2026-08-13 · 07-08-2026
Carried
$44,072.69 · Additional Bridge Reserve authority for Bridge 140
Consequence: Bridge 140 award authorization $224,072.69 after HST rebate, funded from other bridge project allocations.
2 source records August 13, 2026 Council minutes pp. 4–9, resolutions 07–20 Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13
published · Primary record verified
Report 2026-084: Bridge 140 and Bridge Culvert 70 tender results pp. 1–2; paired with carried resolution 07-08-2026 Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13
published · Primary record verified · Bridge 140 amount includes contingency and non-rebatable HST. Do not confuse joint bid $258,664 before HST with Bridge 140 award authorization $224,072.69 after HST rebate.
What the decision changed +$44,072.69 authorization
Before the decision $180,000 After the decision $224,072.69 Bridge 140 authorization includes contingency and non-rebatable HST. Sources for these figures · 2 August 13, 2026 Council minutes pp. 4–9, resolutions 07–20 Report 2026-084: Bridge 140 and Bridge Culvert 70 tender results pp. 1–2; paired with carried resolution 07-08-2026 Authority & recorded votes Township Council
Individual votes are not confirmed.
Connected projects Zorra · Roads & bridges
Bridge 140, 33rd Line over Trout Creek
Zorra
Additional reserve funding and AJN award authorized
Revised budget $224,072.69
Named supplier AJN Builders Inc.
Next target No next date listed
Latest update 2026-08-13 · Funding increased and contract award authorized Open project → Zorra · Roads & bridges
Bridge 70 rigid frame
Zorra
2026 funding approved · completion unconfirmed
2026 allocation $41,000
Next target No next date listed
Latest update 2026-08-13 · Increase Bridge 140 funding and award AJN Builders Open project → Copy this view Print