Award / contractAmount not publishedLancoa Contracting Inc.
Recorded paymentsAmount not publishedNo payment amounts attached
Bid excludes HST. Staff recommended construction amount $2,790,405 includes non-refundable HST. · Bid, award and payment are separate measures. A bid is not the final executed contract value.Sources for these figures · 2
Do not map the recommended $2,790,405 to awardAmount without the adoption/award resolution; contractor retention is verified by Town construction notice.
Town of Tillsonburg · Published 2025-06-16 · Event/reporting date 2025-06-16
staff recommendation; contractor engagement separately confirmed · Primary record verified · Recommends construction $2,790,405 net non-refundable HST plus Planmac $166,327 plus contingency $295,673. $3,252,404 total is a recommended forecast, not verified final expenditure or council-approved revised appropriation.
Town of Tillsonburg · Published 2025-07-16 · Event/reporting date 2025-07-16
· Primary record verified · Names Lancoa Contracting Inc. as retained contractor. Closure window August 5–December 18, 2025 is not a final completion certificate.
The replacement Kinsmen pedestrian bridge and adjoining Veterans Memorial Walkway reopened July 2, 2026.
Tillsonburg
Open to the public
Original whole-project baseline established separately
$4,690,000
Named supplier
Lancoa Contracting Inc.
Next target
No next date listed
Latest update
2026-07-02 · Bridge and walkway reopened
Open project →
What still needs an answer
Make sense of the money+
Your taxes called. They’d like a receipt.
Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.
Why are there different County totals?
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
The budget hub retains an earlier $406.1 million headline. Spending explanations here use the detailed approved schedule.