Money & projects Explore sections
What do these money figures mean?
Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

These are Zorra’s finances. County finances are separate. See County projects located here.

Filters1 active
Reset
Council received; reserve table unauditedannual accounts

2025 Building Department operating and capital result

2025 Building Department operating and capital result department management report; revenues and expenses shown separately · 2025 · CAD · As reported in source; no HST conversion inferred

Original approvedNot established
Revised authorizationNot established
Reported actualNot establishedThrough 2025-12-31
Published forecastNot established

Does the breakdown add up?

Source total -$52,656.69Covered on the stated basis -$52,656.69Reconciled difference $0

Revenue minus expenditure; reserve draw is funding, not another expense.

Definitions, changes & interpretation
  • Operating revenue $286,507.24 less expense $339,163.93 = $52,656.69 deficit. Do not add revenue and expense rows as a spending total. Reserve opening $214,945.08 less deficit $52,656.69 and fee-review/capital draws $74,763.07 = $87,525.32 unaudited closing balance.

What is the total made of?

FiltersRefine results
Clear row filters

3 matching accounts. Parent totals include the indented accounts. — means no published amount.

Allocation by service

Zorra · 2025 · department management report; revenues and expenses shown separately · original

  1. Building revenues$385,000
  2. Building expenses$351,341
  3. Electric vehicle capital$70,000
CAD · Largest 3 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below.
2025 Building Department operating and capital result · 2025 · department management report; revenues and expenses shown separately · CAD
Service / facility / accountOriginal budgetActualPrior actualEvidence
Building revenues$385,000$286,507.24Through 2025-12-31$488,382.86
Details & source

Source location: PDF p. 3

Building expenses$351,341$339,163.93Through 2025-12-31$320,153.44
Details & source

Source location: PDF p. 3

Electric vehicle capital$70,000$69,675.07Through 2025-12-31—
Details & source

Source location: PDF p. 3

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. Report 2026-035: 2025 annual Building Department financial report

    Source ID: zorra-building2025

    Publisher
    Township of Zorra
    Published
    2026-05-06
    Event / reporting date
    2026-05-06
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published
    Passage / page
    PDF pp. 1–3
    Evidence notes
    Building reserve closing schedule explicitly unaudited; distinguish from July consolidated audit.

    Open in source library

From an allocation to a result

Zorra · Parks, recreation & culture

TDRC storage facility

TDRC storage facility

Zorra

Additional reserve authority approved; staff to negotiate with lowest bidder
Revised budget
$260,000
Next target
No next date listed
Latest update
2026-05-06 · Reserve increase approved

Zorra · Parks, recreation & culture

Thamesford multi-use courts

Report 2026-105 described construction on September 24, 2026. Acrylic surfacing might wait until April, and staff recommended a spring ceremony. The November 7 source check did not verify a public opening, finished surfacing or safety sign-off.

Zorra

Construction reported September 24; public opening unverified
2026 allocation
$305,827
Next target
No next date listed
Latest update
2026-09-24 · Construction reported; opening not established

Zorra · Other projects

New school gymnasium co-build

School plan includes 479 JK–Grade 4 places and 88 licensed childcare spaces, with a public-use gymnasium co-build.

Zorra

School and public gym co-build in progress
2026 allocation
$3,087,538
Next target
No next date listed
Latest update
2026-02-03 · Public information session held

Zorra · Roads & bridges

Bridge 640, 25th Line, Meathrell Creek

Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.

Zorra · South-West Oxford

Complete per staff report; road reopened
2026 allocation
$1,322,880
Named supplier
Weathertech Restoration Services Inc.
Next target
No next date listed
Latest update
2026-10-30 · Road 92 and 25th Line paving complete

Zorra · Roads & bridges

Bridge 140, 33rd Line over Trout Creek

Report 2026-112 says Bridge 140 work on 33rd Line between Road 96 and Road 98 started October 5 and was completed with the road reopened within two weeks. Prepared for the November 4 council meeting; no exact reopening day is stated.

Zorra

Complete per staff report; road reopened
Revised budget
$224,072.69
Named supplier
AJN Builders Inc.
Next target
No next date listed
Latest update
2026-10-30 · Bridge 140 work complete; 33rd Line reopened

Zorra · Roads & bridges

Maintenance gravel haul

Maintenance gravel haul

Zorra

Gravel hauling and application completed June 12
Original budget
$305,000
Named supplier
E+W Blane Trucking
Next target
No next date listed
Latest update
2026-06-12 · Gravel work completed