Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.
Bridge 640, 25th Line, Meathrell Creek
Who approves and delivers this project?
Budget authority
Township Council
Approves annual allocation; delivery and contract authority must be traced separately.
Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24. Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.
No separate decision record is linked. Approval details may appear in the timeline or source documents.
Outcomes
Road 92 and 25th Line reopened in the first week of September after paving, shouldering and line painting. John Meathrell Bridge rehabilitation finished July 24.
Questions
What is the latest committed cost, spending to date and completion milestone?
Joint bridge funded 50/50 with South-West Oxford; Zorra invoices partner. Gross contract is not Zorra-only net cost.
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Report header says April 15, approval April 30; May 6 Council agenda receives it. Event date uses Council receipt; inconsistent header retained in note.
pp. 1–2; paired with carried resolution 07-08-2026
Evidence notes
Bridge 140 amount includes contingency and non-rebatable HST. Do not confuse joint bid $258,664 before HST with Bridge 140 award authorization $224,072.69 after HST rebate.
Primary-source body reviewed in the October 30 audit Historical completion, not a new October 30 reopening. John Meathrell is shared with South-West Oxford.