03ProjectsZorra

Zorra · Project

Bridge 140, 33rd Line over Trout Creek

Money & projects Explore sections
Zorra project

At a glance

Location
Zorra
Responsible authority
Zorra
Current stage
Additional reserve funding and AJN award authorizedAs of 2026-08-13
Revised budget
$224,072.69
Next target
No next date listed
Named supplier
AJN Builders Inc. See contract details

Bridge 140, 33rd Line over Trout Creek

Who approves and delivers this project?

Budget authority

Township Council

Approves annual allocation; delivery and contract authority must be traced separately.

Open the source record
  1. 2026 final operating budget and ten-year capital plan, report 2025-130 PDF pp. 1–95; account and project pages retained in rows

    Township of Zorra · Published 2025-12-03 · Event/reporting date 2025-12-03

    adopted · Primary record verified · Final council-approved schedules. 2025 comparatives restated; 2024 not restated. Capital is excluded from the 2026 operating schedule.

Money

How the budget changed

+$44,072.69 · 24.5% higher authorization

  1. Original budget$180,000
  2. Revised budget$224,072.69
Budget authorization, not money paid.

Project money

Budget and forecast

Original published budget
$180,000
Revised published budget
$224,072.69

Annual allocation

2026 allocation
$180,000
2026 Bridge 140 allocation increased by $44,072.69; new ceiling includes contingency and non-rebatable HST

Latest spending total not published here.

CAD · Source budget basis; HST treatment not separately stated · 2026 Bridge 140 allocation increased by $44,072.69; new ceiling includes contingency and non-rebatable HST
Sources for these figures · 3
  1. 2026 final operating budget and ten-year capital plan, report 2025-130PDF pp. 1–95; account and project pages retained in rows
  2. August 13, 2026 Council minutespp. 4–9, resolutions 07–20
  3. Report 2026-084: Bridge 140 and Bridge Culvert 70 tender resultspp. 1–2; paired with carried resolution 07-08-2026
3 source records
  1. 2026 final operating budget and ten-year capital plan, report 2025-130 PDF pp. 1–95; account and project pages retained in rows

    Township of Zorra · Published 2025-12-03 · Event/reporting date 2025-12-03

    adopted · Primary record verified · Final council-approved schedules. 2025 comparatives restated; 2024 not restated. Capital is excluded from the 2026 operating schedule.

  2. August 13, 2026 Council minutes pp. 4–9, resolutions 07–20

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified

  3. Report 2026-084: Bridge 140 and Bridge Culvert 70 tender results pp. 1–2; paired with carried resolution 07-08-2026

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Bridge 140 amount includes contingency and non-rebatable HST. Do not confuse joint bid $258,664 before HST with Bridge 140 award authorization $224,072.69 after HST rebate.

Where the funding comes from

$180,000Listed funding total

  1. ReservesCapital plan allocation
    $180,000100% of listed total
Listed funding adds to the 2026 allocation amount. CAD.
Sources for these figures · 3
  1. 2026 final operating budget and ten-year capital plan, report 2025-130PDF pp. 1–95; account and project pages retained in rows
  2. August 13, 2026 Council minutespp. 4–9, resolutions 07–20
  3. Report 2026-084: Bridge 140 and Bridge Culvert 70 tender resultspp. 1–2; paired with carried resolution 07-08-2026

Timeline

  1. approval

    Annual allocation adopted

    Budget allocation is not a contract award or completion record.

    Open the source record
    1. 2026 final operating budget and ten-year capital plan, report 2025-130 PDF pp. 1–95; account and project pages retained in rows

      Township of Zorra · Published 2025-12-03 · Event/reporting date 2025-12-03

      adopted · Primary record verified · Final council-approved schedules. 2025 comparatives restated; 2024 not restated. Capital is excluded from the 2026 operating schedule.

  2. award

    Funding increased and contract award authorized

    2 source records
    1. August 13, 2026 Council minutes pp. 4–9, resolutions 07–20

      Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

      published · Primary record verified

    2. Report 2026-084: Bridge 140 and Bridge Culvert 70 tender results pp. 1–2; paired with carried resolution 07-08-2026

      Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

      published · Primary record verified · Bridge 140 amount includes contingency and non-rebatable HST. Do not confuse joint bid $258,664 before HST with Bridge 140 award authorization $224,072.69 after HST rebate.

Contracts

2026-08 · Award authorized by Council

Bridge 140 rehabilitation

AJN Builders Inc. · 2026-08-13

Published bid
$195,664
Published award / contract value
$224,072.69
Unit price
Not established

Award ceiling includes proportionate contingency and non-rebatable HST; base bid excludes HST

Joint tender also includes Bridge Culvert 70. Do not add entire joint bid to the authorized Bridge 140 amount. Final payments unknown.

2 source records
  1. August 13, 2026 Council minutes pp. 4–9, resolutions 07–20

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified

  2. Report 2026-084: Bridge 140 and Bridge Culvert 70 tender results pp. 1–2; paired with carried resolution 07-08-2026

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Bridge 140 amount includes contingency and non-rebatable HST. Do not confuse joint bid $258,664 before HST with Bridge 140 award authorization $224,072.69 after HST rebate.

Open procurement record

Decisions

2026-08-13 · 07-08-2026

Increase Bridge 140 funding and award AJN Builders

Carried

$44,072.69 · Additional Bridge Reserve authority for Bridge 140

Consequence: Bridge 140 award authorization $224,072.69 after HST rebate, funded from other bridge project allocations.

2 source records
  1. August 13, 2026 Council minutes pp. 4–9, resolutions 07–20

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified

  2. Report 2026-084: Bridge 140 and Bridge Culvert 70 tender results pp. 1–2; paired with carried resolution 07-08-2026

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Bridge 140 amount includes contingency and non-rebatable HST. Do not confuse joint bid $258,664 before HST with Bridge 140 award authorization $224,072.69 after HST rebate.

Outcomes

Completion not confirmed.

Questions

  • What is the latest committed cost, spending to date and completion milestone?
Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

Open the full money explanation