2026 operating net costs through June 30
Non-overlapping department summary from published June 30 interim report; detailed capital rows remain separately linked. net departmental requirements · 2026 · CAD · Source accounting basis; net service costs include revenues and transfers
Original approved$12,917,962
Revised authorizationNot established
Reported actual$3,548,117.73Through 2026-06-30
Published forecastNot established
Budgeted revenue Not establishedNet levy / subsidy $12,917,962
Does the breakdown add up?
Source total $3,548,117.73Covered on the stated basis $3,548,117.73Reconciled difference $0
Nine department totals $3,548,117.73 less taxation $5,911,349.26 equal published overall net balance -$2,363,231.53.
Definitions, changes & interpretation
Nine department totals excluding taxation; $3,548,117.73 is derived by summing published department net amounts. Taxation received/booked is $5,911,349.26, producing the printed $2,363,231.53 interim surplus. Capital cost commitments, pending invoices and year-end allocations prevent treating this as savings. The $12,917,962 annual comparator is printed in this interim report; $88,000 above original adopted levy requires reconciliation, and must not silently overwrite V6 adopted budget.
CAD · Largest 9 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below.
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Interim operating report excludes capital costs as a project-spending measure and has pending allocations/reserve entries. Its taxation budget is $12,917,962 versus original adopted levy $12,829,962 in V6, a difference of $88,000 not yet reconciled by amendment evidence.
Report 2026-105 described construction on September 24, 2026. Acrylic surfacing might wait until April, and staff recommended a spring ceremony. The November 7 source check did not verify a public opening, finished surfacing or safety sign-off.
Zorra
Construction reported September 24; public opening unverified
2026 allocation
$305,827
Next target
No next date listed
Latest update
2026-09-24 · Construction reported; opening not established
Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.
Zorra · South-West Oxford
Complete per staff report; road reopened
2026 allocation
$1,322,880
Named supplier
Weathertech Restoration Services Inc.
Next target
No next date listed
Latest update
2026-10-30 · Road 92 and 25th Line paving complete
Report 2026-112 says Bridge 140 work on 33rd Line between Road 96 and Road 98 started October 5 and was completed with the road reopened within two weeks. Prepared for the November 4 council meeting; no exact reopening day is stated.
Zorra
Complete per staff report; road reopened
Revised budget
$224,072.69
Named supplier
AJN Builders Inc.
Next target
No next date listed
Latest update
2026-10-30 · Bridge 140 work complete; 33rd Line reopened