2026-07-14 · 15
Add $18,350 and proceed with Phase 1 EA without WECI funding
Carried
$18,350 · Additional Working Capital reserve funding for EA and gabion project
Consequence: Proceed despite unsuccessful provincial WECI application.
2 source records
- July 14, 2026 Council minutes
- Publisher
- Township of South West Oxford
- Published
- 2026-07-14
- Event / reporting date
- 2026-07-14
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- approved minutes
- Passage / page
- Resolutions 4, 15, 17, 19, 22–23
- Evidence notes
- Audit approval; Centreville increase; hub report received; airport request declined; financing by-law.
- CAO33-2026: Centreville Dam project update and funding request
- Publisher
- Township of South West Oxford
- Published
- 2026-07-14
- Event / reporting date
- 2026-07-14
- Retrieved
- 2026-10-01
- Verified
- 2026-10-01
- Evidence status
- verified_primary
- Decision / approval status
- published
- Passage / page
- PDF pp. 1–4
- Evidence notes
- EA and gabion work funding; not total decommissioning cost.