What do these money figures mean?
Budget Planned costs for a stated year or project.
Annual allocation Funding assigned for one year. It may be part of a larger project.
Lifetime project budget The stated budget for the full project across its years.
Forecast An estimate of the eventual cost, as of the date shown.
Tax requirement (levy) The amount to raise from property taxes, after other funding.
Contract award The accepted contract price, with its stated tax and scope.
Recorded costs or payments Amounts reported for the period shown. They do not establish project completion. County spending and County taxes explained →
These are East Zorra-Tavistock’s finances. County finances are separate . See County projects located here .
adopted capital 2026 capital financing schedule 2026 capital financing schedule sources of capital financing · 2026 · CAD · As reported in source; no HST conversion inferred
Original approved $5,154,992
Revised authorization Not established
Reported actual Not established No reporting cutoff established
Published forecast Not established
Does the breakdown add up? Source total $5,154,992 Covered on the stated basis $5,154,992 Reconciled difference $0
Only parentless rows included; account children are not added again.
Definitions, changes & interpretation Published financing total $5,154,992 is $1 less than published capital expenditure total $5,154,993. Not silently changed. Open the source record By-law 2026-10: adopted estimates and tax rates Sections 1–4; Schedules A and C, PDF pp. 1–5 Township of East Zorra Tavistock · Published 2026-04-01 · Event/reporting date 2026-04-01
adopted · Primary record verified · Schedule C expenditures and financing differ by $1 in the original.
From an allocation to a result East Zorra-Tavistock · Roads & bridges
Box Culvert 2015 replacement construction
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
2026 allocation $600,000
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → East Zorra-Tavistock · Roads & bridges
Fuhr Street reconstruction: Township share
East Zorra-Tavistock
Substantial performance certified July 29; final acceptance and final cost unverified
2026 allocation $627,300
Named supplier Elgin Construction Company Limited
Next target No next date listed
Latest update 2026-07-29 · Substantial performance certified Open project → East Zorra-Tavistock · Roads & bridges
Bridge 5 demobilization costs carried into 2026
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
Original budget $2,407,255
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → East Zorra-Tavistock · Roads & bridges
William Street North top lift asphalt
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
Original budget $1,272,283
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → East Zorra-Tavistock · Other projects
Replace 2020 Chevrolet Silverado
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
2026 allocation $53,060
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → East Zorra-Tavistock · Vehicles & equipment
Firefighting equipment, $20,000 per station
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
2026 allocation $60,000
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → Explore all projects Copy this view Print