Zorra · Project

County culvert replacements across local roads

Money & projects Explore sections
Oxford County projectView County project page →

At a glance

Location
Blandford-Blenheim, East Zorra-Tavistock, South-West Oxford, Zorra
Responsible authority
Oxford County
Current stage
Named OR2/OR22/OR59 sections complete; OR10 scheduled mid-October–end-NovemberAs of 2026-10-29
2026 allocation
Not established
Next target
2026-10 · Oxford Road 10 start target
Named supplier
Steve Smith Construction Corporation See contract details

Culvert replacements on parts of Oxford Roads 2, 10, 13, 22, 55 and 59, plus a left-turn lane at Oxford Road 2 and 35th Line.

One multi-location procurement; individual road sections have different closure and completion dates.

Project 930199 · Project 930077

Who approves and delivers this project?

Expenditure approval

Oxford County Council

County capital budget authority; individual votes not inferred.

Asset owner and delivery lead

Oxford County Public Works

County project located within the local municipality; local council is not the County contract manager.

Money

Project money

Project cost not published in this record.

Latest spending total not published here.

CAD · Project allocation as published; bid HST basis not established · Approved 2026 new/additional allocation; excludes carryforward unless expressly stated

Timeline

  1. Target date passed; milestone status needs a verified update

    Oxford Road 2 original target

    The official construction page now labels Oxford Road 2 culvert work complete.

  2. Target date passed; milestone status needs a verified update

    Oxford Road 59 original target

    The official page now labels culvert replacements south of Tavistock complete.

  3. Target date passed; milestone status needs a verified update

    Oxford Road 22 original target

    The official page labels Oxford Road 22 culvert replacement complete.

  4. original target

    Oxford Road 10 start target

    South-West Oxford; two phases with separate detours.

  5. source review

    Section-specific status reviewed

    The central page labels Oxford Road 2 Zorra, Oxford Road 22 and Oxford Road 59 William Street–Oxford Road 8 culverts complete. Oxford Road 10 in South-West Oxford remains a two-phase mid-October–end-November schedule. This does not complete the whole procurement.

  6. original target

    Oxford Road 10 finish target

    End of November is a tentative target.

Contracts

TENDER-ENG-2026-673 · awardee named in annual register

2026 County Culvert Replacements on Parts of Oxford Roads: 2, 10, 13, 22, 55 & 59 & Left-Turn Lane at OR 2 & 35th Line

Steve Smith Construction Corporation

Published bid
$2,837,113.04
Published award / contract value
Not established
Unit price
Not established

The published bid does not establish the final executed contract value. Not established in annual register

Published bid is not an executed or final contract value. The register provides no dated award or payment history.

Open procurement record

Decisions

2025-12-10 · Oxford County Council

2026 Business Plan and Budget approval

County approval confirmed by the official budget hub; the detailed approved document is the financial source.

$406,890,915 · Detailed document total of operating plus financed capital; the budget hub headline conflicts.

Consequence: General levy: $96,680,548; library levy: $6,297,357; court security levy: $61,266. Water and wastewater are supported by utility rates.

Outcomes

Completion not confirmed.

Questions

  • What is the current approved project total, including carryforward and changes?
  • What spending and final completion or acceptance records are available?

Related issues

Which level of infrastructure service are we buying, and what risk does a cheaper option leave behind?
Scope & interpretation notes
  • Individual completed sections do not establish completion of the whole procurement. Final contract changes and payments have not been verified.

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. Approved 2026 Business Plan and Budget

    Source ID: county-budget2026-p41

    Publisher
    Oxford County
    Published
    2026-01-14
    Event / reporting date
    2025-12-10
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    approved
    Passage / page
    PDF page 41; printed page 41
    Evidence notes
    File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

    Open in source library

  2. County construction projects

    Source ID: county-construction

    Publisher
    Oxford County
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    official project notice
    Passage / page
    Named project sections; updates through September 2026

    Open in source library

  3. 2026 procurement register: 2026 County Culvert Replacements on Parts of Oxford Roads: 2, 10, 13, 22, 55 & 59 & Left-Turn Lane at OR 2 & 35th Line

    Source ID: county-award-tender-eng-2026-673

    Publisher
    Oxford County
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    register entry
    Passage / page
    TENDER-ENG-2026-673
    Evidence notes
    Full annual register downloaded and parsed. Contract-value field is -- for this entry; this is not proof the contract does not exist.

    Open in source library

  4. County construction projects — October 29 review

    Source ID: county-construction-20261029

    Publisher
    Oxford County
    Reporting period
    2026
    Reviewed
    2026-10-29
    Retrieved
    2026-10-29
    Verified
    2026-10-29
    Evidence status
    verified_primary
    Decision / approval status
    official source
    Passage / page
    Named road, bridge, culvert and water/wastewater project sections
    Evidence notes
    Current central-page text was reviewed. Named completion notices apply only to their stated scope; a passed target is not proof of completion. Newer linked PDF handouts were not all independently read.

    Open in source library

  5. Approved 2026 Business Plan and Budget

    Source ID: county-budget2026-p5

    Publisher
    Oxford County
    Published
    2026-01-14
    Event / reporting date
    2025-12-10
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    approved
    Passage / page
    PDF page 5; printed page 5
    Evidence notes
    File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

    Open in source library

  6. Business plans and budgets

    Source ID: county-budget-hub

    Publisher
    Oxford County
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    official approval summary
    Passage / page
    2026 approved budget section
    Evidence notes
    The hub reports $406.1 million total and $278.2 million operating, while the approved detailed PDF reports $406,890,915 and $279,035,275.

    Open in source library

  7. Approved 2026 Business Plan and Budget

    Source ID: county-budget2026-p58

    Publisher
    Oxford County
    Published
    2026-01-14
    Event / reporting date
    2025-12-10
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    approved
    Passage / page
    PDF page 58; printed page 58
    Evidence notes
    File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.