What do these money figures mean?
Budget Planned costs for a stated year or project.
Annual allocation Funding assigned for one year. It may be part of a larger project.
Lifetime project budget The stated budget for the full project across its years.
Forecast An estimate of the eventual cost, as of the date shown.
Tax requirement (levy) The amount to raise from property taxes, after other funding.
Contract award The accepted contract price, with its stated tax and scope.
Recorded costs or payments Amounts reported for the period shown. They do not establish project completion. County spending and County taxes explained →
These are East Zorra-Tavistock’s finances. County finances are separate . See County projects located here .
audited annual accounts 2025 audited consolidated expenses 2025 audited consolidated expenses PSAB accrued expense · 2025 · CAD · As reported in source; no HST conversion inferred
Original approved $8,690,684
Revised authorization Not established
Reported actual $11,212,180 Through 2025-12-31
Published forecast Not established
Actual revenue $11,662,345 Net levy / subsidy Not established
Does the breakdown add up? Source total $8,690,684 Covered on the stated basis $8,690,684 Reconciled difference $0
Only parentless rows included; account children are not added again.
Definitions, changes & interpretation Revenue $11,662,345 before other capital/developer/ERTH/disposal items. Annual surplus $1,906,346. Budget omits amortization in cash-basis preparation; compare audited budget carefully. Capital acquisitions $5,045,940 are not the same as PSAB expense. Open the source record 2025 audited consolidated financial statements PDF pp. 5–7, 13–15; notes 7–9 Township of East Zorra Tavistock · Published 2026-06-03 · Event/reporting date 2026-06-03
audited · Primary record verified · Unmodified audit opinion; financial position and operations at December 31, 2025.
What is the total made of? Download these rows · CSV 6 matching accounts. Parent totals include the indented accounts. — means no published amount.
Allocation by service East Zorra-Tavistock · 2025 · PSAB accrued expense · original
Protection $2,651,197 Transportation $2,404,688 General government $1,673,004 Recreation and cultural $1,483,870 Planning and development $473,925 Health $4,000 CAD · Largest 6 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below. Open the source record 2025 audited consolidated financial statements PDF pp. 5–7, 13–15; notes 7–9 Township of East Zorra Tavistock · Published 2026-06-03 · Event/reporting date 2026-06-03
audited · Primary record verified · Unmodified audit opinion; financial position and operations at December 31, 2025.
From an allocation to a result East Zorra-Tavistock · Roads & bridges
Box Culvert 2015 replacement construction
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
2026 allocation $600,000
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → East Zorra-Tavistock · Roads & bridges
Fuhr Street reconstruction: Township share
East Zorra-Tavistock
Substantial performance certified July 29; final acceptance and final cost unverified
2026 allocation $627,300
Named supplier Elgin Construction Company Limited
Next target No next date listed
Latest update 2026-07-29 · Substantial performance certified Open project → East Zorra-Tavistock · Roads & bridges
Bridge 5 demobilization costs carried into 2026
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
Original budget $2,407,255
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → East Zorra-Tavistock · Roads & bridges
William Street North top lift asphalt
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
Original budget $1,272,283
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → East Zorra-Tavistock · Other projects
Replace 2020 Chevrolet Silverado
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
2026 allocation $53,060
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → East Zorra-Tavistock · Vehicles & equipment
Firefighting equipment, $20,000 per station
East Zorra-Tavistock
2026 funding approved · completion unconfirmed
2026 allocation $60,000
Next target No next date listed
Latest update 2026-04-01 · Annual allocation adopted Open project → Explore all projects Copy this view Print