02Follow the moneyEast Zorra-Tavistock

East Zorra-Tavistock · Money

Follow the money.

Open the allocation. Check the actuals. Follow the decision into delivery.

Money & projects Explore sections
What do these money figures mean?
Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

These are East Zorra-Tavistock’s finances. County finances are separate. See County projects located here.

Filters1 active
Reset
adoptedcapital

2026 capital allocations

2026 capital allocations capital allocation · 2026 · CAD · As reported in source; no HST conversion inferred

Original approved$5,154,993
Revised authorizationNot established
Reported actualNot establishedNo reporting cutoff established
Published forecastNot established

Does the breakdown add up?

Source total $5,154,993Covered on the stated basis $5,154,992Unreconciled / unextracted remainder $1

All 36 detailed 2026 allocations total $5,154,992, matching Schedule C financing and $1 below its published expenditure total. Original discrepancy retained.

Definitions, changes & interpretation
  • All 36 2026 detailed project/program allocations extracted; 2027–2030 forecasts excluded. Pumper annual increment must not be confused with its unspent 2025 authorization.
2 source records
  1. By-law 2026-10: adopted estimates and tax rates Sections 1–4; Schedules A and C, PDF pp. 1–5

    Township of East Zorra Tavistock · Published 2026-04-01 · Event/reporting date 2026-04-01

    adopted · Primary record verified · Schedule C expenditures and financing differ by $1 in the original.

  2. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

What is the total made of?

FiltersRefine results
Clear row filters

36 matching accounts. Parent totals include the indented accounts. — means no published amount.

Allocation by service

East Zorra-Tavistock · 2026 · capital allocation · original

  1. Hickson fire station design/build construction$2,725,000
  2. Fuhr Street reconstruction: Township share$627,300
  3. Box Culvert 2015 replacement construction$600,000
  4. Tandem axle plow and replacement 835 truck$450,200
  5. William Street North top lift asphalt$80,000
  6. Township Fire Chief pickup$69,000
  7. Firefighting equipment, $20,000 per station$60,000
  8. Decontamination units and installation$60,000
  9. Shared shouldering apparatus and plow blade$53,500
  10. Replace 2020 Chevrolet Silverado$53,060
  11. Roads Needs Study update$35,000
  12. Arena washroom partitions and toilet upgrades$30,000
CAD · Largest 12 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below.
2 source records
  1. By-law 2026-10: adopted estimates and tax rates Sections 1–4; Schedules A and C, PDF pp. 1–5

    Township of East Zorra Tavistock · Published 2026-04-01 · Event/reporting date 2026-04-01

    adopted · Primary record verified · Schedule C expenditures and financing differ by $1 in the original.

  2. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

2026 capital allocations · 2026 · capital allocation · CAD
Service / facility / accountOriginal budgetEvidence
Replace 2020 Chevrolet SilveradoAccount 12-6-442601-3350Building and Development Services$53,060
Details & source

Source location: PDF p. 72; 12-6-442601-3350

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Firefighting equipment, $20,000 per stationAccount 12-6-41??01-3360Fire and Emergency Management Services$60,000
Details & source

Source location: PDF p. 81; 12-6-41??01-3360

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Communications system upgradesAccount 12-6-41??02-3011Fire and Emergency Management Services$2,075
Details & source

Source location: PDF p. 81; 12-6-41??02-3011

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Fire truck tire replacementAccount 12-6-41??03-3350Fire and Emergency Management Services$9,180
Details & source

Source location: PDF p. 81; 12-6-41??03-3350

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Innerkip pumper inflation incrementAccount 12-6-412507-3350Fire and Emergency Management Services$12,484
Details & source

Source location: PDF p. 81; 12-6-412507-3350

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Township Fire Chief pickupAccount 12-6-412604-3350Fire and Emergency Management Services$69,000
Details & source

Source location: PDF p. 81; 12-6-412604-3350

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Hickson fire station design/build constructionAccount 12-6-412605-4005Fire and Emergency Management Services$2,725,000
Details & source

Source location: PDF p. 81; 12-6-412605-4005

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Decontamination units and installationAccount 12-6-412606-3017Fire and Emergency Management Services$60,000
Details & source

Source location: PDF p. 81; 12-6-412606-3017

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Cyclical IT hardware replacementAccount 12-6-25??01-3034General Government$21,420
Details & source

Source location: PDF p. 91; 12-6-25??01-3034

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Council laptop equipmentAccount 12-6-242601-3034General Government$21,000
Details & source

Source location: PDF p. 91; 12-6-242601-3034

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Staff cell phone replacementsAccount 12-6-252602-3034General Government$18,150
Details & source

Source location: PDF p. 91; 12-6-252602-3034

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Administration building top coat paving and water softenerAccount 12-6-252603-4005General Government$18,000
Details & source

Source location: PDF p. 91; 12-6-252603-4005

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Council Chambers server room coolingAccount 12-6-252604-4270General Government$4,500
Details & source

Source location: PDF p. 91; 12-6-252604-4270

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Bridge 5 demobilization costs carried into 2026Account 12-6-692503-4005Infrastructure and Community Services$20,000
Details & source

Source location: PDF p. 98; 12-6-692503-4005

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

William Street North top lift asphaltAccount 12-6-692504-4005Infrastructure and Community Services$80,000
Details & source

Source location: PDF p. 98; 12-6-692504-4005

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Ball diamond fencing in all three parksAccount 12-6-612603-3740Infrastructure and Community Services$17,500
Details & source

Source location: PDF p. 98; 12-6-612603-3740

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Hickson Park booth roofAccount 12-6-612604-4874Infrastructure and Community Services$4,000
Details & source

Source location: PDF p. 98; 12-6-612604-4874

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Special-event road closure signageAccount 12-6-632601-3170Infrastructure and Community Services$2,000
Details & source

Source location: PDF p. 98; 12-6-632601-3170

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Arena washroom partitions and toilet upgradesAccount 12-6-632602-4420Infrastructure and Community Services$30,000
Details & source

Source location: PDF p. 98; 12-6-632602-4420

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Tavistock Arena and Memorial Hall equipmentAccount 12-6-632603-3017Infrastructure and Community Services$17,700
Details & source

Source location: PDF p. 98; 12-6-632603-3017

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Innerkip Community Centre attic hatch and internetAccount 12-6-632604-4420Infrastructure and Community Services$10,000
Details & source

Source location: PDF p. 98; 12-6-632604-4420

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Box Culvert 2015 engineeringAccount 12-6-692603-4004Infrastructure and Community Services$30,000
Details & source

Source location: PDF p. 98; 12-6-692603-4004

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Box Culvert 2015 replacement constructionAccount 12-6-692603-4005Infrastructure and Community Services$600,000
Details & source

Source location: PDF p. 98; 12-6-692603-4005

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Fuhr Street reconstruction: Township shareAccount 12-6-692604-4005Infrastructure and Community Services$627,300
Details & source

Source location: PDF p. 98; 12-6-692604-4005

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Roads Needs Study updateAccount 12-6-692605-4003Infrastructure and Community Services$35,000
Details & source

Source location: PDF p. 98; 12-6-692605-4003

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Shared shouldering apparatus and plow bladeAccount 12-6-692606-3017Infrastructure and Community Services$53,500
Details & source

Source location: PDF p. 98; 12-6-692606-3017

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Tandem axle plow and replacement 835 truckAccount 12-6-692607-3350Infrastructure and Community Services$450,200
Details & source

Source location: PDF p. 98; 12-6-692607-3350

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Village entrance signsAccount 12-6-692608-3170Infrastructure and Community Services$11,000
Details & source

Source location: PDF p. 98; 12-6-692608-3170

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Half-load sign updatesAccount 12-6-692609-3170Infrastructure and Community Services$10,000
Details & source

Source location: PDF p. 98; 12-6-692609-3170

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Russell Drain: Township roads shareAccount 12-6-842601-4005Infrastructure and Community Services$25,000
Details & source

Source location: PDF p. 98; 12-6-842601-4005

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Memorial trees and benchesAccount 12-6-61??01-variousInfrastructure and Community Services$5,000
Details & source

Source location: PDF p. 97; 12-6-61??01-various

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Annual playground safety chipsAccount 12-6-61??02-4876Infrastructure and Community Services$5,100
Details & source

Source location: PDF p. 97; 12-6-61??02-4876

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Stormwater facility forestry and plantingsAccount 12-6-82??01-3045Infrastructure and Community Services$10,200
Details & source

Source location: PDF p. 97; 12-6-82??01-3045

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Roads small tools and equipmentAccount 12-6-69??01-3007Infrastructure and Community Services$10,000
Details & source

Source location: PDF p. 97; 12-6-69??01-3007

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Snowplow parts and blade replacementAccount 12-6-69??02-3007Infrastructure and Community Services$20,000
Details & source

Source location: PDF p. 97; 12-6-69??02-3007

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

Tavistock Spray Pad donor recognition carryforwardAccount 12-6-612402-3170Infrastructure and Community Services$7,623
Details & source

Source location: PDF p. 97; 12-6-612402-3170

Open the source record
  1. 2026 budget package, revised March 11 Complete 111-page package; individual PDF pages/account codes in rows

    Township of East Zorra Tavistock · Published 2026-03-11 · Event/reporting date 2026-03-11

    supporting detailed schedules; final totals controlled by 2026-10 · Primary record verified · Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

From an allocation to a result

East Zorra-Tavistock · Roads & bridges

Box Culvert 2015 replacement construction

Box Culvert 2015 replacement construction

East Zorra-Tavistock

2026 funding approved · completion unconfirmed
2026 allocation
$600,000
Next target
No next date listed
Latest update
2026-04-01 · Annual allocation adopted

East Zorra-Tavistock · Roads & bridges

Fuhr Street reconstruction: Township share

Fuhr Street reconstruction: Township share

East Zorra-Tavistock

Substantial performance certified July 29; final acceptance and final cost unverified
2026 allocation
$627,300
Named supplier
Elgin Construction Company Limited
Next target
No next date listed
Latest update
2026-07-29 · Substantial performance certified

East Zorra-Tavistock · Roads & bridges

Bridge 5 demobilization costs carried into 2026

Bridge 5 demobilization costs carried into 2026

East Zorra-Tavistock

2026 funding approved · completion unconfirmed
Original budget
$2,407,255
Next target
No next date listed
Latest update
2026-04-01 · Annual allocation adopted

East Zorra-Tavistock · Roads & bridges

William Street North top lift asphalt

William Street North top lift asphalt

East Zorra-Tavistock

2026 funding approved · completion unconfirmed
Original budget
$1,272,283
Next target
No next date listed
Latest update
2026-04-01 · Annual allocation adopted

East Zorra-Tavistock · Other projects

Replace 2020 Chevrolet Silverado

Replace 2020 Chevrolet Silverado

East Zorra-Tavistock

2026 funding approved · completion unconfirmed
2026 allocation
$53,060
Next target
No next date listed
Latest update
2026-04-01 · Annual allocation adopted

East Zorra-Tavistock · Vehicles & equipment

Firefighting equipment, $20,000 per station

Firefighting equipment, $20,000 per station

East Zorra-Tavistock

2026 funding approved · completion unconfirmed
2026 allocation
$60,000
Next target
No next date listed
Latest update
2026-04-01 · Annual allocation adopted
Explore all projects