East Zorra-Tavistock · Procurement record

Culvert 2015 replacement contractor: written bid acceptance

CAO2026-17 / October 21 motion

Money & projects Explore sections
East Zorra-Tavistock procurementBid acceptance recorded in written minutes; adoption unverified

Supplier

Vandenberk Construction

Procurement method
Replacement following mutual termination
Award date
2026-10-21
Contract term
Not established

From bid to payment

Bid acceptance recorded in written minutes; adoption unverified

  1. Published bid$373,454.20
  2. RecommendationAmount not published
  3. Award / contract$373,454.20Vandenberk Construction · 2026-10-21
  4. Recorded paymentsAmount not publishedNo payment amounts attached
Accepted bid exclusive of taxes; $50,000 contingency specified separately in staff report, if needed. An executed contract and payment are not established. · Bid, award and payment are separate measures. No price-change calculation is inferred between them.

Posted October 21 written minutes record a carried motion accepting Vandenberk Construction Inc.’s bid of $373,454.20 exclusive of taxes, with contingency if needed, and authorizing the CAO and Treasurer to sign. The staff report specifies $50,000 contingency; the motion does not repeat that amount. Formal minutes adoption, an executed agreement and completion have not been verified. The earlier caption evidence remains historical; no individual voting record or independent audio review is inferred.

Contract changes & payments

Contract changes unconfirmed.

Payments not confirmed.

Related project

East Zorra-Tavistock · Roads & bridges

Box Culvert 2015 replacement construction

Posted October 21 written minutes record a carried motion accepting Vandenberk Construction Inc.’s bid of $373,454.20 exclusive of taxes, with contingency if needed, and authorizing the CAO and Treasurer to sign. The staff report specifies $50,000 contingency; the motion does not repeat that amount. Formal minutes adoption, an executed agreement and completion have not been verified.

East Zorra-Tavistock

Bid acceptance recorded in written minutes; adoption unverified
2026 allocation
$600,000
Named supplier
Vandenberk Construction
Next target
No next date listed
Latest update
2026-10-21 · Written minutes record bid acceptance

What still needs an answer

  • Where are the adopted minutes, executed replacement agreement and completion record?

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. Culvert 2015 contractor change proposed

    Source ID: oct30-ezt-culvert

    Source date
    2026-10-21
    Event / reporting date
    2026-10-21
    Reviewed
    2026-10-30
    Retrieved
    2026-10-30
    Evidence status
    verified_primary
    Decision / approval status
    staff-reported termination; replacement award unverified
    Passage / page
    Report pages 1–2
    Evidence note
    Primary-source body reviewed in the October 30 audit No October 21 minutes linked. Replacement award and completion unverified. Original capital budget $600,000; paid-to-date $130,486.98 reported.

    Open in source library

  2. October 21 EZT council recording — Culvert 2015 caption window

    Source ID: oct30-ezt-culvert-video

    Source date
    2026-10-21
    Reviewed
    2026-10-30
    Evidence status
    caption_reviewed
    Passage / page
    39:54–40:37 of 42:02; motion called carried at 40:34/40:37
    Evidence note
    Only the target caption window was reviewed. Correct contractor, amount and $50,000 contingency come from written CAO2026-17 report. Audio, written minutes, individual votes, executed agreement and completion were not independently verified.

    Open in source library

  3. October 21 Council written minutes: Culvert 2015 bid acceptance

    Source ID: nov7-ezt-oct21-written-minutes

    Source date
    2026-10-21
    Event / reporting date
    2026-10-21
    Reviewed
    2026-11-07
    Evidence status
    verified_primary
    Passage / page
    Item 9.a, CAO2026-17
    Evidence note
    Posted written minutes record a carried motion. Formal adoption at the November 4 meeting was not verified. Signing authority is not proof of an executed agreement.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.