The published bid does not establish the final executed contract value. Bid excludes HST. Staff recommended construction amount $2,790,405 includes non-refundable HST.
Do not map the recommended $2,790,405 to awardAmount without the adoption/award resolution; contractor retention is verified by Town construction notice.
No savings claimed: full final costs and the approved revised appropriation are not available in opened records. Report’s alternative material offer is not treated as selected.
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Recommends construction $2,790,405 net non-refundable HST plus Planmac $166,327 plus contingency $295,673. $3,252,404 total is a recommended forecast, not verified final expenditure or council-approved revised appropriation.
Updated schedule and cost responsibility paragraphs
Evidence notes
Mid-March target revised to first week May 2026 due to structural supplier production. Additional crane/remobilization costs assigned to contractor and supplier. Does not establish project completion.
Opening paragraph; reconstruction description; Project at a glance
Evidence notes
First-party bridge supplier account. Owner Town of Tillsonburg, contractor Lancoa and consultant Planmac identified. Supplier narrative about savings is not a final municipal cost certificate.
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.
Why are there different County totals?
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.