02Follow the moneyZorra

Zorra · Money

Follow the money.

Open the allocation. Check the actuals. Follow the decision into delivery.

Money & projects Explore sections
What do these money figures mean?
Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

These are Zorra’s finances. County finances are separate. See County projects located here.

Filters1 active
Reset
published interim report; annual comparative printed in reportoperating

2026 operating net costs through June 30

Non-overlapping department summary from published June 30 interim report; detailed capital rows remain separately linked. net departmental requirements · 2026 · CAD · Source accounting basis; net service costs include revenues and transfers

Original approved$12,917,962
Revised authorizationNot established
Reported actual$3,548,117.73Through 2026-06-30
Published forecastNot established
Budgeted revenue Not establishedNet levy / subsidy $12,917,962

Does the breakdown add up?

Source total $3,548,117.73Covered on the stated basis $3,548,117.73Reconciled difference $0

Nine department totals $3,548,117.73 less taxation $5,911,349.26 equal published overall net balance -$2,363,231.53.

Definitions, changes & interpretation
  • Nine department totals excluding taxation; $3,548,117.73 is derived by summing published department net amounts. Taxation received/booked is $5,911,349.26, producing the printed $2,363,231.53 interim surplus. Capital cost commitments, pending invoices and year-end allocations prevent treating this as savings. The $12,917,962 annual comparator is printed in this interim report; $88,000 above original adopted levy requires reconciliation, and must not silently overwrite V6 adopted budget.
Open the source record
  1. Report 2026-081: Financial Results to June 30, 2026 pp. 1–2 basis; pp. 3–6 finance table

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Interim operating report excludes capital costs as a project-spending measure and has pending allocations/reserve entries. Its taxation budget is $12,917,962 versus original adopted levy $12,829,962 in V6, a difference of $88,000 not yet reconciled by amendment evidence.

What is the total made of?

FiltersRefine results
Clear row filters

9 matching accounts. Parent totals include the indented accounts. — means no published amount.

Allocation by service

Zorra · 2026 · net departmental requirements · original

  1. Public transportation$7,115,257
  2. Protection services$2,969,040
  3. General recreation$1,745,974
  4. General government$652,235
  5. Health services$175,101
  6. Agriculture and drainage$164,442
  7. Robinson Pit$75,000
  8. Planning and development$32,713
  9. Environmental-$11,800
CAD · Largest 9 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below.
Open the source record
  1. Report 2026-081: Financial Results to June 30, 2026 pp. 1–2 basis; pp. 3–6 finance table

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Interim operating report excludes capital costs as a project-spending measure and has pending allocations/reserve entries. Its taxation budget is $12,917,962 versus original adopted levy $12,829,962 in V6, a difference of $88,000 not yet reconciled by amendment evidence.

2026 operating net costs through June 30 · 2026 · net departmental requirements · CAD
Service / facility / accountOriginal budgetActualEvidence
General government$652,235-$32,216.24Through 2026-06-30
Details & source

Year-end allocations and reserve transfers pending.

Open the source record
  1. Report 2026-081: Financial Results to June 30, 2026 pp. 1–2 basis; pp. 3–6 finance table

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Interim operating report excludes capital costs as a project-spending measure and has pending allocations/reserve entries. Its taxation budget is $12,917,962 versus original adopted levy $12,829,962 in V6, a difference of $88,000 not yet reconciled by amendment evidence.

Protection services$2,969,040$617,226.55Through 2026-06-30
Details & source

OPP May/June invoices not included at report cutoff; reserve transfers pending.

Open the source record
  1. Report 2026-081: Financial Results to June 30, 2026 pp. 1–2 basis; pp. 3–6 finance table

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Interim operating report excludes capital costs as a project-spending measure and has pending allocations/reserve entries. Its taxation budget is $12,917,962 versus original adopted levy $12,829,962 in V6, a difference of $88,000 not yet reconciled by amendment evidence.

General recreation$1,745,974$251,216.94Through 2026-06-30
Details & source

Seasonal operations and account allocations.

Open the source record
  1. Report 2026-081: Financial Results to June 30, 2026 pp. 1–2 basis; pp. 3–6 finance table

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Interim operating report excludes capital costs as a project-spending measure and has pending allocations/reserve entries. Its taxation budget is $12,917,962 versus original adopted levy $12,829,962 in V6, a difference of $88,000 not yet reconciled by amendment evidence.

Health services$175,101$122,584.82Through 2026-06-30
Details & source

Ingersoll Cemetery cost recovery occurs semi-annually.

Open the source record
  1. Report 2026-081: Financial Results to June 30, 2026 pp. 1–2 basis; pp. 3–6 finance table

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Interim operating report excludes capital costs as a project-spending measure and has pending allocations/reserve entries. Its taxation budget is $12,917,962 versus original adopted levy $12,829,962 in V6, a difference of $88,000 not yet reconciled by amendment evidence.

Planning and development$32,713-$46,271.85Through 2026-06-30
Details & source

Development charges to transfer at year-end; ROEDC invoice not received.

Open the source record
  1. Report 2026-081: Financial Results to June 30, 2026 pp. 1–2 basis; pp. 3–6 finance table

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Interim operating report excludes capital costs as a project-spending measure and has pending allocations/reserve entries. Its taxation budget is $12,917,962 versus original adopted levy $12,829,962 in V6, a difference of $88,000 not yet reconciled by amendment evidence.

Agriculture and drainage$164,442$37,918.39Through 2026-06-30
Details & source

Stormwater and debt allocations pending.

Open the source record
  1. Report 2026-081: Financial Results to June 30, 2026 pp. 1–2 basis; pp. 3–6 finance table

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Interim operating report excludes capital costs as a project-spending measure and has pending allocations/reserve entries. Its taxation budget is $12,917,962 versus original adopted levy $12,829,962 in V6, a difference of $88,000 not yet reconciled by amendment evidence.

Environmental-$11,800$654.88Through 2026-06-30
Details & source

Revenue recognition timing.

Open the source record
  1. Report 2026-081: Financial Results to June 30, 2026 pp. 1–2 basis; pp. 3–6 finance table

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Interim operating report excludes capital costs as a project-spending measure and has pending allocations/reserve entries. Its taxation budget is $12,917,962 versus original adopted levy $12,829,962 in V6, a difference of $88,000 not yet reconciled by amendment evidence.

Public transportation$7,115,257$2,592,158.50Through 2026-06-30
Details & source

Reserve transfers, wages and equipment allocations affect comparability.

Open the source record
  1. Report 2026-081: Financial Results to June 30, 2026 pp. 1–2 basis; pp. 3–6 finance table

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Interim operating report excludes capital costs as a project-spending measure and has pending allocations/reserve entries. Its taxation budget is $12,917,962 versus original adopted levy $12,829,962 in V6, a difference of $88,000 not yet reconciled by amendment evidence.

Robinson Pit$75,000$4,845.74Through 2026-06-30
Details & source
Open the source record
  1. Report 2026-081: Financial Results to June 30, 2026 pp. 1–2 basis; pp. 3–6 finance table

    Township of Zorra · Published 2026-08-13 · Event/reporting date 2026-08-13

    published · Primary record verified · Interim operating report excludes capital costs as a project-spending measure and has pending allocations/reserve entries. Its taxation budget is $12,917,962 versus original adopted levy $12,829,962 in V6, a difference of $88,000 not yet reconciled by amendment evidence.

From an allocation to a result

Zorra · Parks, recreation & culture

TDRC storage facility

TDRC storage facility

Zorra

Additional reserve authority approved; staff to negotiate with lowest bidder
Revised budget
$260,000
Next target
No next date listed
Latest update
2026-05-06 · Reserve increase approved

Zorra · Parks, recreation & culture

Thamesford multi-use courts

Courts will sit on donated parkland off Brock Street near the George Street extension, beside the planned school.

Zorra

Awarded; construction awaits development infrastructure
2026 allocation
$305,827
Next target
No next date listed
Latest update
2025-12-03 · Annual allocation adopted

Zorra · Other projects

New school gymnasium co-build

School plan includes 479 JK–Grade 4 places and 88 licensed childcare spaces, with a public-use gymnasium co-build.

Zorra

School and public gym co-build in progress
2026 allocation
$3,087,538
Next target
No next date listed
Latest update
2026-02-03 · Public information session held

Zorra · Roads & bridges

Bridge 640, 25th Line, Meathrell Creek

Bridge 640, 25th Line, Meathrell Creek

Zorra · South-West Oxford

Bridge rehabilitation completed July 24; road reopening awaited paving
2026 allocation
$1,322,880
Named supplier
Weathertech Restoration Services Inc.
Next target
No next date listed
Latest update
2026-07-24 · Bridge rehabilitation completed

Zorra · Roads & bridges

Bridge 140, 33rd Line over Trout Creek

Bridge 140, 33rd Line over Trout Creek

Zorra

Additional reserve funding and AJN award authorized
Revised budget
$224,072.69
Named supplier
AJN Builders Inc.
Next target
No next date listed
Latest update
2026-08-13 · Funding increased and contract award authorized

Zorra · Roads & bridges

Maintenance gravel haul

Maintenance gravel haul

Zorra

Gravel hauling and application completed June 12
Original budget
$305,000
Named supplier
E+W Blane Trucking
Next target
No next date listed
Latest update
2026-06-12 · Gravel work completed