New six-bay fire hall: Abcott construction bid accepted for $2,563,087 before HST; $2,177,836.30 costs incurred in 2025. Substantial performance certified May 12, 2026.
9,738-square-foot, six-bay fire hall at 707024 Township Road 2.
Who approves and delivers this project?
Municipal authority
Township of Blandford-Blenheim
Budget and municipal project owner; contractor/individual decisions require separate records.
No invoice-level payments extracted. 2025 project costs in annual DC report include whole-project funding and cannot be assigned wholesale as contractor payment.
Substantially performed; final financial closeout not extracted. Completion or reopening of this scope does not establish final acceptance, final project cost or payment.
Questions
What final approved budget and paid-to-date are recorded in CAO 26-25?
When was the planned $2m debenture issued, at what rate, and how much future DC funding is committed?
Construction award differs from whole-project cost. The 2025 DC report schedules $2m debt upon completion; later 2026 closeout/debenture report was located but inaccessible.
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
PDF pp.1–2 narrative, p.4 reserve movement, p.5 project costs and funding
Evidence notes
For April 1 Council. Narrative opening DC balance $205,763.27 conflicts with table $205,763.67 by $0.40; table balance reconciles. Header report number Financial Services 2026-03 while recommendation TR-26-05. Project figures are 2025 costs, not lifetime final totals.
Contains primary Fire Hall and grader award decisions, tandem truck procurement authority, Drumbo OTF funding report and drainage debenture recommendation. Do not treat recommendations as adopted decisions.
Council expenditure authorization reported by municipality
Passage / page
Protective Services: FC-25-16
Evidence notes
$122,000 2025 fire-station expenditures funded from Fire Reserve. This is not necessarily a $122,000 contractor change order or complete project-budget amendment.
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.
Why are there different County totals?
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
Earlier budget material used a $406.1 million headline. Spending explanations here use the detailed approved schedule.