Fuhr Street reconstruction: Township share
270 m road; 160 m storm sewer; 165 m watermain including services; 260 m sanitary sewer and laterals; 260 m sidewalk. Township budget is its $627,300 share, not necessarily the entire multi-utility contract.
Project 12-6-692604-4005
Budget authority
Approves annual allocation; delivery and contract authority must be traced separately.
Sources for this record: [1]
Contractor
Named in signed Form 9 certificate.
Sources for this record: [3]
Payment certifier
Certified substantial performance July 29, 2026.
Sources for this record: [3]
Latest spending total not published here.
Substantial performance is not final acceptance or a final payment statement.
Sources for this record: [3]
EZT-RFT-26-01 · Contractor verified by substantial-performance certificate; award value unavailable
Elgin Construction Company Limited
Not stated
Tender closed March 25. Supplier established by signed certificate, not by inference from a lowest bid.
Sources for this record: [2] [3]
Open procurement recordNo separate decision record is linked. Approval details may appear in the timeline or source documents.
Substantial performance certified July 29; final acceptance and final cost unverified. Completion or reopening of this scope does not establish final acceptance, final project cost or payment.
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: east-zorra-tavistock-budget-details
Source ID: east-zorra-tavistock-fuhr-tender
Source ID: east-zorra-tavistock-fuhr-certificate
Your taxes called. They’d like a receipt.
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.
Detailed approved budget ↗ · County budget hub ↗