Development chargesDedicated 2026 capital account. See the budget row for financing timing.
$683,65018.6% of listed total
This is the total of the listed financing amounts. It is not a confirmed whole-project funding total. Financing and expenditure allocations can differ because of carryforward and timing; the project notes explain the published basis. CAD.
Timeline
recommendation
Multi-year award recommended
Staff recommend Kingdom Construction Limited at $13,267,340 excluding HST, plus RV Anderson Associates Limited inspection services at $940,110 excluding HST. Council disposition not verified.
The published bid does not establish the final executed contract value. Excludes HST
The opened agenda recommends this supplier and value. The actual minutes and executed contract were not extracted; this is not recorded as an awarded contract.
The opened agenda recommends this supplier and value. The actual minutes and executed contract were not extracted; this is not recorded as an awarded contract.
The $6 million 2026 expenditure allocation includes $5.4 million carryforward and $600,000 new funding. The financed 2026 amount is $3,683,631; the difference reflects financing timing. Later multi-year award recommendations are recorded separately. The March 11 agenda recommends a $13,267,340 construction award, a separate $940,110 engineering-inspection award, and future commitments of $5,815,746 in 2027 and $2,843,900 in 2028. Those future commitments are stated as included in the construction price; do not add them to it. Recommended debt ceilings are $6.5 million supported by development charges and $2.1 million supported by rates. All are recommendations until the Council disposition is verified.
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Named road, bridge, culvert and water/wastewater project sections
Evidence notes
Current central-page text was reviewed. Named completion notices apply only to their stated scope; a passed target is not proof of completion. Newer linked PDF handouts were not all independently read.