2026-10-21 · CAO2026-17
Culvert 2015 replacement bid accepted in written minutes
Carried in posted written minutes; formal adoption unverified
$373,454.20 · Bid acceptance exclusive of taxes; contingency if needed. Staff report specifies $50,000 contingency separately. Not an executed contract or payment.
Consequence: Posted October 21 written minutes record a carried motion accepting Vandenberk Construction Inc.’s bid of $373,454.20 exclusive of taxes, with contingency if needed, and authorizing the CAO and Treasurer to sign. The staff report specifies $50,000 contingency; the motion does not repeat that amount. Formal minutes adoption, an executed agreement and completion have not been verified.
3 source records
- Culvert 2015 contractor change proposed
- Source date
- 2026-10-21
- Event / reporting date
- 2026-10-21
- Reviewed
- 2026-10-30
- Retrieved
- 2026-10-30
- Evidence status
- verified_primary
- Decision / approval status
- staff-reported termination; replacement award unverified
- Passage / page
- Report pages 1–2
- Evidence note
- Primary-source body reviewed in the October 30 audit No October 21 minutes linked. Replacement award and completion unverified. Original capital budget $600,000; paid-to-date $130,486.98 reported.
- October 21 EZT council recording — Culvert 2015 caption window
- Source date
- 2026-10-21
- Reviewed
- 2026-10-30
- Evidence status
- caption_reviewed
- Passage / page
- 39:54–40:37 of 42:02; motion called carried at 40:34/40:37
- Evidence note
- Only the target caption window was reviewed. Correct contractor, amount and $50,000 contingency come from written CAO2026-17 report. Audio, written minutes, individual votes, executed agreement and completion were not independently verified.
- October 21 Council written minutes: Culvert 2015 bid acceptance
- Source date
- 2026-10-21
- Event / reporting date
- 2026-10-21
- Reviewed
- 2026-11-07
- Evidence status
- verified_primary
- Passage / page
- Item 9.a, CAO2026-17
- Evidence note
- Posted written minutes record a carried motion. Formal adoption at the November 4 meeting was not verified. Signing authority is not proof of an executed agreement.