South-West Oxford · Evidence coverage
Hold this record to account, too.
See exactly which records were reviewed, what has been extracted and what still needs checking.
Money & projects Explore sections
Research method and coverage examples
Baseline financial extraction cutoff: 2026-10-01. Selected records were refreshed October 29; individual sources retain their actual review dates. Coverage is described by authority and record type. A failed retrieval is an access problem, not proof of non-disclosure.
Select a municipality above or expand its research below. Original sources and research limits are retained.
South-West Oxford
History window: January 1, 2026–2026-10-01. Active project origins may precede this window. Selected project-linked decisions are published; this is not a complete register of every resolution.
History sources and coverage boundary
- Requested history begins
- 2026-01-01
- Research cutoff
- 2026-10-01
- completeness
- No
- reviewed Scope
- Selected January-September 2026 project-linked minutes, original staff reports, tender awards, audited accounts and management year-end schedules. January20 truck purchase/hub shortlist; April7 asphalt award; July14 hub/Centreville/audit decisions; August11 awards, deferral and reserves; September15 childcare proposal and September24 Centreville request. Earlier still-active 2024-2025 contract origins retained.
- reviewed Meeting Dates
- 2026-01-20
- 2026-04-07
- 2026-07-14
- 2026-08-11
- 2026-09-15
- 2026-09-24
- record Status By Meeting
- Adopted minutes: purchase and procurement-shortlist decisions. Adopted minutes and asphalt report. Adopted minutes and original hub/Centreville reports. Adopted minutes and original roof/gravel/year-end reports. Original childcare MOU proposal; adopted outcome not verified. Special meeting agenda and CAO48-2026 original report; adopted minutes not posted in reviewed index at cutoff, outcome unconfirmed.
- earlier Baselines
- 2025-12-16 final adopted 2026 budget
- 2025-11-10 detailed working budget explicitly superseded
- 2025-03-04 two-season grass-cutting award
- Selected 2024-2025 drain/road awards with completion not established
- 2025 audited accounts and management year-end actuals
- Actuals reporting cutoff
- 2026-06-30
- Coverage limit
- Bounded project-linked history, not all Council decisions or the complete current-year expenditure/award/change register. Superseded draft accounts do not establish final adopted account allocations.
- Scope notes
- V7 adds June 30 net departmental figures and selected later delivery updates. Original approvals and reporting periods remain separate.
10 source records
- January 20, 2026 Council minutes
- Publisher
- Township of South West Oxford
- Published
- 2026-01-20
- Event / reporting date
- 2026-01-20
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- approved minutes
- Passage / page
- PDF pp. 2–5; resolutions 4 and 8
- Evidence notes
- Waste truck purchase and civic-hub prequalification.
- April 7, 2026 Council minutes
- Publisher
- Township of South West Oxford
- Published
- 2026-04-07
- Event / reporting date
- 2026-04-07
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- approved minutes
- Passage / page
- PDF p. 4, resolution 7: 2026 asphalt award
- Evidence notes
- Approves Permanent Paving bid plus applicable taxes.
- July 14, 2026 Council minutes
- Publisher
- Township of South West Oxford
- Published
- 2026-07-14
- Event / reporting date
- 2026-07-14
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- approved minutes
- Passage / page
- Resolutions 4, 15, 17, 19, 22–23
- Evidence notes
- Audit approval; Centreville increase; hub report received; airport request declined; financing by-law.
- August 11, 2026 Council minutes
- Publisher
- Township of South West Oxford
- Published
- 2026-08-11
- Event / reporting date
- 2026-08-11
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- approved minutes
- Passage / page
- Resolutions 13, 14, 17, 18 and 22
- Evidence notes
- Roof/gravel awards, Museum deferral, reserve transfers and accounts-payable approval.
- CAO45-2026: Oxford Community Child Care MOU
- Publisher
- Township of South West Oxford
- Published
- 2026-09-15
- Event / reporting date
- 2026-09-15
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- published
- Passage / page
- PDF pp. 1–10; MOU space, occupancy and conditions
- Evidence notes
- Staff recommendation and proposed MOU; not an executed lease or confirmed opening date.
- CAO48-2026: Centreville gabion project and additional funding
- Publisher
- Township of South West Oxford
- Published
- 2026-09-24
- Event / reporting date
- 2026-09-24
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- published
- Passage / page
- PDF pp. 1–4; contract, urgency, funding options
- Evidence notes
- September 15 had not approved additional $40k; September 24 minutes not posted in reviewed official index as of cutoff. Do not call recommendation approved.
- Official bids and tenders: published award archive
- Publisher
- Township of South West Oxford
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- published
- Passage / page
- Awarded tenders section: grass cutting, Piper Drain, asphalt, Strik Drain
- Evidence notes
- Primary archive opened; later closed tenders are not automatically awards.
- December 16, 2025 Council minutes: By-law 77-2025
- Publisher
- Township of South West Oxford
- Published
- 2025-12-16
- Event / reporting date
- 2025-12-16
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- adopted
- Passage / page
- Resolution 14; adoption of 2026 estimates
- Evidence notes
- Final adopted schedule controls over November 10 draft.
- 2025 audited consolidated financial statements
- Publisher
- Township of South West Oxford
- Published
- 2026-07-14
- Event / reporting date
- 2026-07-14
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- audited
- Passage / page
- PDF pp. 5–6 and 14–15: statements and notes 9–10
- Evidence notes
- Original scanned PDF downloaded; key pages OCR-extracted and statement of operations visually checked. Council approved July 14.
- TR12-2026: 2025 surplus/deficit and reserve allocation
- Publisher
- Township of South West Oxford
- Published
- 2026-08-11
- Event / reporting date
- 2026-08-11
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- published
- Passage / page
- PDF pp. 1–15: year-end service and asset actuals; reserve continuity
- Evidence notes
- Management net-budget basis. 2026 reserve column is projected after transfers, not audited 2026 closing cash.
10 budget schedules · 965 extracted allocation rows · 23 projects · 11 procurement records · 18 decisions
Extracted 2026 decision dates: 2026-01-20 · 2026-04-07 · 2026-07-14 · 2026-08-11 · 2026-09-01 · 2026-09-15 · 2026-10-06 · 2026-10-20. These dates are not a list of all meetings reviewed.
| Record type | Research state | Coverage & remaining question |
|---|---|---|
| Approved operating budget | Primary record verified | Complete final combined expenditure and net levy schedules Limit: January–September 2026 source review with earlier active-contract origins. Not a claim every decision, project or invoice is indexed. November draft account numbers remain explicitly superseded. Next question: Publish the final adopted account export, latest committed spending and complete 2026 award/change register. Search boundary
3 source records
|
| Approved capital budget | Primary record verified | Capital within adopted combined budget; major preliminary hub provision Limit: Adopted capital is embedded in a combined budget. Only separately labelled lines and the staff-confirmed preliminary hub authorization are extracted as approved capital; no invented total-capital headline. Next question: Publish the final adopted account export, latest committed spending and complete 2026 award/change register. Search boundary
3 source records
|
| Detailed service & account schedules | Primary record verified | Final 38-row spending schedule; superseded full working account ledger; detailed 2025 actual service/asset ledger Limit: January–September 2026 source review with earlier active-contract origins. Not a claim every decision, project or invoice is indexed. November draft account numbers remain explicitly superseded. Next question: Publish the final adopted account export, latest committed spending and complete 2026 award/change register. Search boundary
4 source records
|
| Amendments & carryforwards | Primary record verified | July Centreville increase, September request, Museum deferral and reserve transfers Limit: January–September 2026 source review with earlier active-contract origins. Not a claim every decision, project or invoice is indexed. November draft account numbers remain explicitly superseded. Next question: Publish the final adopted account export, latest committed spending and complete 2026 award/change register. Search boundary
4 source records
|
| Latest interim actuals | Primary record verified | 2026 net departmental budget-to-actual schedule through June 30; eleven non-overlapping parent totals extracted. Limit: Net cost/financing basis; not gross expenditure or full project payment register. Next question: What has changed since June 30, and which invoices remain unposted? Search boundary
Open the source record
|
| Audited annual accounts | Primary record verified | 2025 consolidated accounts approved July 14 Limit: January–September 2026 source review with earlier active-contract origins. Not a claim every decision, project or invoice is indexed. November draft account numbers remain explicitly superseded. Next question: Publish the final adopted account export, latest committed spending and complete 2026 award/change register. Search boundary
2 source records
|
| Funding, reserves & debt | Primary record verified | Final financing, management reserve continuity and audited debt/reserves Limit: January–September 2026 source review with earlier active-contract origins. Not a claim every decision, project or invoice is indexed. November draft account numbers remain explicitly superseded. Next question: Publish the final adopted account export, latest committed spending and complete 2026 award/change register. Search boundary
4 source records
|
| Active projects & timelines | Primary record verified | Hub, park, Centreville, roads, maintenance and local community works Limit: January–September 2026 source review with earlier active-contract origins. Not a claim every decision, project or invoice is indexed. November draft account numbers remain explicitly superseded. Next question: Publish the final adopted account export, latest committed spending and complete 2026 award/change register. Search boundary
6 source records
|
| Procurement & awards | Primary record verified | Published active earlier awards and verified 2026 award decisions Limit: January–September 2026 source review with earlier active-contract origins. Not a claim every decision, project or invoice is indexed. November draft account numbers remain explicitly superseded. Next question: Publish the final adopted account export, latest committed spending and complete 2026 award/change register. Search boundary
5 source records
|
| Responsibility & decisions | Primary record verified | Council decisions separated from staff recommendations and UTRCA contracting Limit: January–September 2026 source review with earlier active-contract origins. Not a claim every decision, project or invoice is indexed. November draft account numbers remain explicitly superseded. Next question: Publish the final adopted account export, latest committed spending and complete 2026 award/change register. Search boundary
5 source records
|
| Payments & contract changes | Not found in sources reviewed | Project-specific invoices and executed change orders Limit: Council AP aggregate approvals are available but do not attribute actual paid amounts to individual projects. Next question: What has been paid against the hub, roads, grass contract and Centreville, with change orders? 2 source records
|
| Candidate & official evidence | Not applicable | Separate countywide candidate evidence workstream Limit: Collective Council outcomes cannot be assigned as individual votes without a recorded vote. |
What the labels mean
- Available captions reviewed; audio and written outcome not verified
- Awaiting review before factual publication.
- Primary record verified
- The primary record was opened and the published fields checked. This is not a transaction audit.
- Source located; extraction incomplete
- A source exists, but this edition has not extracted all relevant detail.
- Not found in sources reviewed
- The bounded search did not locate the record. Its absence is not proof that the authority does not publish it.
- Source temporarily inaccessible
- A located source could not be retrieved by the available methods.
- Records need reconciliation
- Two records differ and have not been fully reconciled.
- Not applicable
- This record type does not apply to the item.
- Extracted; review pending
- Awaiting review before factual publication.
Make sense of the money+
Make sense of the money
Your taxes called. They’d like a receipt.
- Budget
- Planned costs for a stated year or project.
- Annual allocation
- Funding assigned for one year. It may be part of a larger project.
- Lifetime project budget
- The stated budget for the full project across its years.
- Forecast
- An estimate of the eventual cost, as of the date shown.
- Tax requirement (levy)
- The amount to raise from property taxes, after other funding.
- Contract award
- The accepted contract price, with its stated tax and scope.
- Recorded costs or payments
- Amounts reported for the period shown. They do not establish project completion.
County spending and County taxes explained →
Open the full money explanation