Zorra · Roads & bridges
Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.
Zorra
Complete per staff report; road reopened- 2026 allocation
- $172,616
- Named suppliers
- Brantco Construction; Claussen Farms Custom Farming Inc.
- Next target
- No next date listed
- Latest update
- 2026-10-30 · Road 92 and 25th Line paving complete
Open project →Zorra · Roads & bridges
Report 2026-112 says Bridge 140 work on 33rd Line between Road 96 and Road 98 started October 5 and was completed with the road reopened within two weeks. Prepared for the November 4 council meeting; no exact reopening day is stated.
Zorra
Complete per staff report; road reopened- Revised budget
- $224,072.69
- Named supplier
- AJN Builders Inc.
- Next target
- No next date listed
- Latest update
- 2026-10-30 · Bridge 140 work complete; 33rd Line reopened
Open project →Zorra · Roads & bridges
Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.
Zorra · South-West Oxford
Complete per staff report; road reopened- 2026 allocation
- $1,322,880
- Named supplier
- Weathertech Restoration Services Inc.
- Next target
- No next date listed
- Latest update
- 2026-10-30 · Road 92 and 25th Line paving complete
Open project →Zorra · Roads & bridges
Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.
Zorra
Complete per staff report; road reopened- 2026 allocation
- $426,798
- Named suppliers
- Brantco Construction; Claussen Farms Custom Farming Inc.
- Next target
- No next date listed
- Latest update
- 2026-10-30 · Road 92 and 25th Line paving complete
Open project →Zorra · Roads & bridges
Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.
Zorra
Complete per staff report; road reopened- 2026 allocation
- $426,798
- Named suppliers
- Brantco Construction; Claussen Farms Custom Farming Inc.
- Next target
- No next date listed
- Latest update
- 2026-10-30 · Road 92 and 25th Line paving complete
Open project →County · Roads & bridges
Culvert replacements on parts of Oxford Roads 2, 10, 13, 22, 55 and 59, plus a left-turn lane at Oxford Road 2 and 35th Line.
Blandford-Blenheim · East Zorra-Tavistock · South-West Oxford · Zorra
Named OR2/OR22/OR59 sections complete; OR10 scheduled mid-October–end-November- 2026 allocation
- Not established
- Named supplier
- Steve Smith Construction Corporation
- Next target
- 2026-10 · Oxford Road 10 start target
- Latest update
- 2026-10-29 · Section-specific status reviewed
Open project →County · Roads & bridges
New signals at George Street, a crossing relocated to Stanley Street, a central turn lane, signal upgrades and removal of on-street parking.
Zorra
KWS named; September 28 week–November 2026 construction schedule- 2026 allocation
- Not established
- Named suppliers
- J.L. Richards & Associates Limited; KWS Electrical Services
- Next target
- 2026-11 · Expected finish
- Latest update
- 2026-09-24 · Pre-construction meeting
Open project →Zorra · Parks, recreation & culture
Report 2026-105 described construction on September 24, 2026. Acrylic surfacing might wait until April, and staff recommended a spring ceremony. The November 7 source check did not verify a public opening, finished surfacing or safety sign-off.
Zorra
Construction reported September 24; public opening unverified- 2026 allocation
- $305,827
- Next target
- No next date listed
- Latest update
- 2026-09-24 · Construction reported; opening not established
Open project →Zorra · Parks, recreation & culture
Proposed off-leash area behind the ball diamond. Matheson Park selected; committee requested fall 2026 fencing and amenities.
Zorra
Location selected; committee requested earlier phase-one construction- 2026 allocation
- Not established
- Next target
- No next date listed
- Latest update
- 2026-08-20 · Committee requested fall fencing and amenities
Open project →Zorra · Roads & bridges
Bridge 70 rigid frame
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $41,000
- Next target
- No next date listed
- Latest update
- 2026-08-13 · Increase Bridge 140 funding and award AJN Builders
Open project →Zorra · Fire & public safety
Council selected the former Public Works site at 8 Commissioners Street as the preferred location and requested separate cost, funding and implementation reports for Embro and Uniondale.
Zorra
Preferred site endorsed; detailed cost and delivery plan requested- 2026 allocation
- Not established
- Next target
- No next date listed
- Latest update
- 2026-08-13 · Endorse former Public Works site for replacement Embro fire station
Open project →Zorra · Parks, recreation & culture
Don Knox trail phase 2
Zorra
Paving completed in July 2026- 2026 allocation
- $20,000
- Next target
- No next date listed
- Latest update
- 2026-07 · Trail paving completed
Open project →Zorra · Roads & bridges
Maintenance gravel haul
Zorra
Gravel hauling and application completed June 12- Original budget
- $305,000
- Named supplier
- E+W Blane Trucking
- Next target
- No next date listed
- Latest update
- 2026-06-12 · Gravel work completed
Open project →Zorra · Parks, recreation & culture
TDRC storage facility
Zorra
Additional reserve authority approved; staff to negotiate with lowest bidder- Revised budget
- $260,000
- Next target
- No next date listed
- Latest update
- 2026-05-06 · Reserve increase approved
Open project →County · Water, drainage & wastewater
New two-storey headworks, aeration-roof removal, generator and process equipment.
Zorra
Multi-year construction planned May/June 2026–May 2028- 2026 allocation
- $6,000,000
- Next target
- 2028-05 · Expected completion
- Latest update
- 2026-03-11 · Multi-year award recommended
Open project →Zorra · Other projects
School plan includes 479 JK–Grade 4 places and 88 licensed childcare spaces, with a public-use gymnasium co-build.
Zorra
School and public gym co-build in progress- 2026 allocation
- $3,087,538
- Next target
- No next date listed
- Latest update
- 2026-02-03 · Public information session held
Open project →County · Other projects
Backup generators and transfer equipment at the Drumbo and Highland patrol yards.
Blandford-Blenheim · Zorra
Funding approved · delivery unconfirmed- 2026 allocation
- $350,000
- Named supplier
- 2592275 Ontario inc
- Next target
- No next date listed
- Latest update
- 2025-12-10 · 2026 Business Plan and Budget approval
Open project →County · Roads & bridges
Rehabilitate culvert194950 south of Oxford Road 2 in Thamesford.
Zorra
Funding approved · delivery unconfirmed- 2026 allocation
- $750,000
- Named supplier
- 2274084 ONTARIO LTD o/a GMP CONTRACTING
- Next target
- No next date listed
- Latest update
- 2025-12-10 · 2026 Business Plan and Budget approval
Open project →Zorra · Other projects
Annual IT upgrades
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $20,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Roads & bridges
Asphalt patching
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $102,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Vehicles & equipment
Bunker gear, radios and firefighting equipment
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $107,970
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Housing & community services
Childcare window film
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $20,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Fire & public safety
Embro fire station security
Zorra
2026 funding approved · completion unconfirmed- 2026 allocation
- $5,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →Zorra · Parks, recreation & culture
EZCC desuperheater
Zorra
Equipment delivered; installation pending- 2026 allocation
- $12,000
- Next target
- No next date listed
- Latest update
- 2025-12-03 · Annual allocation adopted
Open project →