Award / contract$224,072.69AJN Builders Inc. · 2026-08-13
Recorded paymentsAmount not publishedNo payment amounts attached
Award ceiling includes proportionate contingency and non-rebatable HST; base bid excludes HST · Bid, award and payment are separate measures. No price-change calculation is inferred between them.
Joint tender also includes Bridge Culvert 70. Do not add entire joint bid to the authorized Bridge 140 amount. Final payments unknown.
Report 2026-112 says Bridge 140 work on 33rd Line between Road 96 and Road 98 started October 5 and was completed with the road reopened within two weeks. Prepared for the November 4 council meeting; no exact reopening day is stated.
Zorra
Complete per staff report; road reopened
Revised budget
$224,072.69
Named supplier
AJN Builders Inc.
Next target
No next date listed
Latest update
2026-10-30 · Bridge 140 work complete; 33rd Line reopened
Open project →
What still needs an answer
What was the final completed-work cost?
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
pp. 1–2; paired with carried resolution 07-08-2026
Evidence notes
Bridge 140 amount includes contingency and non-rebatable HST. Do not confuse joint bid $258,664 before HST with Bridge 140 award authorization $224,072.69 after HST rebate.