Zorra · Evidence coverage
Hold this record to account, too.
See exactly which records were reviewed, what has been extracted and what still needs checking.
Money & projects Explore sections
Research method and coverage examples
Baseline financial extraction cutoff: 2026-10-01. Selected records were refreshed October 29; individual sources retain their actual review dates. Coverage is described by authority and record type. A failed retrieval is an access problem, not proof of non-disclosure.
Select a municipality above or expand its research below. Original sources and research limits are retained.
Zorra
History window: January 1, 2026–2026-10-01. Active project origins may precede this window. Selected project-linked decisions are published; this is not a complete register of every resolution.
History sources and coverage boundary
- Requested history begins
- 2026-01-01
- Research cutoff
- 2026-10-01
- completeness
- No
- reviewed Scope
- Full adopted 2026 financial/capital schedules; selected first-quarter road and recreation delivery records and awards; May 6 reserve-amendment/building-deficit decisions; May court-tender status; 2025 audited accounts issued July 15. Project status is bounded to its source report and is not presumed current in October.
- reviewed Meeting Dates
- 2026-05-06
- record Status By Meeting
- Adopted minutes and original storage/building reports reviewed; Q1 roads report bears inconsistent April15 header and April30 signoff, retained in source note.
- earlier Baselines
- 2025-12-03 adopted 2026 budget and capital plan
- 2024-07-03 staff dust-suppressant recommendation for 2025-2027 term; adoption not verified
- 2025 audited consolidated accounts
- Actuals reporting cutoff
- 2026-06-30
- Coverage limit
- Not a complete January-September Council/project decision register. Later in-year financial/project updates, completion certificates, executed changes and payments remain unverified in this dataset.
- Scope notes
- V7 adds June 30 net departmental figures and selected later delivery updates. Original approvals and reporting periods remain separate.
9 source records
- 2026 final operating budget and ten-year capital plan, report 2025-130
- Publisher
- Township of Zorra
- Published
- 2025-12-03
- Event / reporting date
- 2025-12-03
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- adopted
- Passage / page
- PDF pp. 1–95; account and project pages retained in rows
- Evidence notes
- Final council-approved schedules. 2025 comparatives restated; 2024 not restated. Capital is excluded from the 2026 operating schedule.
- Official finance page: 2026 budget and By-law 2025-51
- Publisher
- Township of Zorra
- Published
- 2025-12-03
- Event / reporting date
- 2025-12-03
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- adopted
- Passage / page
- 2026 budget links
- Evidence notes
- Adoption corroborates final report; draft November report has different totals.
- Report 2026-033: Roads Division Q1 update
- Publisher
- Township of Zorra
- Published
- 2026-05-06
- Event / reporting date
- 2026-05-06
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- published
- Passage / page
- PDF pp. 1–3; tender results and project update
- Evidence notes
- Report header says April 15, approval April 30; May 6 Council agenda receives it. Event date uses Council receipt; inconsistent header retained in note.
- Recreation and Facilities seasonal update Q1
- Publisher
- Township of Zorra
- Published
- 2026-05-06
- Event / reporting date
- 2026-05-06
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- published
- Passage / page
- PDF pp. 1–2 capital status and p. 6 facility utilization
- Evidence notes
- Status is as of report, not a fabricated October completion.
- May 6, 2026 Council minutes
- Publisher
- Township of Zorra
- Published
- 2026-05-06
- Event / reporting date
- 2026-05-06
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- approved minutes
- Passage / page
- Resolutions 12-05-2026 and 18-05-2026
- Evidence notes
- Carried motions; no roll-call supplied for these decisions.
- Report 2026-046: TDRC storage shed tender results
- Publisher
- Township of Zorra
- Published
- 2026-05-06
- Event / reporting date
- 2026-05-06
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- published
- Passage / page
- PDF pp. 1–4; full 11-bid table p. 4
- Evidence notes
- Lowest bid and negotiation authority do not establish an executed construction award.
- Report 2026-035: 2025 annual Building Department financial report
- Publisher
- Township of Zorra
- Published
- 2026-05-06
- Event / reporting date
- 2026-05-06
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- published
- Passage / page
- PDF pp. 1–3
- Evidence notes
- Building reserve closing schedule explicitly unaudited; distinguish from July consolidated audit.
- Thamesford multi-use court tender portal
- Publisher
- Township of Zorra
- Published
- 2026-05-13
- Event / reporting date
- 2026-05-13
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- published
- Passage / page
- Bid status and public bid summary
- Evidence notes
- Portal shows awarded status; accessible bid summary shows Van Roestel total, while dynamic award-vendor rows were not exposed. Tax basis not given in accessible summary.
- 2025 audited consolidated financial statements
- Publisher
- Township of Zorra
- Published
- 2026-07-15
- Event / reporting date
- 2026-07-15
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- audited
- Passage / page
- PDF pp. 5–7 and 14–15; notes 8–9
- Evidence notes
- Unmodified audit report; year ended December 31, 2025.
7 budget schedules · 759 extracted allocation rows · 41 projects · 20 procurement records · 7 decisions
Extracted 2026 decision dates: 2026-05-06 · 2026-08-13. These dates are not a list of all meetings reviewed.
| Record type | Research state | Coverage & remaining question |
|---|---|---|
| Approved operating budget | Primary record verified | Final approved levy and detailed signed accounts Limit: The reviewed sources do not establish a full 2026 invoice or change-order register. Next question: Publish latest commitments, change orders and completion certificates. Search boundary
2 source records
|
| Approved capital budget | Primary record verified | Complete 38-row 2026 project allocation register Limit: The reviewed sources do not establish a full 2026 invoice or change-order register. Next question: Publish latest commitments, change orders and completion certificates. Search boundary
2 source records
|
| Detailed service & account schedules | Primary record verified | Account-level operating and project-level capital rows Limit: The reviewed sources do not establish a full 2026 invoice or change-order register. Next question: Publish latest commitments, change orders and completion certificates. Search boundary
Open the source record
|
| Amendments & carryforwards | Primary record verified | Storage project $60,000 amendment with 2027 deferral Limit: The reviewed sources do not establish a full 2026 invoice or change-order register. Next question: Publish latest commitments, change orders and completion certificates. Search boundary
2 source records
|
| Latest interim actuals | Primary record verified | 2026 interim operating net requirements through June 30; nine parent departments extracted. Limit: Not capital project spending; pending invoices and allocations. Annual comparator differs by $88,000 from V6 original adopted levy. Next question: Which entries explain the $88,000 budget comparator difference and the later capital expenditure position? Search boundary
Open the source record
|
| Audited annual accounts | Primary record verified | 2025 consolidated financial statements Limit: The reviewed sources do not establish a full 2026 invoice or change-order register. Next question: Publish latest commitments, change orders and completion certificates. Search boundary
Open the source record
|
| Funding, reserves & debt | Primary record verified | Capital financing and audited debt/reserves Limit: The reviewed sources do not establish a full 2026 invoice or change-order register. Next question: Publish latest commitments, change orders and completion certificates. Search boundary
2 source records
|
| Active projects & timelines | Primary record verified | Roads/recreation status and project register Limit: The reviewed sources do not establish a full 2026 invoice or change-order register. Next question: Publish latest commitments, change orders and completion certificates. Search boundary
4 source records
|
| Procurement & awards | Primary record verified | Four explicit 2026 staff-reported awards; full shed bid table; other procurement stages separated Limit: The reviewed sources do not establish a full 2026 invoice or change-order register. Next question: Publish latest commitments, change orders and completion certificates. Search boundary
3 source records
|
| Responsibility & decisions | Primary record verified | Carried reserve approvals and delegated award report Limit: The reviewed sources do not establish a full 2026 invoice or change-order register. Next question: Publish latest commitments, change orders and completion certificates. Search boundary
2 source records
|
| Payments & contract changes | Not found in sources reviewed | Project-specific actual payments and executed changes Limit: Award amounts and reserve authority are not payments. Next question: What has been paid against each contract and what changes were executed? 2 source records
|
| Candidate & official evidence | Not applicable | Candidate evidence compiled in separate countywide workstream Limit: Collective decisions do not establish every councillor’s personal position. |
What the labels mean
- Available captions reviewed; audio and written outcome not verified
- Awaiting review before factual publication.
- Primary record verified
- The primary record was opened and the published fields checked. This is not a transaction audit.
- Source located; extraction incomplete
- A source exists, but this edition has not extracted all relevant detail.
- Not found in sources reviewed
- The bounded search did not locate the record. Its absence is not proof that the authority does not publish it.
- Source temporarily inaccessible
- A located source could not be retrieved by the available methods.
- Records need reconciliation
- Two records differ and have not been fully reconciled.
- Not applicable
- This record type does not apply to the item.
- Extracted; review pending
- Awaiting review before factual publication.
Make sense of the money+
Make sense of the money
Your taxes called. They’d like a receipt.
- Budget
- Planned costs for a stated year or project.
- Annual allocation
- Funding assigned for one year. It may be part of a larger project.
- Lifetime project budget
- The stated budget for the full project across its years.
- Forecast
- An estimate of the eventual cost, as of the date shown.
- Tax requirement (levy)
- The amount to raise from property taxes, after other funding.
- Contract award
- The accepted contract price, with its stated tax and scope.
- Recorded costs or payments
- Amounts reported for the period shown. They do not establish project completion.
County spending and County taxes explained →
Open the full money explanation