02Follow the moneyEast Zorra-Tavistock

East Zorra-Tavistock · Suppliers

Vandenberk Construction

Money & projects Explore sections

Vandenberk Construction

1 linked procurement records · 0 disclosed payment allocations · East Zorra-Tavistock

East Zorra-Tavistock · CAO2026-17 / October 21 motion

Culvert 2015 replacement contractor: written bid acceptance

Bid acceptance recorded in written minutes; adoption unverified

Published bid
$373,454.20
Published award / contract value
$373,454.20
Unit price
Not established

Accepted bid exclusive of taxes; $50,000 contingency specified separately in staff report, if needed. An executed contract and payment are not established.

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →