02Follow the moneySouth-West Oxford

South-West Oxford · Money

Follow the money.

Open the allocation. Check the actuals. Follow the decision into delivery.

Money & projects Explore sections
What do these money figures mean?
Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

These are South-West Oxford’s finances. County finances are separate. See County projects located here.

Filters1 active
Reset
adoptedcapital

Selected explicit capital lines in adopted Schedule A

Selected explicit capital lines in adopted Schedule A partial capital allocation extract · 2026 · CAD · As reported in source; no HST conversion inferred

Original approvedNot established
Revised authorizationNot established
Reported actualNot establishedNo reporting cutoff established
Published forecastNot established

Does the breakdown add up?

Source total Not establishedCovered on the stated basis $3,074,336Unreconciled / unextracted remainder Not established

Only parentless rows included; account children are not added again.

Definitions, changes & interpretation
  • Two separately labelled capital lines in combined adopted schedule, totaling $3,074,336. This is partial scope, not a Township capital-budget headline; general-government/facility capital is embedded elsewhere. Do not add to the combined expenditure schedule.
2 source records
  1. By-law 77-2025 Schedule A: 2026 expenditures PDF p. 1, all expenditure rows

    Township of South West Oxford · Published 2025-12-16 · Event/reporting date 2025-12-16

    adopted · Primary record verified · Combined operating, capital, debt and reserve-transfer budget; not PSAB annual expense.

  2. December 16, 2025 Council minutes: By-law 77-2025 Resolution 14; adoption of 2026 estimates

    Township of South West Oxford · Published 2025-12-16 · Event/reporting date 2025-12-16

    adopted · Primary record verified · Final adopted schedule controls over November 10 draft.

What is the total made of?

FiltersRefine results
Clear row filters

2 matching accounts. Parent totals include the indented accounts. — means no published amount.

Allocation by service

South-West Oxford · 2026 · partial capital allocation extract · original

  1. Road capital$2,554,336
  2. Recreation capital$520,000
CAD · Largest 2 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below.
2 source records
  1. By-law 77-2025 Schedule A: 2026 expenditures PDF p. 1, all expenditure rows

    Township of South West Oxford · Published 2025-12-16 · Event/reporting date 2025-12-16

    adopted · Primary record verified · Combined operating, capital, debt and reserve-transfer budget; not PSAB annual expense.

  2. December 16, 2025 Council minutes: By-law 77-2025 Resolution 14; adoption of 2026 estimates

    Township of South West Oxford · Published 2025-12-16 · Event/reporting date 2025-12-16

    adopted · Primary record verified · Final adopted schedule controls over November 10 draft.

Selected explicit capital lines in adopted Schedule A · 2026 · partial capital allocation extract · CAD
Service / facility / accountOriginal budgetEvidence
Recreation capitalHealth/Recreation$520,000
Details & source

Source location: Schedule A, PDF p. 1

Open the source record
  1. By-law 77-2025 Schedule A: 2026 expenditures PDF p. 1, all expenditure rows

    Township of South West Oxford · Published 2025-12-16 · Event/reporting date 2025-12-16

    adopted · Primary record verified · Combined operating, capital, debt and reserve-transfer budget; not PSAB annual expense.

Road capitalTransportation$2,554,336
Details & source

Source location: Schedule A, PDF p. 1

Open the source record
  1. By-law 77-2025 Schedule A: 2026 expenditures PDF p. 1, all expenditure rows

    Township of South West Oxford · Published 2025-12-16 · Event/reporting date 2025-12-16

    adopted · Primary record verified · Combined operating, capital, debt and reserve-transfer budget; not PSAB annual expense.

From an allocation to a result

South-West Oxford · Housing & community services

Mount Elgin municipal office, library and childcare hub

Mount Elgin municipal office, library and childcare hub

South-West Oxford

All-electric mechanical system selected; childcare MOU authorized
Original budget
$12,000,000
Next target
2028-01-01 · Anticipated childcare occupancy in proposed MOU
Latest update
2026-09-15 · Childcare MOU proposed

South-West Oxford · Parks, recreation & culture

New Mount Elgin Park: concept and cost range

New Mount Elgin Park: concept and cost range

South-West Oxford

Preliminary landscape estimate; construction commitment unverified
2026 allocation
Not established
Next target
No next date listed

South-West Oxford · Water, drainage & wastewater

Centreville Dam: erosion protection and environmental assessment

Centreville Dam: erosion protection and environmental assessment

South-West Oxford

July increase approved; September further funding request and execution status unresolved
2026 allocation
$45,000
Named supplier
Better Made Fence
Next target
No next date listed
Latest update
2026-10-01 · Reported regulatory-approval expiry

South-West Oxford · Roads & bridges

Airport Road and Mount Elgin Road resurfacing

Airport Road and Mount Elgin Road resurfacing

South-West Oxford

Mount Elgin Road reported complete; Airport Road ongoing
2026 allocation
Not established
Named supplier
Permanent Paving Inc.
Next target
No next date listed
Latest update
2026-09-01 · Mount Elgin section reported complete

South-West Oxford · Buildings & facilities

Public Works building roof replacement

Public Works building roof replacement

South-West Oxford

Contract awarded · completion and payment unconfirmed
2026 allocation
Not established
Named supplier
Nedlaw Roofing
Next target
No next date listed
Latest update
2026-08-11 · Approve Public Works building roof replacement

South-West Oxford · Vehicles & equipment

2026 waste-management truck replacement

2026 waste-management truck replacement

South-West Oxford

Truck ordered; delivery not confirmed
2026 allocation
Not established
Next target
No next date listed
Latest update
2026-01-20 · Approve new waste-management truck
Explore all projects