270 m road; 160 m storm sewer; 165 m watermain including services; 260 m sanitary sewer and laterals; 260 m sidewalk. Township budget is its $627,300 share, not necessarily the entire multi-utility contract.
Project 12-6-692604-4005
Who approves and delivers this project?
Budget authority
Township Council
Approves annual allocation; delivery and contract authority must be traced separately.
Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11
supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.
2026 annual capital allocation; not a final contract or lifetime cost
Latest spending total not published here.
CAD · Source budget basis; HST treatment not separately stated · 2026 annual capital allocation; not a final contract or lifetime costSources for these figures · 3
Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11
supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.