Award / contract$373,454.20Vandenberk Construction · 2026-10-21
Recorded paymentsAmount not publishedNo payment amounts attached
Accepted bid exclusive of taxes; $50,000 contingency specified separately in staff report, if needed. An executed contract and payment are not established. · Bid, award and payment are separate measures. No price-change calculation is inferred between them.
Posted October 21 written minutes record a carried motion accepting Vandenberk Construction Inc.’s bid of $373,454.20 exclusive of taxes, with contingency if needed, and authorizing the CAO and Treasurer to sign. The staff report specifies $50,000 contingency; the motion does not repeat that amount. Formal minutes adoption, an executed agreement and completion have not been verified. The earlier caption evidence remains historical; no individual voting record or independent audio review is inferred.
Posted October 21 written minutes record a carried motion accepting Vandenberk Construction Inc.’s bid of $373,454.20 exclusive of taxes, with contingency if needed, and authorizing the CAO and Treasurer to sign. The staff report specifies $50,000 contingency; the motion does not repeat that amount. Formal minutes adoption, an executed agreement and completion have not been verified.
East Zorra-Tavistock
Bid acceptance recorded in written minutes; adoption unverified
2026 allocation
$600,000
Named supplier
Vandenberk Construction
Next target
No next date listed
Latest update
2026-10-21 · Written minutes record bid acceptance
Open project →
What still needs an answer
Where are the adopted minutes, executed replacement agreement and completion record?
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
staff-reported termination; replacement award unverified
Passage / page
Report pages 1–2
Evidence note
Primary-source body reviewed in the October 30 audit No October 21 minutes linked. Replacement award and completion unverified. Original capital budget $600,000; paid-to-date $130,486.98 reported.
39:54–40:37 of 42:02; motion called carried at 40:34/40:37
Evidence note
Only the target caption window was reviewed. Correct contractor, amount and $50,000 contingency come from written CAO2026-17 report. Audio, written minutes, individual votes, executed agreement and completion were not independently verified.
Posted written minutes record a carried motion. Formal adoption at the November 4 meeting was not verified. Signing authority is not proof of an executed agreement.