Open the allocation. Check the actuals. Follow the decision into delivery.
Money & projects Explore sections
Early Works amount in draft minutes
Resolution 8 carried in draft minutes; adoption unverified
October 20 draft minutes record resolution 8 authorizing $1,304,091 plus applicable HST for Early Works from the Working Capital Reserve and arrangements with Sierra General Contracting, subject to approvals. A November 3 staff follow-up says Sierra was notified. Minutes adoption, an executed contract and payment are not established; this is not approval or completion of the whole facility.
October 20, 2026 Council consideration · publication date not established
Event / reporting date
2026-10-20
Reviewed
2026-10-29
Decision / approval status
Staff recommendation; October 20 outcome unverified
Passage / page
Pages 1–2 and 5–6
Evidence notes
CAO 51-2026 recommended Sierra early site works of CAD $1,304,091 plus applicable HST from the Working Capital Reserve for October 20 consideration. That scheduled consideration date has passed, but the Council outcome was not verified. This remains a staff recommendation, not a confirmed award, payment or approval of the full construction budget. The full construction budget and financing require a separate later decision.
Primary-source body reviewed in the October 30 audit Not approval or completion of the whole facility. Highlights do not repeat an awarded dollar amount; October 20 minutes not linked.
Draft minutes attached to the November 3 agenda; adoption was not verified. Early Works authority remains separate from full facility funding, executed contracts and payments.
published interim report; annual comparative printed in reportoperating
2026 budget and net costs through June 30
Non-overlapping department summary from published June 30 interim report; detailed capital rows remain separately linked. net departmental requirements · 2026 · CAD · Source accounting basis; net service costs include revenues and transfers
Original approved$7,712,934
Revised authorizationNot established
Reported actual$4,656,460Through 2026-06-30
Published forecastNot established
Budgeted revenue Not establishedNet levy / subsidy $7,712,934
Does the breakdown add up?
Source total $4,656,460Covered on the stated basis $4,656,460Reconciled difference $0
Signed department totals reconcile to reported or explicitly derived net requirement; not gross spending.
Definitions, changes & interpretation
This is the published net levy-requirement schedule across operations, capital and financing, not gross cash spending or PSAB expense. Annual budget includes unfinished projects and reserve transfers. The $3,056,474 difference is unspent/unearned annual authorization, not a final saving. Summary table transcribed; all supporting account detail remains available in linked report. Blank cells remain null.
CAD · Largest 10 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below.
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Actual cutoff June 30; narrative can describe later work. Capital and operating entries ongoing. Public accounting net amounts, not gross payment totals.
October 20 draft minutes record resolution 8 authorizing $1,304,091 plus applicable HST for Early Works from the Working Capital Reserve and arrangements with Sierra General Contracting, subject to approvals. A November 3 staff follow-up says Sierra was notified. Minutes adoption, an executed contract and payment are not established; this is not approval or completion of the whole facility.
South-West Oxford
Early Works authorized in draft minutes; full facility separate
Original budget
$12,000,000
Next target
2028-01-01 · Anticipated childcare occupancy in proposed MOU
Latest update
2026-11-03 · Staff report says Sierra was notified
Resolution 6 records approval of Smith Services for the Brownsville Community Centre/Fire Hall generator at $105,180.48 plus taxes. File labelled draft; adoption not independently established.