What do these money figures mean?
Budget Planned costs for a stated year or project.
Annual allocation Funding assigned for one year. It may be part of a larger project.
Lifetime project budget The stated budget for the full project across its years.
Forecast An estimate of the eventual cost, as of the date shown.
Tax requirement (levy) The amount to raise from property taxes, after other funding.
Contract award The accepted contract price, with its stated tax and scope.
Recorded costs or payments Amounts reported for the period shown. They do not establish project completion. County spending and County taxes explained →
These are South-West Oxford’s finances. County finances are separate . See County projects located here .
adopted capital Selected explicit capital lines in adopted Schedule A Selected explicit capital lines in adopted Schedule A partial capital allocation extract · 2026 · CAD · As reported in source; no HST conversion inferred
Original approved Not established
Revised authorization Not established
Reported actual Not established No reporting cutoff established
Published forecast Not established
Does the breakdown add up? Source total Not established Covered on the stated basis $3,074,336 Unreconciled / unextracted remainder Not established
Only parentless rows included; account children are not added again.
Definitions, changes & interpretation Two separately labelled capital lines in combined adopted schedule, totaling $3,074,336. This is partial scope, not a Township capital-budget headline; general-government/facility capital is embedded elsewhere. Do not add to the combined expenditure schedule. 2 source records By-law 77-2025 Schedule A: 2026 expenditures PDF p. 1, all expenditure rows Township of South West Oxford · Published 2025-12-16 · Event/reporting date 2025-12-16
adopted · Primary record verified · Combined operating, capital, debt and reserve-transfer budget; not PSAB annual expense.
December 16, 2025 Council minutes: By-law 77-2025 Resolution 14; adoption of 2026 estimates Township of South West Oxford · Published 2025-12-16 · Event/reporting date 2025-12-16
adopted · Primary record verified · Final adopted schedule controls over November 10 draft.
What is the total made of? Download these rows · CSV 2 matching accounts. Parent totals include the indented accounts. — means no published amount.
Allocation by service South-West Oxford · 2026 · partial capital allocation extract · original
Road capital $2,554,336 Recreation capital $520,000 CAD · Largest 2 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below. 2 source records By-law 77-2025 Schedule A: 2026 expenditures PDF p. 1, all expenditure rows Township of South West Oxford · Published 2025-12-16 · Event/reporting date 2025-12-16
adopted · Primary record verified · Combined operating, capital, debt and reserve-transfer budget; not PSAB annual expense.
December 16, 2025 Council minutes: By-law 77-2025 Resolution 14; adoption of 2026 estimates Township of South West Oxford · Published 2025-12-16 · Event/reporting date 2025-12-16
adopted · Primary record verified · Final adopted schedule controls over November 10 draft.
From an allocation to a result South-West Oxford · Housing & community services
Mount Elgin municipal office, library and childcare hub
South-West Oxford
All-electric mechanical system selected; childcare MOU authorized
Original budget $12,000,000
Next target 2028-01-01 · Anticipated childcare occupancy in proposed MOU
Latest update 2026-09-15 · Childcare MOU proposed Open project → South-West Oxford · Parks, recreation & culture
New Mount Elgin Park: concept and cost range
South-West Oxford
Preliminary landscape estimate; construction commitment unverified
2026 allocation Not established
Next target No next date listed Open project → South-West Oxford · Water, drainage & wastewater
Centreville Dam: erosion protection and environmental assessment
South-West Oxford
July increase approved; September further funding request and execution status unresolved
2026 allocation $45,000
Named supplier Better Made Fence
Next target No next date listed
Latest update 2026-10-01 · Reported regulatory-approval expiry Open project → South-West Oxford · Roads & bridges
Airport Road and Mount Elgin Road resurfacing
South-West Oxford
Mount Elgin Road reported complete; Airport Road ongoing
2026 allocation Not established
Named supplier Permanent Paving Inc.
Next target No next date listed
Latest update 2026-09-01 · Mount Elgin section reported complete Open project → South-West Oxford · Buildings & facilities
Public Works building roof replacement
South-West Oxford
Contract awarded · completion and payment unconfirmed
2026 allocation Not established
Named supplier Nedlaw Roofing
Next target No next date listed
Latest update 2026-08-11 · Approve Public Works building roof replacement Open project → South-West Oxford · Vehicles & equipment
2026 waste-management truck replacement
South-West Oxford
Truck ordered; delivery not confirmed
2026 allocation Not established
Next target No next date listed
Latest update 2026-01-20 · Approve new waste-management truck Open project → Explore all projects Copy this view Print