What do these money figures mean?
Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

These are Zorra’s finances. County finances are separate. See County projects located here.

Filters2 active
Reset
auditedreserve

2025 audited earmarked reserves

2025 audited earmarked reserves year-end reserve balance · 2025 · CAD · As reported in source; no HST conversion inferred

Budget / comparison balanceNot established
Revised balanceNot established
Reported balance$10,936,421Through 2025-12-31
Published forecastNot established

Does the breakdown add up?

Source total $10,936,421Covered on the stated basis $10,936,421Reconciled difference $0

Audited reserve-balance rows; not annual spending or unrestricted cash.

Definitions, changes & interpretation
  • Cash $8,868,548; net financial assets $2,848,201. Deferred obligatory reserves $1,191,127 separate. Net long-term liabilities $9,332,125; $43,923 tile-drain principal assumed by individuals separate. 2026 tax-supported principal schedule $865,853; interest paid in 2025 $436,344. Reserve totals are not cash.

What is the total made of?

Filters1 active
Clear row filters

5 matching accounts. Parent totals include the indented accounts. — means no published amount.

Reported actuals by service

Zorra · 2025 · year-end reserve balance · Actual through 2025-12-31

  1. Capital replacement$7,028,191
  2. General purposes$2,313,943
  3. Tax rate stabilization$867,505
  4. Working capital$677,103
  5. Insurance$49,679
CAD · Largest 5 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below.
2025 audited earmarked reserves · 2025 · year-end reserve balance · CAD
Service / facility / accountActualPrior actualEvidence
Working capital$677,103Through 2025-12-31$544,200
Details & source

Source location: PDF p. 15, note 9

General purposes$2,313,943Through 2025-12-31$2,069,125
Details & source

Source location: PDF p. 15, note 9

Capital replacement$7,028,191Through 2025-12-31$5,021,281
Details & source

Source location: PDF p. 15, note 9

Tax rate stabilization$867,505Through 2025-12-31$867,505
Details & source

Source location: PDF p. 15, note 9

Insurance$49,679Through 2025-12-31$39,679
Details & source

Source location: PDF p. 15, note 9

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. 2025 audited consolidated financial statements

    Source ID: zorra-audit2025

    Publisher
    Township of Zorra
    Published
    2026-07-15
    Event / reporting date
    2026-07-15
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    audited
    Passage / page
    PDF pp. 5–7 and 14–15; notes 8–9
    Evidence notes
    Unmodified audit report; year ended December 31, 2025.

    Open in source library

From an allocation to a result

Zorra · Parks, recreation & culture

TDRC storage facility

TDRC storage facility

Zorra

Additional reserve authority approved; staff to negotiate with lowest bidder
Revised budget
$260,000
Next target
No next date listed
Latest update
2026-05-06 · Reserve increase approved

Zorra · Parks, recreation & culture

Thamesford multi-use courts

Report 2026-105 described construction on September 24, 2026. Acrylic surfacing might wait until April, and staff recommended a spring ceremony. The November 7 source check did not verify a public opening, finished surfacing or safety sign-off.

Zorra

Construction reported September 24; public opening unverified
2026 allocation
$305,827
Next target
No next date listed
Latest update
2026-09-24 · Construction reported; opening not established

Zorra · Other projects

New school gymnasium co-build

School plan includes 479 JK–Grade 4 places and 88 licensed childcare spaces, with a public-use gymnasium co-build.

Zorra

School and public gym co-build in progress
2026 allocation
$3,087,538
Next target
No next date listed
Latest update
2026-02-03 · Public information session held

Zorra · Roads & bridges

Bridge 640, 25th Line, Meathrell Creek

Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.

Zorra · South-West Oxford

Complete per staff report; road reopened
2026 allocation
$1,322,880
Named supplier
Weathertech Restoration Services Inc.
Next target
No next date listed
Latest update
2026-10-30 · Road 92 and 25th Line paving complete

Zorra · Roads & bridges

Bridge 140, 33rd Line over Trout Creek

Report 2026-112 says Bridge 140 work on 33rd Line between Road 96 and Road 98 started October 5 and was completed with the road reopened within two weeks. Prepared for the November 4 council meeting; no exact reopening day is stated.

Zorra

Complete per staff report; road reopened
Revised budget
$224,072.69
Named supplier
AJN Builders Inc.
Next target
No next date listed
Latest update
2026-10-30 · Bridge 140 work complete; 33rd Line reopened

Zorra · Roads & bridges

Maintenance gravel haul

Maintenance gravel haul

Zorra

Gravel hauling and application completed June 12
Original budget
$305,000
Named supplier
E+W Blane Trucking
Next target
No next date listed
Latest update
2026-06-12 · Gravel work completed