What do these money figures mean?
Budget Planned costs for a stated year or project.
Annual allocation Funding assigned for one year. It may be part of a larger project.
Lifetime project budget The stated budget for the full project across its years.
Forecast An estimate of the eventual cost, as of the date shown.
Tax requirement (levy) The amount to raise from property taxes, after other funding.
Contract award The accepted contract price, with its stated tax and scope.
Recorded costs or payments Amounts reported for the period shown. They do not establish project completion. County spending and County taxes explained →
These are East Zorra-Tavistock’s finances. County finances are separate . See County projects located here .
adopted operating Adopted operating and tax-supported capital financing Adopted operating and tax-supported capital financing sources of financing · 2026 · CAD · As reported in source; no HST conversion inferred
Original approved $12,088,383
Revised authorization Not established
Reported actual Not established No reporting cutoff established
Published forecast Not established
Budgeted revenue $12,088,383 Net levy / subsidy Not established
Does the breakdown add up? Source total $12,088,383 Covered on the stated basis $12,088,383 Reconciled difference $0
Only parentless rows included; account children are not added again.
Definitions, changes & interpretation Revenue and transfers finance the expenditure schedule. These are not extra expenditures. Sources for this record: [1]
What is the total made of? Download these rows · CSV 20 matching accounts. Parent totals include the indented accounts. — means no published amount.
Allocation by service East Zorra-Tavistock · 2026 · sources of financing · original
Adopted tax levy $8,945,280 Licences permits and rents $1,101,202 OMPF $1,007,800 Investment income $363,230 City of Woodstock boundary adjustment $115,771 Fines and penalties $96,481 User fees and charges $78,779 Supplemental taxation $60,000 Contributions from other municipalities $54,098 Cost recoveries $52,284 Building Code Act deferred revenue $50,000 Landowner recovery $37,804 CAD · Largest 12 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below. Sources for this record: [1]
Sources & evidence These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: east-zorra-tavistock-budget-adoption
Publisher Township of East Zorra Tavistock
Published 2026-04-01
Event / reporting date 2026-04-01
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status adopted
Passage / page Sections 1–4; Schedules A and C, PDF pp. 1–5
Evidence notes Schedule C expenditures and financing differ by $1 in the original. Open in source library
From an allocation to a result East Zorra-Tavistock · Roads & bridges
Posted October 21 written minutes record a carried motion accepting Vandenberk Construction Inc.’s bid of $373,454.20 exclusive of taxes, with contingency if needed, and authorizing the CAO and Treasurer to sign. The staff report specifies $50,000 contingency; the motion does not repeat that amount. Formal minutes adoption, an executed agreement and completion have not been verified.
East Zorra-Tavistock
Bid acceptance recorded in written minutes; adoption unverified
2026 allocation $600,000
Named supplier Vandenberk Construction
Next target No next date listed
Latest update 2026-10-21 · Written minutes record bid acceptance Open project → East Zorra-Tavistock · Roads & bridges
Fuhr Street reconstruction: Township share
East Zorra-Tavistock
Substantial performance certified July 29; final acceptance and final cost unverified
2026 allocation $627,300
Named supplier Elgin Construction Company Limited
Next target No next date listed
Latest update 2026-07-29 · Substantial performance certified Open project → East Zorra-Tavistock · Roads & bridges
Bridge 5 demobilization costs carried into 2026
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
Original budget $2,407,255
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → East Zorra-Tavistock · Roads & bridges
William Street North top lift asphalt
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
Original budget $1,272,283
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → East Zorra-Tavistock · Other projects
Replace 2020 Chevrolet Silverado
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
2026 allocation $53,060
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → East Zorra-Tavistock · Vehicles & equipment
Firefighting equipment, $20,000 per station
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
2026 allocation $60,000
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → Explore all projects Copy this view Print