Centreville Dam: erosion protection and environmental assessment

Money & projects Explore sections
South-West Oxford project

At a glance

Location
South-West Oxford
Responsible authority
South-West Oxford
Current stage
July increase approved; September further funding request and execution status unresolvedAs of 2026-09-24
2026 allocation
$45,000
Next target
No next date listed
Named supplier
Better Made Fence See contract details

Centreville Dam: erosion protection and environmental assessment

Who approves and delivers this project?

Property owner and funding authority

South-West Oxford

Costs historically levied to Township; Council directs local funding.

Technical manager and contracting body

Upper Thames River Conservation Authority

Report states UTRCA entered contractor and consultant contracts; recommends erosion work and EA.

Construction contractor

Better Made Fence

UTRCA successful contractor named in CAO48; approx $60,000 including supplies/materials, exact agreement not extracted.

Money

Project money

Annual allocation

2026 allocation
$45,000
Annual 2026 local provision approximately $45,000; July approved extra $18,350; September further request up to $40,000 has no confirmed adopted minutes

Latest spending total not published here.

CAD · Source budget basis; HST treatment not separately stated · Annual 2026 local provision approximately $45,000; July approved extra $18,350; September further request up to $40,000 has no confirmed adopted minutes

Timeline

  1. approval

    Extra $18,350 approved

  2. decision

    Council did not authorize extra ~$40,000; requested details

  3. proposal

    Further report requested authorization and funding direction

  4. constraint

    Reported regulatory-approval expiry

    Expiry stated in Sept24 report; no renewal or completion proof obtained.

Contracts

· UTRCA contract execution explicitly reported; exact signed amount not supplied

Centreville gabion and erosion protection

Better Made Fence

Published bid
Not established
Published award / contract value
Not established
Unit price
Not established

Unstated

Staff report calls successful contractor price approximately $60,000 including supplies/materials, other bid over $100,000. Approximation retained in notes, not normalized to a false precise executed award.

Open procurement record

Decisions

Outcomes

Completion not confirmed.

Questions

  • What did Council decide on September 24, and which reserve or levy pays?
  • Did works proceed before the reported October 1 permit expiry?
  • What is the combined EA and stabilization budget, with commitments and payments?
Scope & interpretation notes
  • July UTRCA levy/invoice $63,350 is not entire lifetime dam removal cost. September report estimates gabion contractor $60k, consultant $10k, UTRCA wages $5k; tax treatment unstated. Eventual decommissioning estimated 5–6 years away and requires EA; full removal not predetermined.

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. CAO33-2026: Centreville Dam project update and funding request

    Source ID: south-west-oxford-centreville-july

    Publisher
    Township of South West Oxford
    Published
    2026-07-14
    Event / reporting date
    2026-07-14
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published
    Passage / page
    PDF pp. 1–4
    Evidence notes
    EA and gabion work funding; not total decommissioning cost.

    Open in source library

  2. CAO48-2026: Centreville gabion project and additional funding

    Source ID: south-west-oxford-centreville-september

    Publisher
    Township of South West Oxford
    Published
    2026-09-24
    Event / reporting date
    2026-09-24
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published
    Passage / page
    PDF pp. 1–4; contract, urgency, funding options
    Evidence notes
    September 15 had not approved additional $40k; September 24 minutes not posted in reviewed official index as of cutoff. Do not call recommendation approved.

    Open in source library

  3. July 14, 2026 Council minutes

    Source ID: south-west-oxford-jul14-minutes

    Publisher
    Township of South West Oxford
    Published
    2026-07-14
    Event / reporting date
    2026-07-14
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    approved minutes
    Passage / page
    Resolutions 4, 15, 17, 19, 22–23
    Evidence notes
    Audit approval; Centreville increase; hub report received; airport request declined; financing by-law.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.