Oxford County · Project

Fuhr Street reconstruction: Township share

Money & projects Explore sections
East Zorra-Tavistock projectView East Zorra-Tavistock project page →

At a glance

Location
East Zorra-Tavistock
Responsible authority
East Zorra-Tavistock
Current stage
Substantial performance certified July 29; final acceptance and final cost unverifiedAs of 2026-07-29
2026 allocation
$627,300
Next target
No next date listed
Named supplier
Elgin Construction Company Limited See contract details

Fuhr Street reconstruction: Township share

270 m road; 160 m storm sewer; 165 m watermain including services; 260 m sanitary sewer and laterals; 260 m sidewalk. Township budget is its $627,300 share, not necessarily the entire multi-utility contract.

Project 12-6-692604-4005

Who approves and delivers this project?

Budget authority

Township Council

Approves annual allocation; delivery and contract authority must be traced separately.

Contractor

Elgin Construction Company Limited

Named in signed Form 9 certificate.

Payment certifier

K. Smart Associates Limited

Certified substantial performance July 29, 2026.

Money

Project money

Annual allocation

2026 allocation
$627,300
2026 annual capital allocation; not a final contract or lifetime cost

Latest spending total not published here.

CAD · Source budget basis; HST treatment not separately stated · 2026 annual capital allocation; not a final contract or lifetime cost

Timeline

  1. completion

    Substantial performance certified

    Substantial performance is not final acceptance or a final payment statement.

Contracts

EZT-RFT-26-01 · Contractor verified by substantial-performance certificate; award value unavailable

Fuhr Street reconstruction

Elgin Construction Company Limited

Published bid
Not established
Published award / contract value
Not established
Unit price
Not established

Not stated

Tender closed March 25. Supplier established by signed certificate, not by inference from a lowest bid.

Open procurement record

Decisions

No separate decision record is linked. Approval details may appear in the timeline or source documents.

Outcomes

Substantial performance certified July 29; final acceptance and final cost unverified. Completion or reopening of this scope does not establish final acceptance, final project cost or payment.

Questions

  • What is the latest committed cost, spending to date and completion milestone?
Scope & interpretation notes
  • Allocation in detailed capital schedule, PDF p. 98; later-year forecasts are excluded.

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. 2026 budget package, revised March 11

    Source ID: east-zorra-tavistock-budget-details

    Publisher
    Township of East Zorra Tavistock
    Published
    2026-03-11
    Event / reporting date
    2026-03-11
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    supporting detailed schedules; final totals controlled by 2026-10
    Passage / page
    Complete 111-page package; individual PDF pages/account codes in rows
    Evidence notes
    Opened full 11,959,726-byte original and extracted text. Supporting schedules retain proposed labels; adoption by-law controls the final levy. Draft Schedule A1 uses $8,678,778 tax levy and does not balance to the final requirement; do not publish this draft revenue figure as the adopted levy.

    Open in source library

  2. Fuhr Street reconstruction RFT

    Source ID: east-zorra-tavistock-fuhr-tender

    Publisher
    Township of East Zorra Tavistock
    Published
    2026-03-09
    Event / reporting date
    2026-03-09
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published
    Passage / page
    Bid details; closing March 25
    Evidence notes
    Portal status Closed does not establish award value.

    Open in source library

  3. Fuhr Street Form 9 certificate of substantial performance

    Source ID: east-zorra-tavistock-fuhr-certificate

    Publisher
    K. Smart Associates Limited / Township of East Zorra-Tavistock
    Published
    2026-07-29
    Event / reporting date
    2026-07-29
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published
    Passage / page
    PDF p. 1; Form 9

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

Why are there different County totals?

The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.

Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.

Detailed approved budget ↗ · County budget hub ↗