Zorra · Project

Thamesford multi-use courts

Money & projects Explore sections
Zorra project

At a glance

Location
Zorra
Responsible authority
Zorra
Current stage
Construction reported September 24; public opening unverifiedAs of 2026-09-24
2026 allocation
$305,827
Next target
No next date listed

Report 2026-105 described construction on September 24, 2026. Acrylic surfacing might wait until April, and staff recommended a spring ceremony. The November 7 source check did not verify a public opening, finished surfacing or safety sign-off.

Thamesford multi-use courts

Who approves and delivers this project?

Budget authority

Township Council

Approves annual allocation; delivery and contract authority must be traced separately.

Money

Project money

Annual allocation

2026 allocation
$305,827
2026 annual capital allocation; not a final contract or lifetime cost

Latest spending total not published here.

CAD · Source budget basis; HST treatment not separately stated · 2026 annual capital allocation; not a final contract or lifetime cost

Where the funding comes from

$305,827Listed funding total

  1. ReservesCapital plan allocation
    $79,95026.1% of listed total
  2. other capital fundingSource funding category; not proof of grant receipt
    $225,87773.9% of listed total
Listed funding adds to the 2026 allocation amount. CAD.

Timeline

  1. approval

    Annual allocation adopted

    Budget allocation is not a contract award or completion record.

  2. staff report

    Construction reported; opening not established

    Report 2026-105 described construction on September 24. Acrylic surfacing might wait until April, and staff recommended a spring ceremony. The report does not establish finished surfacing, safety sign-off or public opening.

Contracts

· Portal marked awarded May 13; awardee/contract value not verified from accessible award row

Thamesford multi-use courts

Awardee not established

Published bid
$262,028.23
Published award / contract value
Not established
Unit price
Not established

The published bid does not establish the final executed contract value. Not stated

Van Roestel bid total from public bid summary; do not automatically treat it as awarded value.

Open procurement record

Decisions

No separate decision record is linked. Approval details may appear in the timeline or source documents.

Outcomes

Public opening, safety sign-off, final surfacing, fourth-court funding and final cost are not established by the cited record.

Questions

  • What is the latest committed cost, spending to date and completion milestone?

Related issues

What is the usable opening date for the community courts, and what remains between construction and public access?

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. 2026 final operating budget and ten-year capital plan, report 2025-130

    Source ID: zorra-budget2026

    Publisher
    Township of Zorra
    Published
    2025-12-03
    Event / reporting date
    2025-12-03
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    adopted
    Passage / page
    PDF pp. 1–95; account and project pages retained in rows
    Evidence notes
    Final council-approved schedules. 2025 comparatives restated; 2024 not restated. Capital is excluded from the 2026 operating schedule.

    Open in source library

  2. Current dog park and multi-use court project status

    Source ID: zorra-v7-committee-status

    Publisher
    Township of Zorra
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published
    Passage / page
    Embro Dog Park and Zorra Multi-Use Court sections
    Evidence notes
    Undated current page observed October 1; courts awarded and waiting for infrastructure work; supplier/award price not supplied. Dog-park date inconsistency resolved by adopted minutes.

    Open in source library

  3. Report 2026-105: Thamesford courts construction and donor recognition

    Source ID: nov7-zorra-courts-report2026-105

    Source date
    2026-09-24
    Event / reporting date
    2026-09-24
    Reviewed
    2026-11-07
    Evidence status
    verified_primary
    Passage / page
    Report 2026-105, September 24 committee meeting
    Evidence note
    Reports construction at that time; acrylic surfacing might wait until April and a spring ceremony was recommended. This does not establish finished surfacing, safety sign-off or public opening.

    Open in source library

  4. Thamesford multi-use court tender portal

    Source ID: zorra-courts-tender

    Publisher
    Township of Zorra
    Published
    2026-05-13
    Event / reporting date
    2026-05-13
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published
    Passage / page
    Bid status and public bid summary
    Evidence notes
    Portal shows awarded status; accessible bid summary shows Van Roestel total, while dynamic award-vendor rows were not exposed. Tax basis not given in accessible summary.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

Open the full money explanation