includes 479 JK–Grade 4 places and 88 licensed childcare spaces, with a public-use gymnasium co-build.
Zorra
School and public gym co-build in progress- 2026 allocation
- $3,087,538
- Next target
- No next date listed
- Latest update
- 2026-02-03 · Public information session held
Open project →County · Roads & bridges
Culvert replacements on parts of Oxford Roads 2, 10, 13, 22, 55 and 59, plus a left-turn lane at Oxford Road 2 and 35th Line.
Blandford-Blenheim · East Zorra-Tavistock · South-West Oxford · Zorra
Some sections listed complete; Oxford Road 10 scheduled for October–November- 2026 allocation
- Not established
- Named supplier
- Steve Smith Construction Corporation
- Next target
- 2026-10 · Oxford Road 10 start target
- Latest update
- 2025-12-10 · 2026 Business Plan and Budget approval
Open project →County · Other projects
Backup generators and transfer equipment at the Drumbo and Highland patrol yards.
Blandford-Blenheim · Zorra
Funding approved · delivery unconfirmed- 2026 allocation
- $350,000
- Named supplier
- 2592275 Ontario inc
- Next target
- No next date listed
- Latest update
- 2025-12-10 · 2026 Business Plan and Budget approval
Open project →County · Roads & bridges
Rehabilitate culvert194950 south of Oxford Road 2 in Thamesford.
Zorra
Funding approved · delivery unconfirmed- 2026 allocation
- $750,000
- Named supplier
- 2274084 ONTARIO LTD o/a GMP CONTRACTING
- Next target
- No next date listed
- Latest update
- 2025-12-10 · 2026 Business Plan and Budget approval
Open project →Zorra · Roads & bridges
25th Line, Road 60 to bridge, 0.7 km
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $172,616
- Named suppliers
- Brantco Construction; Claussen Farms Custom Farming Inc.
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Other projects
Annual IT upgrades
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $20,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Roads & bridges
Asphalt patching
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $102,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Vehicles & equipment
Bunker gear, radios and firefighting equipment
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $107,970
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Housing & community services
Childcare window film
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $20,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Fire & public safety
Embro fire station security
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $5,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Parks, recreation & culture
EZCC desuperheater
Zorra
Equipment delivered; installation pending- 2026 allocation
- $12,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Parks, recreation & culture
EZCC electrical panel and soft start
Zorra
Equipment delivered; installation pending- 2026 allocation
- $80,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Parks, recreation & culture
EZCC parking lot
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $20,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Parks, recreation & culture
EZCC plate chiller
Zorra
Equipment delivered; installation pending- 2026 allocation
- $150,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →