2025 audited earmarked reserves year-end reserve balance · 2025 · CAD · As reported in source; no HST conversion inferred
Budget / comparison balanceNot established
Revised balanceNot established
Reported balance$10,936,421Through 2025-12-31
Published forecastNot established
Does the breakdown add up?
Source total $10,936,421Covered on the stated basis $10,936,421Reconciled difference $0
Audited reserve-balance rows; not annual spending or unrestricted cash.
Definitions, changes & interpretation
Cash $8,868,548; net financial assets $2,848,201. Deferred obligatory reserves $1,191,127 separate. Net long-term liabilities $9,332,125; $43,923 tile-drain principal assumed by individuals separate. 2026 tax-supported principal schedule $865,853; interest paid in 2025 $436,344. Reserve totals are not cash.
CAD · Largest 5 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below.
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Report 2026-105 described construction on September 24, 2026. Acrylic surfacing might wait until April, and staff recommended a spring ceremony. The November 7 source check did not verify a public opening, finished surfacing or safety sign-off.
Zorra
Construction reported September 24; public opening unverified
2026 allocation
$305,827
Next target
No next date listed
Latest update
2026-09-24 · Construction reported; opening not established
Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.
Zorra · South-West Oxford
Complete per staff report; road reopened
2026 allocation
$1,322,880
Named supplier
Weathertech Restoration Services Inc.
Next target
No next date listed
Latest update
2026-10-30 · Road 92 and 25th Line paving complete
Report 2026-112 says Bridge 140 work on 33rd Line between Road 96 and Road 98 started October 5 and was completed with the road reopened within two weeks. Prepared for the November 4 council meeting; no exact reopening day is stated.
Zorra
Complete per staff report; road reopened
Revised budget
$224,072.69
Named supplier
AJN Builders Inc.
Next target
No next date listed
Latest update
2026-10-30 · Bridge 140 work complete; 33rd Line reopened