02Follow the moneyOxford County

Oxford County · Money

Follow the money.

Open the allocation. Check the actuals. Follow the decision into delivery.

Money & projects Explore sections
What do these money figures mean?
Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

Why are there different County totals?

The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

The budget hub retains an earlier $406.1 million headline. Spending explanations here use the detailed approved schedule.

Detailed approved budget ↗ · County budget hub ↗

County finances cover shared services. Municipal budgets are separate. No combined spending total is implied.

Filters1 active
Reset
approvedoperating

2026 CAO Office operating detail

2026 CAO Office operating detail gross expenditure · 2026 · CAD · As published; no separate HST breakdown established

Original approved$723,520
Revised authorizationNot established
Reported actualNot establishedNo reporting cutoff established
Published forecastNot established
Budgeted revenue Not establishedNet levy / subsidy $723,520

Does the breakdown add up?

Source total $723,520Covered on the stated basis $723,520Reconciled difference $0

Sum of top-level rows; subsidiary schedules are separate views and must not be added again.

Definitions, changes & interpretation
  • Service schedule includes allocated internal charges. This is a drill-down, not an additional County expenditure. 2025 comparative is the source revised/account-reclassified budget, not audited actual; priorForecast is labelled separately. Capital is excluded from this operating schedule.
Open the source record
  1. Approved 2026 Business Plan and Budget PDF page 267; printed page 267

    Oxford County · Published 2026-01-14 · Event/reporting date 2025-12-10 · 2026

    approved · Primary record verified · File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

What is the total made of?

FiltersRefine results
Clear row filters

6 matching accounts. Parent totals include the indented accounts. — means no published amount.

Allocation by service

County · 2026 · gross expenditure · original

  1. SALARIES$490,072
  2. BENEFITS$138,955
  3. CONTRACTED SERVICES$50,000
  4. INTERDEPARTMENTAL CHARGES$49,983
  5. SALARIES GAPPING-$36,600
  6. OPERATING EXPENSES$31,110
CAD · Largest 6 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below.
Open the source record
  1. Approved 2026 Business Plan and Budget PDF page 267; printed page 267

    Oxford County · Published 2026-01-14 · Event/reporting date 2025-12-10 · 2026

    approved · Primary record verified · File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

2026 CAO Office operating detail · 2026 · gross expenditure · CAD
Service / facility / accountOriginal budgetPrior budgetEvidence
SALARIESCAO$490,072$362,601
Details & source
Open the source record
  1. Approved 2026 Business Plan and Budget PDF page 267; printed page 267

    Oxford County · Published 2026-01-14 · Event/reporting date 2025-12-10 · 2026

    approved · Primary record verified · File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

BENEFITSCAO$138,955$91,645
Details & source
Open the source record
  1. Approved 2026 Business Plan and Budget PDF page 267; printed page 267

    Oxford County · Published 2026-01-14 · Event/reporting date 2025-12-10 · 2026

    approved · Primary record verified · File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

SALARIES GAPPINGCAO-$36,600$0
Details & source
Open the source record
  1. Approved 2026 Business Plan and Budget PDF page 267; printed page 267

    Oxford County · Published 2026-01-14 · Event/reporting date 2025-12-10 · 2026

    approved · Primary record verified · File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

OPERATING EXPENSESCAO$31,110$25,145
Details & source
Open the source record
  1. Approved 2026 Business Plan and Budget PDF page 267; printed page 267

    Oxford County · Published 2026-01-14 · Event/reporting date 2025-12-10 · 2026

    approved · Primary record verified · File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

CONTRACTED SERVICESCAO$50,000$65,000
Details & source
Open the source record
  1. Approved 2026 Business Plan and Budget PDF page 267; printed page 267

    Oxford County · Published 2026-01-14 · Event/reporting date 2025-12-10 · 2026

    approved · Primary record verified · File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

INTERDEPARTMENTAL CHARGESCAO$49,983$42,801
Details & source
Open the source record
  1. Approved 2026 Business Plan and Budget PDF page 267; printed page 267

    Oxford County · Published 2026-01-14 · Event/reporting date 2025-12-10 · 2026

    approved · Primary record verified · File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs.

From an allocation to a result

County · Roads & bridges

808 Dundas: from purchase to an operating support centre

The County bought the property for $4.55 million. Renovation and operation are separate commitments.

Woodstock · 808 Dundas Street, Woodstock

Property acquired; spring 2028 opening remains a target
2026 allocation
Not established
Next target
2028-04 · Centre opening target
Latest update
2026-09-21 · Engagement feedback published

County · Water, drainage & wastewater

Thamesford wastewater plant upgrade

New two-storey headworks, aeration-roof removal, generator and process equipment.

Zorra

Multi-year construction planned May/June 2026–May 2028
2026 allocation
$6,000,000
Next target
2028-05 · Expected completion
Latest update
2026-03-11 · Multi-year award recommended

County · Roads & bridges

County culvert replacements across local roads

Culvert replacements on parts of Oxford Roads 2, 10, 13, 22, 55 and 59, plus a left-turn lane at Oxford Road 2 and 35th Line.

Blandford-Blenheim · East Zorra-Tavistock · South-West Oxford · Zorra

Some sections listed complete; Oxford Road 10 scheduled for October–November
2026 allocation
Not established
Named supplier
Steve Smith Construction Corporation
Next target
2026-10 · Oxford Road 10 start target
Latest update
2025-12-10 · 2026 Business Plan and Budget approval

County · Roads & bridges

Dundas Street reconstruction: phases and closures

Oxford Road 2 reconstruction from west city limit to Mill Street, with utility and road improvements.

Woodstock

Phase 2B scheduled September 14; overall November 2026 target
2026 allocation
Not established
Named supplier
Network Sewer and Watermain Ltd
Next target
2026-11 · Overall completion target
Latest update
2026-07-21 · Phase 1 reported complete

County · Roads & bridges

Otterville bridge: follow the full project cost

Bridge rehabilitation on Oxford Road 19 between Church and Bullock Streets, phased with alternating traffic.

Norwich

Construction notice updated September 21; December 2026 target
2026 allocation
$400,000
Named supplier
Urbanlink Civil Ltd.
Next target
2026-12 · Expected completion
Latest update
2026-09-28 · Scheduled one-day girder installation closure

County · Roads & bridges

Burgessville Church Street reconstruction

Urbanize Oxford Road 59 across Burgessville with road, sidewalk and lighting upgrades.

Norwich

Work scheduled through October 2026
2026 allocation
$4,100,000
Named supplier
GIP Paving Inc.
Next target
2026-10 · Published completion target
Latest update
2026-04-30 · Public information centre