Oxford County procurementrecommended award; Council disposition not verified
Supplier
Not established in the reviewed record
Procurement method
Single source
Award date
Not established
Contract term
Multi-year project; construction notice targets May 2028 completion
From bid to payment
recommended award; Council disposition not verified
Published bidAmount not published
Recommendation$940,110RV Anderson Associates Limited
Award / contractAmount not published
Recorded paymentsAmount not publishedNo payment amounts attached
Excludes HST · Bid, award and payment are separate measures.
The opened agenda recommends this supplier and value. The actual minutes and executed contract were not extracted; this is not recorded as an awarded contract.
Recommendation awaiting a verified decision
RV Anderson Associates Limited · $940,110
A staff recommendation does not establish a Council award or an executed contract.
New two-storey headworks, aeration-roof removal, generator and process equipment.
Zorra
Multi-year construction planned May/June 2026–May 2028
2026 allocation
$6,000,000
Next target
2028-05 · Expected completion
Latest update
2026-03-11 · Multi-year award recommended
Open project →
What still needs an answer
Did Council carry or amend the recommended award?
What is the executed contract value and current approved project total?
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.