Award / contract$2,563,087Abcott Construction Ltd. · 2025-08-06
Recorded paymentsAmount not publishedNo payment amounts attached
Excluding HST · Bid, award and payment are separate measures.
No invoice-level payments extracted. 2025 project costs in annual DC report include whole-project funding and cannot be assigned wholesale as contractor payment.
Township of Blandford-Blenheim · Published 2025-09-03 · Event/reporting date 2025-09-03
Minutes record carried decisions; staff reports separately recommendations · Primary record verified · Contains primary Fire Hall and grader award decisions, tandem truck procurement authority, Drumbo OTF funding report and drainage debenture recommendation. Do not treat recommendations as adopted decisions.
New six-bay fire hall: Abcott construction bid accepted for $2,563,087 before HST; $2,177,836.30 costs incurred in 2025. Substantial performance certified May 12, 2026.
Blandford-Blenheim · Princeton Fire Station 81
Substantially performed; final financial closeout not extracted
2026 allocation
Not established
Named supplier
Abcott Construction Ltd.
Next target
No next date listed
Latest update
2026-05-12 · Substantial performance
Open project →
What still needs an answer
Make sense of the money+
Your taxes called. They’d like a receipt.
Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.
Why are there different County totals?
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
The budget hub retains an earlier $406.1 million headline. Spending explanations here use the detailed approved schedule.