Township of Zorra · Published 2026-05-13 · Event/reporting date 2026-05-13
published · Primary record verified · Portal shows awarded status; accessible bid summary shows Van Roestel total, while dynamic award-vendor rows were not exposed. Tax basis not given in accessible summary.
Courts will sit on donated parkland off Brock Street near the George Street extension, beside the planned school.
Zorra
Awarded; construction awaits development infrastructure
2026 allocation
$305,827
Next target
No next date listed
Latest update
2025-12-03 · Annual allocation adopted
Open project →
What still needs an answer
Where are the executed agreement, changes and final payment record?
Make sense of the money+
Your taxes called. They’d like a receipt.
Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.
Why are there different County totals?
The detailed 2026 budget lists $279,035,275 in operating expenses and $127,855,640 in financed capital: $406,890,915 combined. The $103,039,171 property-tax requirement is a different measure, after other funding.
The budget hub retains an earlier $406.1 million headline. Spending explanations here use the detailed approved schedule.